Round 1 - Technical 

(2 Questions)

  • Q1. Governor is control' by Turbine speed
  • Q2. By oppitimizi combustion fuel,to increase boiler Efficiency
Round 2 - Group Discussion 

As I am shift incharge ,i wanted technical knowledge

Round 3 - Case Study 

Very interesting knowledge Questions should ask for interview

Utility Manager Interview Questions asked at other Companies

Q1. How many chillers you have handed with what capacity
View answer (3)
Interview experience
4
Good
Difficulty level
Easy
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Recruitment Consulltant and was interviewed in Oct 2024. There were 2 interview rounds.

Round 1 - One-on-one 

(2 Questions)

  • Q1. What are precautions of work at height
  • Ans. 

    Precautions for working at height include proper training, use of fall protection equipment, regular inspection of equipment, and securing tools and materials.

    • Ensure workers are properly trained on working at height procedures

    • Use appropriate fall protection equipment such as harnesses, lanyards, and guardrails

    • Regularly inspect all equipment used for working at height to ensure it is in good condition

    • Secure tools and ma...

  • Answered by AI
  • Q2. What are you know about lifting plan.
  • Ans. 

    A lifting plan is a detailed document outlining the procedures and precautions to be taken when lifting heavy objects.

    • A lifting plan should include the weight of the object being lifted

    • It should specify the equipment to be used for lifting

    • The plan should outline the steps to be taken to ensure the safety of workers involved

    • It should also consider factors such as the location of the lift and any potential hazards

    • Regular...

  • Answered by AI
Round 2 - HR 

(2 Questions)

  • Q1. What is risk assessment
  • Ans. 

    Risk assessment is the process of identifying, analyzing, and evaluating potential risks in order to determine the likelihood and impact of harmful events.

    • Identifying potential hazards and risks in the workplace or environment

    • Analyzing the likelihood of these risks occurring

    • Evaluating the potential impact of these risks on people, property, and the environment

    • Developing strategies to mitigate or eliminate these risks

    • Re...

  • Answered by AI
  • Q2. How to calculate capacity of wire rop sling
  • Ans. 

    Capacity of wire rope sling can be calculated by considering factors like diameter, material, and configuration.

    • Capacity is determined by the breaking strength of the wire rope and the design factor used.

    • Calculate the breaking strength of the wire rope by multiplying the area of the rope cross-section by the tensile strength of the material.

    • Consider the configuration of the sling (single leg, double leg, etc.) and appl...

  • Answered by AI

Safety Officer Interview Questions asked at other Companies

Q1. If you don't have any safety equipment and documents how to complete the work ?
View answer (17)

Turbine DCS Engineer Interview Questions & Answers

user image abhishek mishra

posted on 12 Sep 2024

Interview experience
4
Good
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Power plant related 

(4 Questions)

  • Q1. Turbine rolling
  • Q2. Cold light-up warm light-up and hot light-up
  • Q3. Emergency handling
  • Q4. All equipment performance testing

Turbine DCS Engineer Interview Questions asked at other Companies

Q1. What is the Heat Rate of turbine? How is it calculated? What are the normal parameters for DCS boiler/turbine? What is the condenser capacity of your current plant? What are the steam parameters? What is the permit procedure for hot work in... read more
View answer (1)

Instrument Engineer Interview Questions & Answers

user image Ram Anugrah Manjhi

posted on 13 Jun 2024

Interview experience
4
Good
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Technical 

(2 Questions)

  • Q1. Why are you looking for a new job?
  • Q2. Why are you not satisfied with the old company?

Instrument Engineer Interview Questions asked at other Companies

Q1. 1.General current and voltage working ranges of instruments. 2. Temperature sensors types and working principals. 3. Suitable for working hours or not. 4. General questions related to purpose of instruments required.
View answer (2)

Power Mech Projects interview questions for popular designations

 Electrical Engineer

 (4)

 Engineer

 (4)

 Mechanical Engineer

 (4)

 Senior Engineer

 (4)

 Safety Officer

 (3)

 Assistant Manager

 (2)

 Deputy Manager

 (2)

 Engineer Trainee

 (2)

Interview experience
5
Excellent
Difficulty level
Easy
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Naukri.com and was interviewed in Aug 2024. There was 1 interview round.

Round 1 - STORE 

(2 Questions)

  • Q1. What is stored material?
  • Ans. 

    Stored material refers to any items or products that are kept in a designated storage area for future use or distribution.

    • Stored material can include inventory, supplies, equipment, and raw materials.

    • Examples of stored material in a retail setting may include clothing, electronics, and household goods.

    • Proper organization and labeling of stored material is essential for efficient inventory management.

    • Regular inventory c...

  • Answered by AI
  • Q2. What is stored row material?
  • Ans. 

    Raw materials are the basic materials used in the production of goods.

    • Raw materials are the basic materials used in the production of goods

    • Examples include wood, metal, plastic, fabric, chemicals, etc.

    • Stored raw materials need to be properly organized and managed to ensure efficient production processes

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - we have bought in expert,

Store Incharge Interview Questions asked at other Companies

Q1. if material purchase in party but some material in liquid and some has been expiared how would have in this case?
View answer (4)

Get interview-ready with Top Power Mech Projects Interview Questions

Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Group Discussion 

Group Discussion - Operation & Maintenance

Deputy Manager Interview Questions asked at other Companies

Q1. 1.WHAT IS SPECIAL OF UR HOME TOWN 2.Who is Main compitetor with us and which products...3.what is main business in your area and its functions...4 Previous comoany achevements 5.Your strengts and weakness.
View answer (67)

Jobs at Power Mech Projects

View all
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Referral and was interviewed in Aug 2023. There were 2 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - Technical 

(5 Questions)

  • Q1. What is standard deviation how to apply for different grades
  • Ans. 

    Standard deviation is a measure of the amount of variation or dispersion of a set of values.

    • Standard deviation is calculated by taking the square root of the variance.

    • It is used to quantify the amount of variation or dispersion of a set of values.

    • Higher standard deviation indicates more spread out data points, while lower standard deviation indicates data points are closer to the mean.

    • It is commonly used in quality con...

  • Answered by AI
  • Q2. What is passing criteria and What is MDD and OMC
  • Q3. How to clear NCR and what is specific procedure
  • Ans. 

    To clear NCR, identify root cause, implement corrective actions, verify effectiveness, and close out the NCR.

    • Identify the root cause of the non-conformance.

    • Implement corrective actions to address the root cause.

    • Verify the effectiveness of the corrective actions through testing or inspection.

    • Close out the NCR once the corrective actions have been successful.

    • Document all steps taken in the NCR clearance process.

  • Answered by AI
  • Q4. Testing procedure for coarse aggregate
  • Ans. 

    Testing procedure for coarse aggregate involves determining its physical properties and quality through various tests.

    • Conduct sieve analysis to determine particle size distribution

    • Perform specific gravity and absorption test to assess porosity

    • Check for shape, surface texture, and angularity through visual inspection

    • Test for resistance to abrasion and impact to evaluate durability

  • Answered by AI
  • Q5. Silt content limit as per is code
  • Ans. 

    Silt content limit as per IS code is 3% for fine aggregate.

    • Silt content limit for fine aggregate as per IS code is 3%.

    • Excessive silt content can affect the quality of concrete.

    • Silt content can be determined by conducting a sieve analysis test.

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Be confidence

Senior Quality Engineer Interview Questions asked at other Companies

Q1. what is least count of vernier caliper ,micrometer, height gauge?
View answer (13)
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - HR 

(2 Questions)

  • Q1. About your self
  • Q2. About previous project

Diploma Electrical Engineer Interview Questions asked at other Companies

Q1. What is the use of star delta connection in electrical ?
View answer (3)
Interview experience
4
Good
Difficulty level
Easy
Process Duration
More than 8 weeks
Result
Selected Selected

I applied via Approached by Company and was interviewed in Jan 2024. There was 1 interview round.

Round 1 - Technical 

(2 Questions)

  • Q1. Mechanical maintenance relatives
  • Q2. Types of PM and type of valves
  • Ans. 

    There are various types of PM (Programmable Logic Controllers) and valves used in engineering.

    • Types of PM include PLC (Programmable Logic Controller), DCS (Distributed Control System), and SCADA (Supervisory Control and Data Acquisition).

    • Types of valves include gate valves, globe valves, ball valves, butterfly valves, and check valves.

    • Each type of PM and valve has its own specific applications and advantages.

    • For exampl...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Questions related to your field

Senior Engineer Interview Questions asked at other Companies

Q1. what is the meaning of M in M20,M25,M30 grade of concrete?
View answer (54)

Assistant Manager - Planning and Co-ordination Interview Questions & Answers

user image Mayur Mittal

posted on 12 Nov 2023

Interview experience
4
Good
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Walk-in and was interviewed in May 2023. There were 2 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Don’t add your photo or details such as gender, age, and address in your resume. These details do not add any value.
View all tips
Round 2 - Technical 

(5 Questions)

  • Q1. About previous projects
  • Q2. About job role in previous company
  • Q3. About thorough questioning on skills and roles mentioned in resume
  • Q4. About relevant IS Codes
  • Q5. About standards and practices

Interview Preparation Tips

Interview preparation tips for other job seekers - Be confident in interview and you can crack it easily.

Power Mech Projects Interview FAQs

How many rounds are there in Power Mech Projects interview?
Power Mech Projects interview process usually has 2-3 rounds. The most common rounds in the Power Mech Projects interview process are Technical, Resume Shortlist and HR.
How to prepare for Power Mech Projects interview?
Go through your CV in detail and study all the technologies mentioned in your CV. Prepare at least two technologies or languages in depth if you are appearing for a technical interview at Power Mech Projects. The most common topics and skills that interviewers at Power Mech Projects expect are Project Implementation, Project Management, Debugging, Power Plant and Maintenance.
What are the top questions asked in Power Mech Projects interview?

Some of the top questions asked at the Power Mech Projects interview -

  1. Hazards of confined space, Percentage of O2 in confined space for safe working,...read more
  2. Why use 4-20 ma why do not 0-20...read more
  3. All type contractors in use electrical pa...read more
How long is the Power Mech Projects interview process?

The duration of Power Mech Projects interview process can vary, but typically it takes about less than 2 weeks to complete.

Tell us how to improve this page.

Power Mech Projects Interview Process

based on 92 interviews

Interview experience

4.4
  
Good
View more

Interview Questions from Similar Companies

Siemens Interview Questions
4.1
 • 426 Interviews
Thermax Limited Interview Questions
4.2
 • 236 Interviews
ABB Interview Questions
4.1
 • 227 Interviews
Tata Power Interview Questions
3.9
 • 160 Interviews
BHEL Interview Questions
4.1
 • 106 Interviews
GE Vernova Interview Questions
4.2
 • 87 Interviews
View all

Power Mech Projects Reviews and Ratings

based on 1.6k reviews

3.9/5

Rating in categories

3.7

Skill development

3.6

Work-life balance

3.5

Salary

3.8

Job security

3.5

Company culture

3.4

Promotions

3.6

Work satisfaction

Explore 1.6k Reviews and Ratings
Sap Abap Consultant

Hyderabad / Secunderabad

5-7 Yrs

Not Disclosed

Sap Hcm Payroll Consultant

Hyderabad / Secunderabad

3-5 Yrs

₹ 4-7 LPA

Explore more jobs
Senior Engineer
411 salaries
unlock blur

₹3 L/yr - ₹8.4 L/yr

Assistant Manager
334 salaries
unlock blur

₹4.1 L/yr - ₹10 L/yr

Engineer
273 salaries
unlock blur

₹2 L/yr - ₹6.9 L/yr

Mechanical Engineer
242 salaries
unlock blur

₹2 L/yr - ₹6.7 L/yr

Electrical Engineer
218 salaries
unlock blur

₹2 L/yr - ₹7.5 L/yr

Explore more salaries
Compare Power Mech Projects with

Thermax Limited

4.2
Compare

BGR Energy Systems

3.7
Compare

Larsen & Toubro Limited

4.0
Compare

Kalpataru Projects International

4.2
Compare
Did you find this page helpful?
Yes No
write
Share an Interview