Upload Button Icon Add office photos

Filter interviews by

Sj Contracts Senior Planning Engineer Interview Questions and Answers

Updated 30 Mar 2023

Sj Contracts Senior Planning Engineer Interview Experiences

1 interview found

Interview experience
4
Good
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Referral and was interviewed before Mar 2022. There were 2 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - One-on-one 

(4 Questions)

  • Q1. Discussion on work done in previous organizations?
  • Q2. Reporting to higher management
  • Q3. Solving situations that could arise on the work site
  • Q4. Delay analysis done for earlier projects
  • Ans. 

    I have conducted delay analysis for several earlier projects.

    • Used various delay analysis techniques such as As-Planned vs As-Built, Time Impact Analysis, Impacted As-Planned, etc.

    • Identified critical delays and their causes

    • Provided recommendations to mitigate delays in future projects

    • Examples: Delay analysis for construction of a hospital, delay analysis for a road project, delay analysis for a power plant project

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Generally, interviews will be completed in a single day. 50% of the questions will be technical and the balance will be personal such as family background, your life goals, etc. If you are selected, they will respond within a week.

Interview questions from similar companies

Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Technical 

(1 Question)

  • Q1. Detailed about last working experience, study, current role applied jd
Round 2 - HR 

(1 Question)

  • Q1. Basic HR round.
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
-
Result
Selected Selected

I was interviewed in Jul 2023.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - Technical 

(2 Questions)

  • Q1. What is Rolling Margin?
  • Ans. 

    Rolling Margin is the difference between the revenue generated and the variable costs incurred in a specific period.

    • Rolling Margin helps in determining the profitability of a product or service.

    • It is calculated by subtracting the variable costs from the revenue for a specific period.

    • For example, if a product generates $1000 in revenue and the variable costs are $300, the rolling margin would be $700.

    • It is important for...

  • Answered by AI
  • Q2. Manpower coefficient for Reinforcement, shuttering, Brickwork
  • Ans. 

    Manpower coefficient varies for different construction activities like reinforcement, shuttering, and brickwork.

    • Manpower coefficient is the ratio of total manpower required to complete a specific task.

    • It is influenced by factors like complexity of the task, skill level of workers, equipment availability, etc.

    • For example, reinforcement work may have a higher manpower coefficient compared to brickwork due to the intricat...

  • Answered by AI
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Aptitude Test 

General aptitude questions

Round 2 - Technical 

(2 Questions)

  • Q1. General technical
  • Q2. Deep Core technical questions
Round 3 - HR 

(1 Question)

  • Q1. Basic HR questions
Interview experience
4
Good
Difficulty level
-
Process Duration
-
Result
-
Round 1 - HR 

(2 Questions)

  • Q1. Tell me about yourself
  • Ans. 

    Experienced Planning Engineer with a background in civil engineering and a proven track record of successfully managing projects.

    • Bachelor's degree in Civil Engineering

    • 5+ years of experience in planning and managing construction projects

    • Proficient in project management software such as Primavera P6

    • Strong analytical and problem-solving skills

    • Excellent communication and teamwork abilities

  • Answered by AI
  • Q2. Where do you see yourself in 5 years
  • Ans. 

    In 5 years, I see myself as a senior Planning Engineer leading a team on major projects and contributing to the growth of the company.

    • Leading a team of planning engineers on major projects

    • Contributing to the growth and success of the company

    • Continuing to enhance my skills and knowledge in planning and project management

    • Possibly pursuing further certifications or advanced degrees in the field

  • Answered by AI
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Approached by Company and was interviewed in Oct 2023. There were 3 interview rounds.

Round 1 - Technical 

(2 Questions)

  • Q1. What is M4 in Planning
  • Ans. 

    M4 in Planning refers to a milestone that marks the completion of a significant phase or deliverable in a project schedule.

    • M4 is typically used in project management to signify a key point in the project timeline.

    • It is often associated with the completion of a major task or the achievement of an important project milestone.

    • M4 can help track progress, identify potential delays, and ensure that the project stays on sched...

  • Answered by AI
  • Q2. How will you provide detailed schedule of 300 km laying
  • Ans. 

    I will break down the 300 km laying project into smaller sections, assign resources, estimate durations, and create a detailed schedule.

    • Break down the project into manageable sections such as 10 km segments

    • Assign resources including equipment, manpower, and materials to each section

    • Estimate durations for each activity based on historical data or industry standards

    • Create a detailed schedule using a scheduling software l...

  • Answered by AI
Round 2 - HR 

(2 Questions)

  • Q1. Salary expectation
  • Q2. Reason of changing job
Round 3 - Case Study 

How will you provide schedule of WTP

Interview experience
4
Good
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Technical 

(2 Questions)

  • Q1. Primavera related questions
  • Q2. OBS , WBS, Planning & Billing
Interview experience
4
Good
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Walk-in and was interviewed in May 2023. There were 2 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Don’t add your photo or details such as gender, age, and address in your resume. These details do not add any value.
View all tips
Round 2 - Technical 

(2 Questions)

  • Q1. Deep technical question and checked the knowledge on terms written in the resume. also checking confidence by saying your answer is wrong even if you answer right.
  • Ans. Prepare all advance functions of primavera, resource loading and evm
  • Answered Anonymously
  • Q2. Wether you will work in contract or thrid party pay roll
  • Ans. If company contract ok but refuse if offering third party payroll
  • Answered Anonymously

Interview Preparation Tips

Interview preparation tips for other job seekers - keep your confidence level high they seek person having clear thoughts and confident
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
2-4 weeks
Result
Selected Selected

I applied via Approached by Company and was interviewed before Feb 2023. There was 1 interview round.

Round 1 - Technical 

(1 Question)

  • Q1. Related to Planning & contract management
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Technical 

(1 Question)

  • Q1. Detailed about last working experience, study, current role applied jd
Round 2 - HR 

(1 Question)

  • Q1. Basic HR round.

Sj Contracts Interview FAQs

How many rounds are there in Sj Contracts Senior Planning Engineer interview?
Sj Contracts interview process usually has 2 rounds. The most common rounds in the Sj Contracts interview process are Resume Shortlist and One-on-one Round.
How to prepare for Sj Contracts Senior Planning Engineer interview?
Go through your CV in detail and study all the technologies mentioned in your CV. Prepare at least two technologies or languages in depth if you are appearing for a technical interview at Sj Contracts. The most common topics and skills that interviewers at Sj Contracts expect are Scheduling, MS Project, MSP, Monitoring and Planning.
What are the top questions asked in Sj Contracts Senior Planning Engineer interview?

Some of the top questions asked at the Sj Contracts Senior Planning Engineer interview -

  1. Delay analysis done for earlier proje...read more
  2. Reporting to higher managem...read more

Tell us how to improve this page.

Interview Questions from Similar Companies

Apco Infratech Interview Questions
3.8
 • 111 Interviews
AECOM Interview Questions
4.3
 • 110 Interviews
Bechtel Interview Questions
4.0
 • 65 Interviews
Samsung E&A Interview Questions
4.1
 • 59 Interviews
Wood Group Interview Questions
3.7
 • 55 Interviews
View all
Sj Contracts Senior Planning Engineer Salary
based on 5 salaries
₹7.8 L/yr - ₹10 L/yr
At par with the average Senior Planning Engineer Salary in India
View more details

Sj Contracts Senior Planning Engineer Reviews and Ratings

based on 5 reviews

4.4/5

Rating in categories

4.3

Skill development

3.4

Work-life balance

4.3

Salary

4.5

Job security

4.1

Company culture

4.1

Promotions

3.5

Work satisfaction

Explore 5 Reviews and Ratings
Billing Engineer
73 salaries
unlock blur

₹2.8 L/yr - ₹7.8 L/yr

Senior Engineer
51 salaries
unlock blur

₹4.5 L/yr - ₹10.8 L/yr

Junior Engineer
51 salaries
unlock blur

₹1.5 L/yr - ₹5 L/yr

Planning Engineer
47 salaries
unlock blur

₹3.7 L/yr - ₹7.5 L/yr

Site Engineer
41 salaries
unlock blur

₹3.2 L/yr - ₹8 L/yr

Explore more salaries
Compare Sj Contracts with

L&T Energy Hydrocarbon

3.9
Compare

AECOM

4.3
Compare

Apco Infratech

3.8
Compare

Toyo Engineering

3.9
Compare
Did you find this page helpful?
Yes No