Filter interviews by
Clear (1)
I applied via Naukri.com and was interviewed in Apr 2023. There were 3 interview rounds.
Process of variation involves documenting and analyzing changes in project scope, cost, or schedule.
Variations are changes to the original scope, cost, or schedule of a project
Variations must be documented and approved by the relevant parties
The impact of variations on project budget and timeline must be analyzed
Examples of variations include design changes, unforeseen site conditions, and client requests
Top trending discussions
I applied via Recruitment Consulltant and was interviewed before May 2022. There were 3 interview rounds.
I applied via Referral and was interviewed before Mar 2022. There were 2 interview rounds.
Developed a unique algorithm to optimize data processing in a large-scale distributed system.
Identified a bottleneck in the system's data processing pipeline
Implemented a parallel processing approach to distribute the workload across multiple nodes
Utilized a combination of caching and pre-processing techniques to reduce computational overhead
Achieved a significant improvement in overall system performance and reduced p
Yes
Yes, I have received constructive criticism on my work assignments.
I always view constructive criticism as an opportunity for growth and improvement.
I actively listen to the feedback provided and take notes to ensure I understand the areas that need improvement.
I analyze the criticism objectively and identify areas where I can make adjustments or implement changes.
I seek clarification if needed and ask for specific ...
I have extensive experience interfacing with clients both directly and indirectly.
I have worked as a Senior Engineer for the past five years, where I have regularly interacted with clients.
I have directly communicated with clients to gather requirements, provide updates, and address any concerns or issues.
I have also indirectly interfaced with clients through project managers and business analysts, ensuring their needs...
Yes, I have experience dealing with treatment plant equipment such as screens, grit, macerator, and sludge handling equipment.
I have worked on various projects involving the installation and maintenance of treatment plant equipment.
I am familiar with the operation and troubleshooting of screens used for removing large debris from wastewater.
I have experience with grit removal systems that separate sand, gravel, and oth...
Yes
Implemented a new Agile methodology to improve team productivity
Introduced a knowledge sharing platform to encourage continuous learning
Implemented a mentorship program to foster professional growth
Introduced automated testing tools to improve software quality
posted on 23 Aug 2023
Response Surface Methodology (RSM) is a statistical technique used to model and analyze the relationship between a response variable and multiple input variables.
Design a set of experiments based on a factorial design
Collect data from the experiments
Fit a regression model to the data
Analyze the model to determine optimal input settings for the response variable
I applied via Approached by Company and was interviewed before Mar 2022. There were 3 interview rounds.
It depends on the region, for me they conducted tool test in the 1st round.
I was interviewed in May 2023.
Bus bar schemes are different ways of connecting bus bars in power systems.
Single bus bar scheme
Double bus bar scheme
Main and transfer bus bar scheme
Ring bus bar scheme
Breaker and a half scheme
Mesh bus bar scheme
The equipment sequence for any line bay starts with the circuit breaker and ends with the transformer.
The circuit breaker is the first equipment in the sequence.
Next comes the isolator switch.
After that, the earth switch is operated.
Then the line disconnector is opened.
Finally, the transformer is disconnected from the line.
The sequence is reversed when the line bay is put back into service.
I applied via Company Website and was interviewed before Jan 2022. There were 3 interview rounds.
based on 1 interview
Interview experience
based on 1 review
Rating in categories
Civil Inspector
18
salaries
| ₹0 L/yr - ₹0 L/yr |
Site Engineer
18
salaries
| ₹0 L/yr - ₹0 L/yr |
Section Engineer
17
salaries
| ₹0 L/yr - ₹0 L/yr |
Resident Engineer
13
salaries
| ₹0 L/yr - ₹0 L/yr |
Bridge Design Engineer
13
salaries
| ₹0 L/yr - ₹0 L/yr |
AECOM
Jacobs Engineering Group
Bechtel
Fluor Corporation