I applied via Approached by Company and was interviewed before Feb 2021. There were 3 interview rounds.
Calculation of mortar quantity
Mortar quantity is calculated based on the volume of bricks or blocks being used.
The ratio of cement, sand, and water in the mortar mix is also important.
The standard ratio for mortar mix is 1:4 (cement:sand).
The water-cement ratio should be around 0.5.
The quantity of mortar required can be calculated using the formula: Volume of bricks/blocks x 0.0015.
This formula assumes a mortar joint t
Top trending discussions
I applied via Walk-in and was interviewed in Oct 2022. There were 3 interview rounds.
posted on 30 Dec 2024
I am fascinated by the impact Civil Lines have on urban development and infrastructure.
The opportunity to contribute to the design and construction of roads, bridges, and buildings
The challenge of ensuring safety and efficiency in infrastructure projects
The chance to work on projects that improve the quality of life for communities
The satisfaction of seeing tangible results of your work, such as a new bridge connecting
I was impressed by your company's reputation for innovative projects and commitment to sustainability.
Reputation for innovative projects
Commitment to sustainability
Positive reviews from current employees
Company's values align with my own
Opportunities for professional growth and development
posted on 26 Jul 2024
The ratio of M25 concrete is 1:1:2 (cement:sand:aggregate)
The ratio of M25 concrete is 1:1:2, which means 1 part cement, 1 part sand, and 2 parts aggregate.
This ratio is commonly used in construction for medium strength concrete.
For example, to make 1 cubic meter of M25 concrete, you would need 1/4 cubic meters of cement, 1/4 cubic meters of sand, and 1/2 cubic meters of aggregate.
As an Assistant Engineer - Civil at my previous company, my responsibilities included assisting senior engineers in project planning, design, and construction.
Assisted senior engineers in project planning and design
Participated in site visits and inspections
Prepared project reports and documentation
Collaborated with team members and contractors
Ensured compliance with safety regulations and quality standards
Managed site operations, coordinated with contractors, ensured compliance with safety regulations.
Managed day-to-day site operations
Coordinated with contractors for timely completion of projects
Ensured compliance with safety regulations and quality standards
Prepared progress reports and communicated with stakeholders
Implemented cost-saving measures without compromising quality
The name of the client is XYZ Construction Company.
XYZ Construction Company is a well-known construction firm in the region.
They have completed several projects in the past, including the construction of a new office building in downtown.
The client has a reputation for high-quality work and timely project completion.
I applied via Referral and was interviewed in Dec 2023. There was 1 interview round.
Fixed connection does not allow rotation at the base plate, while pinned connection allows rotation.
Fixed connection is rigid and does not allow rotation at the base plate.
Pinned connection allows rotation at the base plate.
Fixed connection provides more stability and resistance to lateral forces.
Pinned connection is more flexible and allows for some movement.
Examples: Fixed connection is commonly used in high-rise bui...
The rise is the vertical distance between two consecutive steps, while the tread is the horizontal distance.
The rise is typically around 7-8 inches, while the tread is usually around 10-11 inches.
The rise and tread dimensions are important for ensuring safe and comfortable stair design.
Building codes often dictate the minimum and maximum rise and tread dimensions for safety reasons.
Pitch distance in bolt refers to the distance between the centers of adjacent bolts in a bolted connection.
Pitch distance is typically measured from the center of one bolt to the center of the next bolt in a row.
It is important to maintain consistent pitch distances to ensure proper load distribution and structural integrity.
For example, in a bolted connection with a pitch distance of 2 inches, the centers of adjacent
To create a pipe rack section on both directions.
Identify the location and dimensions for the pipe rack section
Consider the load requirements and support structures
Design the pipe rack section using appropriate materials and connections
Ensure proper spacing and alignment for pipes in both directions
posted on 12 Mar 2024
I applied via Walk-in and was interviewed in Feb 2024. There were 2 interview rounds.
SOLAR ENERGY RELETED CIVIL CONSTRUCTION DISCUSSION
Solar system refers to the collection of planets and other objects that orbit around a star, typically referring to our own solar system with the Sun at its center.
The solar system consists of the Sun, eight planets, moons, asteroids, comets, and other celestial bodies.
The planets in our solar system are Mercury, Venus, Earth, Mars, Jupiter, Saturn, Uranus, and Neptune.
The Sun is the central star of our solar system, p...
I applied via Referral and was interviewed in Aug 2023. There was 1 interview round.
Grades of concrete in a mixed batch can be estimated by performing a slump test and conducting compressive strength tests on samples.
Perform a slump test to determine the workability of the concrete mix.
Take samples from the mixed batch and cast test specimens for compressive strength testing.
Conduct compressive strength tests on the specimens to determine the grade of concrete.
Compare the test results with the standar
Site and laboratory tests on bricks and cement are essential for ensuring quality and durability of construction materials.
Site tests for bricks include visual inspection, water absorption test, compressive strength test, and efflorescence test.
Laboratory tests for bricks involve water absorption test, compressive strength test, efflorescence test, and soundness test.
Site tests for cement include checking the color, sm...
Plastering work calculation involves determining the surface area of the wall and the thickness of the plaster.
Calculate the surface area of the wall by multiplying the height and length of each wall segment.
Determine the total surface area to be plastered by adding up the surface areas of all wall segments.
Multiply the total surface area by the desired thickness of the plaster to get the volume of plaster needed.
Consi...
I applied via Walk-in and was interviewed before Aug 2023. There was 1 interview round.
posted on 17 Aug 2023
I applied via AmbitionBox and was interviewed before Aug 2022. There were 2 interview rounds.
It is very difficult test to pass
I applied via LinkedIn and was interviewed in May 2022. There were 2 interview rounds.
Hydration process is the chemical reaction between cement and water which results in the hardening of concrete.
Hydration process starts as soon as water is added to cement.
The reaction produces heat and causes the mixture to harden and gain strength.
The process continues for weeks and even months, resulting in a stronger and more durable concrete.
The amount of water used in the mixture affects the hydration process and...
Concrete strength depends on various factors.
Water-cement ratio
Type and quality of cement
Aggregate size and shape
Curing conditions
Mix design
Age of concrete
Temperature and humidity
Presence of admixtures
Water is added to concrete mixer to make the mixture more workable and to achieve the desired consistency.
Water is added to hydrate the cement and activate the chemical reaction that causes it to harden
The amount of water added affects the strength and durability of the concrete
Too much water can weaken the concrete and cause cracking
The water should be added gradually and mixed thoroughly to ensure even distribution
Ot...
Civil Site Engineer
6
salaries
| ₹2.4 L/yr - ₹3 L/yr |
Site Engineer
4
salaries
| ₹3 L/yr - ₹3.4 L/yr |
Senior Executive