Erection of transformer involves several steps including site preparation, foundation construction, assembly of transformer components, and testing.
Site preparation involves clearing the area and ensuring proper drainage
Foundation construction involves excavation, pouring concrete, and curing
Assembly of transformer components includes positioning the core, winding the coils, and connecting the bushings
Testing involves ...
LV and HV panel erection involves proper planning, installation, and testing.
Plan the layout and location of the panels
Install the panels according to manufacturer's instructions
Ensure proper grounding and wiring
Test the panels for functionality and safety
Follow all safety protocols and regulations
Examples: Schneider Electric LV Panel, ABB HV Panel
Yes, I have experience in cable laying.
I have experience in laying power and communication cables
I am familiar with cable routing and cable tray installation
I have worked on projects involving underground cable laying
I am knowledgeable in cable termination and splicing techniques
I applied via Approached by Company and was interviewed before Oct 2022. There were 2 interview rounds.
Yes, I am able to handle multiple tasks efficiently and prioritize effectively.
I have experience juggling multiple projects simultaneously
I am skilled at time management and can prioritize tasks based on deadlines and importance
I am able to adapt quickly to changing priorities and work well under pressure
I was interviewed in Mar 2022.
I applied via Approached by Company and was interviewed before Mar 2022. There were 3 interview rounds.
NDT clearance process involves inspection and testing of materials and equipment to ensure compliance with standards.
NDT methods include visual inspection, radiography, ultrasonic testing, magnetic particle testing, and dye penetrant testing.
Inspection and testing is carried out by certified NDT personnel.
Clearance is given based on the results of the inspection and testing.
Documentation of the NDT clearance process is
Offshore Infrastructures interview questions for popular designations
I applied via Walk-in and was interviewed before Mar 2022. There were 2 interview rounds.
There are several types of scaffolds used in construction.
Supported scaffold
Suspended scaffold
Rolling scaffold
Aerial lift scaffold
Mobile scaffold
Cantilever scaffold
Single pole scaffold
Double pole scaffold
Trestle scaffold
Patented scaffold
OSHA 29CFR 1926, Sub Part -L outlines the requirements for scaffolding in construction work.
Subpart L covers all aspects of scaffolding, including design, construction, and use.
It requires that scaffolds be able to support their own weight and at least four times the maximum intended load.
It also mandates that scaffolds be inspected by a competent person before each use.
Training is required for all employees who work o...
Get interview-ready with Top Offshore Infrastructures Interview Questions
I applied via Naukri.com and was interviewed before Jan 2022. There were 2 interview rounds.
Earthing method involves connecting electrical equipment to the earth to prevent electric shock and damage to equipment.
Earthing can be done through a rod, plate, or strip depending on the soil resistivity
Tray types include ladder, perforated, solid-bottom, and wire mesh
Testing of equipment involves checking insulation resistance, continuity, and polarity
Panel testing includes checking for loose connections, proper lab
Cabling process involves planning, routing, pulling, terminating and testing of cables.
Plan the cable routing based on the requirements and specifications
Pull the cables through the conduits or trays
Terminate the cables at both ends using connectors or terminals
Test the cables for continuity, insulation resistance and other parameters
Label the cables for easy identification and maintenance
Ensure compliance with safety
I applied via Approached by Company and was interviewed in Aug 2021. There were 3 interview rounds.
Site situation handling
I applied via Company Website and was interviewed in Oct 2021. There were 3 interview rounds.
Test was good
Top trending discussions
The duration of Offshore Infrastructures interview process can vary, but typically it takes about less than 2 weeks to complete.
based on 35 interviews
Interview experience
based on 442 reviews
Rating in categories
Mechanical Engineer
124
salaries
| ₹1.9 L/yr - ₹7.2 L/yr |
Safety Officer
71
salaries
| ₹2.3 L/yr - ₹7.1 L/yr |
Piping Engineer
64
salaries
| ₹2 L/yr - ₹7 L/yr |
Senior Engineer
55
salaries
| ₹3 L/yr - ₹10 L/yr |
QA QC Engineer
55
salaries
| ₹2 L/yr - ₹8.3 L/yr |
Larsen & Toubro Limited
Essar Group
Adani Group
GMR Group