EOT proposal is a request for an extension of time in a construction project due to delays beyond the contractor's control.
EOT stands for Extension of Time.
It is a formal request made by the contractor to the client or project owner.
The request is usually accompanied by supporting documentation such as delay analysis reports, weather reports, and other relevant evidence.
EOT proposals are typically reviewed by the proje...
To plan 2 lacs Cum concrete in 1 year, calculate daily production target and number of RMC plants needed.
Calculate daily production target by dividing total volume by number of working days in a year
Determine the capacity of each RMC plant and divide the daily production target by it to find out how many plants are needed
Consider factors like downtime, maintenance, and transportation in your planning
posted on 20 Jan 2025
I applied via Naukri.com and was interviewed in Nov 2023. There were 2 interview rounds.
The planning initiation process involves defining the project scope, objectives, and deliverables.
Identify the need for planning
Define the project scope, objectives, and deliverables
Identify key stakeholders and their roles
Establish a project team
Develop a project charter or initiation document
Conduct a feasibility study
Identify risks and constraints
Define the planning timeline and milestones
The scheduling process involves considering durations in relation to productivity.
The scheduling process starts by identifying the tasks that need to be completed.
The duration of each task is estimated based on historical data or expert judgment.
Productivity levels are taken into account when determining the duration of tasks.
Factors such as employee skills, equipment availability, and potential bottlenecks are conside...
The productivity norms in planning management vary across industries and sites.
Productivity norms in planning management are specific to each industry and site.
These norms are determined based on factors such as the nature of work, resources available, and industry standards.
For example, in the manufacturing industry, the productivity norm for planning managers may be measured in terms of units produced per hour.
In the...
Trackers are prepared for site tracking and schedule upgradation.
Trackers are tools used to monitor and track progress on a site or project.
They help in keeping track of tasks, deadlines, and milestones.
Trackers can be in the form of spreadsheets, software, or project management tools.
They provide visibility into the status of various activities and help in identifying bottlenecks or delays.
Upgradation of schedules inv...
posted on 30 Jun 2023
I applied via Referral and was interviewed in May 2023. There was 1 interview round.
I applied via Company Website and was interviewed in Mar 2023. There were 2 interview rounds.
I applied via Approached by Company and was interviewed before Feb 2023. There was 1 interview round.
posted on 27 May 2022
I applied via Referral and was interviewed in Apr 2022. There was 1 interview round.
I applied via Naukri.com and was interviewed in Feb 2024. There were 2 interview rounds.
Project cost, bbs, agreement clause, critical activities, total float are key aspects of project planning and management.
Project cost refers to the total expenses incurred in completing a project.
BBS (Bill of Quantities) is a document used in construction projects to itemize the materials, parts, and labor required.
Agreement clause outlines the terms and conditions agreed upon by all parties involved in the project.
Cri...
posted on 2 Aug 2024
I applied via Company Website and was interviewed in Feb 2024. There was 1 interview round.
I am highly confident in my skills and abilities.
I have a strong track record of successfully managing planning projects in my previous roles.
I continuously seek opportunities to improve my skills through training and professional development.
I have received positive feedback from colleagues and supervisors on my performance and contributions.
I am confident in my ability to analyze data, develop strategies, and make in
Yes, I am ready to work 12 hours per day as an Assistant Planning Manager.
I am dedicated to my work and willing to put in the extra hours when needed
I understand the demands of the role and am prepared to meet them
I have experience working long hours in previous positions
based on 8 reviews
Rating in categories
Senior Engineer
887
salaries
| ₹3.2 L/yr - ₹11.5 L/yr |
Engineer
870
salaries
| ₹2.2 L/yr - ₹7 L/yr |
Associate Manager
509
salaries
| ₹4.8 L/yr - ₹15.2 L/yr |
Mechanical Engineer
410
salaries
| ₹2 L/yr - ₹7.1 L/yr |
Civil Engineer
352
salaries
| ₹2.2 L/yr - ₹8.2 L/yr |
Larsen & Toubro Limited
Tata Projects
GMR Group
Hindustan Construction Company