I applied via Walk-in and was interviewed before Mar 2022. There were 4 interview rounds.
Answering questions related to Planning Engineer role
Prepare a site schedule with sequencing and duration to determine project duration in MSP/on paper
Critical Path Method (CPM) is a project management technique to identify the longest path of planned activities to determine the shortest possible project duration
To identify critical path on paper, draw a network diagram and calculate the earliest start and finish times...
Top trending discussions
I applied via Approached by Company and was interviewed in Jan 2024. There were 2 interview rounds.
The shape of project progress curve is typically an S-curve.
The project progress curve starts off slow as the project is initiated and planned.
It then accelerates as work is being executed and completed.
Finally, the curve levels off as the project nears completion and final tasks are finished.
The S-curve represents the typical pattern of project progress over time.
posted on 5 Jun 2024
Optimistic costing involves estimating project costs on the lower end of the spectrum.
Identify all potential cost-saving measures and efficiencies in the project plan.
Use historical data and benchmarks to estimate costs on the lower side.
Consider best-case scenarios and optimistic assumptions when estimating costs.
Collaborate with stakeholders to gather insights and input on cost-saving opportunities.
Regularly review a...
posted on 13 Sep 2022
I applied via Naukri.com and was interviewed in Aug 2022. There were 2 interview rounds.
based on 11 reviews
Rating in categories
Planning Engineer
33
salaries
| ₹3 L/yr - ₹9 L/yr |
Safety Officer
30
salaries
| ₹1.5 L/yr - ₹4.5 L/yr |
Junior Engineer Civil
18
salaries
| ₹1.2 L/yr - ₹3.5 L/yr |
Junior Engineer
17
salaries
| ₹1.8 L/yr - ₹4.8 L/yr |
Senior Engineer
17
salaries
| ₹4 L/yr - ₹7.4 L/yr |
Larsen & Toubro Limited
TCS
Hindustan Construction Company
BHEL