The sequence of works in construction typically involves planning, site preparation, foundation work, structural construction, finishing touches, and final inspection.
Planning: Develop project plans, obtain permits, and create a timeline.
Site preparation: Clear the site, set up temporary facilities, and install utilities.
Foundation work: Excavate, pour footings, and construct foundation walls.
Structural construction: B...
I appeared for an interview before Mar 2024, where I was asked the following questions.
posted on 19 Mar 2025
posted on 4 Apr 2025
I appeared for an interview in Oct 2024, where I was asked the following questions.
Extensive experience in civil construction, focusing on project management, quality control, and team collaboration.
Managed multiple large-scale construction projects, ensuring timely completion and adherence to budget constraints.
Implemented quality control measures that reduced rework by 20%, enhancing overall project efficiency.
Collaborated with architects and engineers to optimize design plans, resulting in a 15% c...
Tile flooring involves selecting, preparing, and installing tiles for aesthetic and functional purposes in flats.
Choose the right type of tile: ceramic, porcelain, vinyl, or natural stone.
Prepare the subfloor: ensure it's clean, dry, and level.
Use appropriate adhesive: thin-set mortar for most tiles, mastic for vinyl.
Measure and plan layout: start from the center for symmetry.
Cut tiles as needed: use a tile cutter or w...
Snagging and de-snagging involve identifying and rectifying defects in newly constructed flats before handover.
Snagging is the process of inspecting a property for defects or unfinished work.
Common snags include paint imperfections, misaligned doors, and plumbing issues.
De-snagging refers to the rectification of identified issues before final handover.
For example, if a window doesn't close properly, it would be noted d...
based on 1 interview
Interview experience
based on 19 reviews
Rating in categories
Senior Engineer
83
salaries
| ₹4.1 L/yr - ₹9 L/yr |
Safety Officer
83
salaries
| ₹1.9 L/yr - ₹6 L/yr |
Assistant Engineer
45
salaries
| ₹3.5 L/yr - ₹6.4 L/yr |
Junior Engineer
44
salaries
| ₹2.4 L/yr - ₹4.3 L/yr |
Junior Engineer Civil
41
salaries
| ₹2 L/yr - ₹4.2 L/yr |
Sobha
Lodha Group
Cushman & Wakefield
Godrej Properties