The cost expenditure per sqm without materials depends on various factors such as location, skill level of labor, project complexity, and market conditions.
The cost expenditure per sqm without materials can vary significantly depending on the location. Labor costs tend to be higher in urban areas compared to rural areas.
The skill level of labor also affects the cost. Highly skilled laborers may charge more for their se...
BBS (Bar Bending Schedule) is prepared by calculating the number of bars required for reinforcement and their lengths.
Calculate the number of bars required for reinforcement
Calculate the length of each bar
Prepare a detailed list of all the bars required for the project
Ensure that the BBS is accurate and meets the design requirements
Use software tools like AutoCAD, Excel, etc. to prepare the BBS
Review and verify the BBS
Top trending discussions
posted on 4 Aug 2022
I was interviewed in Jan 2023.
Measurement sheet is prepared by taking off quantities from drawings and specifications.
Review drawings and specifications to identify items to be measured
Take accurate measurements using appropriate tools and techniques
Record measurements in a systematic manner on the measurement sheet
Include relevant details such as dimensions, quantities, and units
Double-check measurements for accuracy and completeness
Organize the m...
Our current project billing process involves tracking expenses, labor costs, and materials used to accurately bill clients.
We track expenses such as equipment rentals, subcontractor costs, and travel expenses.
Labor costs are calculated based on hours worked by each team member and their respective rates.
Materials used are documented and their costs are included in the billing.
We ensure all expenses are properly allocat...
posted on 4 Jan 2025
I applied via Walk-in and was interviewed in Jul 2024. There were 2 interview rounds.
Project management process involves initiating, planning, executing, monitoring, and closing a project.
Initiating: Define project scope, objectives, and stakeholders.
Planning: Create a detailed project plan, including timelines, resources, and budget.
Executing: Implement the project plan and manage resources effectively.
Monitoring: Track project progress, identify risks, and make necessary adjustments.
Closing: Finalize...
Risk management involves identifying, assessing, and prioritizing risks, as well as developing mitigation plans to minimize their impact.
Identify potential risks by conducting a thorough risk assessment
Assess the likelihood and impact of each risk on the project
Prioritize risks based on their severity and potential impact
Develop a mitigation plan for each identified risk, including strategies to minimize or eliminate t...
Long lead items can be tracked by creating a detailed schedule, monitoring progress regularly, and communicating with suppliers.
Create a detailed schedule outlining the delivery dates of long lead items
Regularly monitor the progress of long lead items to ensure they are on track
Communicate effectively with suppliers to address any delays or issues
Utilize project management software to track and manage long lead items
Bar Bending Schedule is a document detailing the reinforcement placement in a beam.
Bar Bending Schedule includes details like bar diameter, spacing, length, and shape for each bar in the beam.
It helps in ensuring proper reinforcement placement as per structural design requirements.
Example: Bar Bending Schedule for a beam may specify 10mm diameter bars at 150mm spacing with a total length of 2.5m.
Bar Bending schedule for Column involves detailing the reinforcement requirements for columns in a construction project.
Bar Bending schedule includes details of reinforcement bars, their sizes, shapes, and placement in the column.
It is essential for ensuring the structural integrity and strength of the column.
The schedule is prepared based on structural drawings and design requirements.
Example: A typical bar bending sc...
I applied via Recruitment Consulltant and was interviewed in Nov 2023. There were 2 interview rounds.
I applied via Job Portal and was interviewed in Mar 2022. There were 3 interview rounds.
MEP Execution standard and codes
I applied via Approached by Company and was interviewed in Mar 2022. There were 2 interview rounds.
posted on 24 Jan 2022
LD reduces workability and increases the risk of cracking in high grade concrete.
LD (Lignite Dust) is a fine powder that is added to concrete to improve workability.
However, in high grade concrete, LD can reduce workability and increase the risk of cracking.
This is because high grade concrete has a lower water-cement ratio, which means there is less water available to hydrate the cement and make the concrete workable.
A...
posted on 14 Mar 2024
I applied via Walk-in and was interviewed before Mar 2023. There was 1 interview round.
based on 1 review
Rating in categories
Assistant Engineer
191
salaries
| ₹2 L/yr - ₹6.4 L/yr |
Junior Engineer
103
salaries
| ₹2 L/yr - ₹5 L/yr |
Senior Engineer
90
salaries
| ₹4.2 L/yr - ₹9 L/yr |
Engineer
84
salaries
| ₹3.8 L/yr - ₹7.5 L/yr |
Assistant Engineer - Civil
83
salaries
| ₹2.5 L/yr - ₹5.3 L/yr |
Prestige Group
Sobha
Godrej Properties
DLF