Round 1 - Technical 

(2 Questions)

  • Q1. Baselines in Primavera?
  • Ans. 

    Baselines in Primavera are snapshots of the project schedule at a specific point in time, used for comparison and tracking progress.

    • Baselines capture the original project plan before any changes are made.

    • They are used as a reference point to compare actual progress against planned progress.

    • Baselines help in identifying deviations from the original plan and taking corrective actions.

    • In Primavera, baselines can be create...

  • Answered by AI
  • Q2. How to track a project on daily basis in Primavera P6
  • Ans. 

    To track a project in Primavera P6 on a daily basis, use the following steps.

    • Update progress for each activity daily

    • Review critical path activities regularly

    • Monitor resource allocation and availability

    • Compare planned vs. actual progress

    • Generate daily reports for stakeholders

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Work culture is good. But priority is given to people from south mostly.

I applied via Walk-in and was interviewed in Jan 2022. There were 2 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - Technical 

(2 Questions)

  • Q1. As pr job regarding , we are working on WBS and AEC also
  • Q2. On basis of construction for civil engineer

Interview Preparation Tips

Interview preparation tips for other job seekers - We working on WBS and ACE for civil construction

Planning Engineer Interview Questions Asked at Other Companies

Q1. Prepare a small given example site schedule with sequencing and d ... read more
Q2. What is CPI & SPI how to do that how to load resources into t ... read more
Q3. What software using for planning? How much proficiency you have o ... read more
Q4. what is clim digger function? How much total float is allowed in ... read more
asked in KPMG India
Q5. Productivity of workers and how to calculate task duration from t ... read more

Planning Engineer Jobs at Nagarjuna Construction Company

View all

Interview questions from similar companies

Interview experience
4
Good
Difficulty level
Easy
Process Duration
-
Result
-
Round 1 - Technical 

(2 Questions)

  • Q1. What is your favourite subject
  • Q2. Depends on you it can be any.

Interview Preparation Tips

Interview preparation tips for other job seekers - Stay calm and answer genuinely
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Technical 

(1 Question)

  • Q1. WBS of highway and structure
  • Ans. 

    WBS stands for Work Breakdown Structure, which is a hierarchical decomposition of the total scope of work to be carried out by the project team.

    • WBS for a highway project would include major components like earthwork, pavement, drainage, signage, lighting, etc.

    • WBS for a structure project would include components like foundation, superstructure, finishes, MEP (mechanical, electrical, plumbing), etc.

    • Each major component i...

  • Answered by AI
Interview experience
4
Good
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Technical 

(1 Question)

  • Q1. What is S- Curv in Primavera ?
  • Ans. 

    S-Curve in Primavera is a graphical representation of project progress over time.

    • S-Curve shows the planned and actual progress of a project.

    • It helps in visualizing the project's performance and identifying any deviations from the plan.

    • The curve is shaped like an 'S' due to the gradual increase in progress at the beginning and end, with a steeper slope in the middle.

    • The x-axis represents time, and the y-axis represents ...

  • Answered by AI
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - HR 

(1 Question)

  • Q1. What is which you are looking for in our organisation.

Interview Preparation Tips

Interview preparation tips for other job seekers - Be crisp to your answer and tell the truth what is correct rest will be taken care
Interview experience
3
Average
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Naukri.com and was interviewed in May 2023. There were 3 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - HR 

(1 Question)

  • Q1. Why do you want to leave your previous company
Round 3 - Technical 

(2 Questions)

  • Q1. Free float vs Total Float
  • Ans. 

    Free float is the amount of time an activity can be delayed without delaying the project, while total float is the amount of time an activity can be delayed without delaying the successor activity.

    • Free float is specific to an activity, while total float is related to the entire project schedule.

    • Free float is calculated by subtracting the early start of the activity from the early start of the successor activity, while ...

  • Answered by AI
  • Q2. Time limited vs resource limited
  • Ans. 

    Time limited projects have fixed deadlines while resource limited projects have fixed resources.

    • Time limited projects require completion by a specific deadline.

    • Resource limited projects have a fixed amount of resources available.

    • Balancing time and resources is crucial for project success.

    • Example: A construction project with a deadline to finish before winter (time limited) vs a project with a fixed budget (resource lim

  • Answered by AI

Skills evaluated in this interview

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Don’t add your photo or details such as gender, age, and address in your resume. These details do not add any value.
View all tips
Round 2 - Technical 

(3 Questions)

  • Q1. Highway Civil Eng tecnical question
  • Q2. Billing / planning question
  • Q3. Site Question in Highway
Round 3 - Aptitude Test 

Interview Preparation Tips

Interview preparation tips for other job seekers - Kanpur job requirements & Locknow required
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Approached by Company and was interviewed before Feb 2023. There was 1 interview round.

Round 1 - Technical 

(1 Question)

  • Q1. Manager will ask practical experience on work
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Properly align and format text in your resume. A recruiter will have to spend more time reading poorly aligned text, leading to high chances of rejection.
View all tips
Round 2 - Technical 

(1 Question)

  • Q1. Basic question related your previous work

Interview Preparation Tips

Interview preparation tips for other job seekers - Preparation should on as per your previous work

Nagarjuna Construction Company Interview FAQs

How many rounds are there in Nagarjuna Construction Company Planning Engineer interview?
Nagarjuna Construction Company interview process usually has 1-2 rounds. The most common rounds in the Nagarjuna Construction Company interview process are Technical and Resume Shortlist.
How to prepare for Nagarjuna Construction Company Planning Engineer interview?
Go through your CV in detail and study all the technologies mentioned in your CV. Prepare at least two technologies or languages in depth if you are appearing for a technical interview at Nagarjuna Construction Company. The most common topics and skills that interviewers at Nagarjuna Construction Company expect are Resource Planning, Planning, Primavera, MSP and Urban Planning.
What are the top questions asked in Nagarjuna Construction Company Planning Engineer interview?

Some of the top questions asked at the Nagarjuna Construction Company Planning Engineer interview -

  1. How to track a project on daily basis in Primavera...read more
  2. Baselines in Primave...read more
  3. As pr job regarding , we are working on WBS and AEC a...read more

Tell us how to improve this page.

Nagarjuna Construction Company Planning Engineer Interview Process

based on 1 interview

Interview experience

5
  
Excellent
View more
Nagarjuna Construction Company Planning Engineer Salary
based on 27 salaries
₹3.4 L/yr - ₹8 L/yr
29% less than the average Planning Engineer Salary in India
View more details

Nagarjuna Construction Company Planning Engineer Reviews and Ratings

based on 13 reviews

4.0/5

Rating in categories

3.3

Skill development

3.1

Work-life balance

3.6

Salary

4.0

Job security

3.0

Company culture

3.4

Promotions

3.3

Work satisfaction

Explore 13 Reviews and Ratings
Junior Engineer
877 salaries
unlock blur

₹1.8 L/yr - ₹5.8 L/yr

Assistant Engineer
790 salaries
unlock blur

₹3 L/yr - ₹9 L/yr

Junior Engineer Civil
459 salaries
unlock blur

₹1.8 L/yr - ₹6.5 L/yr

Senior Engineer
359 salaries
unlock blur

₹4 L/yr - ₹11 L/yr

Civil Site Engineer
257 salaries
unlock blur

₹1.9 L/yr - ₹7 L/yr

Explore more salaries
Compare Nagarjuna Construction Company with

Larsen & Toubro Limited

4.0
Compare

TCS

3.7
Compare

BHEL

4.1
Compare

Infosys

3.6
Compare
Did you find this page helpful?
Yes No
write
Share an Interview