WBS stands for Work Breakdown Structure, which is a hierarchical decomposition of the total scope of work to be carried out by the project team.
WBS for a highway project would include major components like earthwork, pavement, drainage, signage, lighting, etc.
WBS for a structure project would include components like foundation, superstructure, finishes, MEP (mechanical, electrical, plumbing), etc.
Each major component i...
Top trending discussions
posted on 11 Aug 2024
Baselines in Primavera are snapshots of the project schedule at a specific point in time, used for comparison and tracking progress.
Baselines capture the original project plan before any changes are made.
They are used as a reference point to compare actual progress against planned progress.
Baselines help in identifying deviations from the original plan and taking corrective actions.
In Primavera, baselines can be create...
To track a project in Primavera P6 on a daily basis, use the following steps.
Update progress for each activity daily
Review critical path activities regularly
Monitor resource allocation and availability
Compare planned vs. actual progress
Generate daily reports for stakeholders
posted on 13 Oct 2023
I applied via campus placement at National Institute of Technology (NIT), Jamshedpur and was interviewed in Sep 2023. There were 4 interview rounds.
The level of the exam was normal.
Quality of brick, cement, and SF & BMD diagram can be checked through visual inspection, testing, and comparison with standards.
Brick quality can be checked by inspecting for uniform size, shape, and color, and conducting water absorption test.
Cement quality can be checked by performing tests like fineness test, setting time test, and compressive strength test.
SF & BMD diagram quality can be checked by verifying accura...
S-Curve in Primavera is a graphical representation of project progress over time.
S-Curve shows the planned and actual progress of a project.
It helps in visualizing the project's performance and identifying any deviations from the plan.
The curve is shaped like an 'S' due to the gradual increase in progress at the beginning and end, with a steeper slope in the middle.
The x-axis represents time, and the y-axis represents ...
I applied via Referral and was interviewed in Mar 2023. There were 4 interview rounds.
Yes, I have experience in scheduling.
I have worked on scheduling projects using software such as Primavera P6 and Microsoft Project.
I am familiar with creating and updating project schedules, resource allocation, and critical path analysis.
I have also worked on schedule risk analysis and mitigation planning.
I understand the importance of accurate scheduling in project management and strive to ensure that schedules are
posted on 9 Feb 2024
I applied via Approached by Company and was interviewed before Feb 2023. There was 1 interview round.
posted on 27 Feb 2022
I applied via Walk-in and was interviewed in Jan 2022. There were 2 interview rounds.
based on 2 reviews
Rating in categories
Assistant Manager
386
salaries
| ₹4.6 L/yr - ₹11.5 L/yr |
Senior Engineer
223
salaries
| ₹3.6 L/yr - ₹8.9 L/yr |
Engineer
138
salaries
| ₹2 L/yr - ₹6.5 L/yr |
Senior Executive
131
salaries
| ₹3 L/yr - ₹8 L/yr |
Deputy Manager
126
salaries
| ₹6.6 L/yr - ₹17.5 L/yr |
Nagarjuna Construction Company
PNC Infratech
Ashoka Buildcon
IRB Infrastructure