Filter interviews by
I applied via Naukri.com and was interviewed in Jun 2022. There were 2 interview rounds.
Yes, I can prepare BBS (Bar Bending Schedule).
I have experience in preparing BBS for various projects.
I am proficient in using software like AutoCAD and Excel for BBS preparation.
I ensure that the BBS is accurate and meets the project requirements.
I also coordinate with the site team to ensure timely delivery of BBS.
Yes, I am familiar with Rate Analysis. A rate analysis for blockwork involves calculating the cost of materials, labor, and equipment needed for the project.
Determine the quantity of materials needed for the blockwork
Calculate the cost of materials per unit
Estimate the labor cost based on the time required for the project
Include equipment costs such as scaffolding and tools
Add all costs together to determine the total ...
Yes, I am familiar with item rate billing.
Item rate billing is a method of billing where each item or service is charged separately.
It is commonly used in construction and engineering projects.
The rates for each item are pre-determined and agreed upon by both parties.
This type of billing allows for greater transparency and accuracy in billing.
It also allows for easier tracking of expenses and budgeting.
Basic rate variation refers to the change in the standard rate of a particular item or service.
It is a change in the standard rate of a particular item or service
It can be due to various factors such as inflation, market demand, etc.
For example, if the basic rate of a product is $10 and it increases to $12, it is a basic rate variation.
Basic rate variation is due to changes in the scope of work, while rate escalation is due to inflation or market changes.
Basic rate variation occurs due to changes in the scope of work, such as additional work or changes in the design.
Rate escalation occurs due to inflation or market changes, such as an increase in the cost of materials or labor.
Basic rate variation is typically negotiated and agreed upon before the st...
I applied via Naukri.com and was interviewed before Feb 2022. There was 1 interview round.
Yes, I can prepare bar bending schedule.
I have experience in preparing bar bending schedules for various projects.
I am proficient in using software such as AutoCAD and Excel to prepare the schedules.
I ensure that the schedules are accurate and comply with the project specifications.
I also coordinate with the project team to ensure that the schedules are delivered on time.
The mix proportion of M30 is 1:1:2 (cement:sand:aggregate) by weight.
M30 is a grade of concrete used in construction.
The mix proportion of M30 is determined by weight.
The mix proportion of M30 is 1:1:2 (cement:sand:aggregate) by weight.
This means that for every 1 part cement, 1 part sand and 2 parts aggregate are used.
Top trending discussions
posted on 3 Mar 2024
Shuttering quantity calculation involves determining the amount of formwork needed for a construction project.
Calculate the surface area of the structure that needs formwork
Determine the type of formwork material to be used
Consider the complexity of the structure and any special requirements
Account for wastage and extra material for safety
Use standard formulas or software for accurate calculations
posted on 28 Nov 2023
I applied via Naukri.com and was interviewed in Oct 2023. There were 3 interview rounds.
I have completed 5 years of billing and execution work in the civil engineering field.
I have 5 years of experience in handling billing and execution work in civil engineering projects.
During these years, I have successfully managed the billing process and ensured accurate and timely invoicing.
I have also coordinated with project teams and contractors to track progress and ensure proper execution of work.
In addition, I ...
My expectation of CTC is based on my experience, skills, and market standards.
Consider my experience and skills in the field
Research market standards for Billing Engineer Civil
Take into account the company's budget and compensation structure
Negotiate based on the value I can bring to the organization
Be open to discussing other benefits and perks
posted on 22 Nov 2023
I applied via Campus Placement and was interviewed in Oct 2023. There were 2 interview rounds.
posted on 23 Nov 2022
Problems you've faced during construction
posted on 28 Jun 2022
I applied via Company Website and was interviewed in Dec 2021. There were 2 interview rounds.
posted on 11 Oct 2022
I applied via Naukri.com and was interviewed before Oct 2021. There were 4 interview rounds.
Client bills are submitted by verifying the services provided and charges incurred, generating an invoice, and sending it to the client.
Verify services provided and charges incurred
Generate invoice
Send invoice to client
Variations & extra items refer to additional charges or changes made to a standard billing item.
Variations can include changes in pricing due to location, time of day, or other factors.
Extra items can include additional services or products added to a standard billing item.
These charges are typically added on top of the standard billing item and can increase the overall cost.
Examples include a hotel charging extra for ...
posted on 1 Sep 2017
I was interviewed in Mar 2017.
Working hours of an equipment can be calculated by subtracting the start time from the end time.
Obtain the start time and end time of the equipment's operation.
Convert the start and end times to a common time format, such as hours and minutes.
Subtract the start time from the end time to calculate the duration of operation.
Consider any breaks or downtime during the operation and subtract them from the total duration.
The...
Depreciation is the decrease in the value of an asset over time due to wear and tear, obsolescence, or other factors.
Depreciation is a method used in accounting to allocate the cost of an asset over its useful life.
It represents the reduction in the value of an asset on the balance sheet.
Depreciation can be calculated using various methods such as straight-line, declining balance, or units of production.
Example: A comp...
The per hour cost of operating a batching plant depends on various factors such as the size of the plant, the type of materials being processed, and the labor and maintenance costs.
The size of the batching plant affects the operating cost. Larger plants generally have higher operating costs due to increased energy consumption and maintenance requirements.
The type of materials being processed also impacts the cost. Diff...
posted on 17 Mar 2024
I applied via Walk-in and was interviewed in Sep 2023. There was 1 interview round.
Earth cutting as per CPWD norms involves following specific guidelines for excavation work.
CPWD norms specify the depth and width of excavation for different types of soil
The guidelines also include safety measures to be followed during earth cutting
Proper disposal of excavated material is also a key aspect of CPWD norms
Deductions in measurements include shrinkage, wastage, breakage, and spillage.
Shrinkage: Reduction in size or weight of materials during handling or storage.
Wastage: Loss of materials during the construction process.
Breakage: Damage to materials during transportation or handling.
Spillage: Accidental loss of materials due to spills or leaks.
Interview experience
based on 6 reviews
Rating in categories
Senior Engineer
144
salaries
| ₹4.5 L/yr - ₹10 L/yr |
Assistant Manager
97
salaries
| ₹5.8 L/yr - ₹12 L/yr |
Civil Site Engineer
66
salaries
| ₹3 L/yr - ₹6.5 L/yr |
Junior Engineer
52
salaries
| ₹2 L/yr - ₹4 L/yr |
Senior Civil Engineer
48
salaries
| ₹3.8 L/yr - ₹8.5 L/yr |
Larsen & Toubro Limited
Punj Lloyd
Simplex Infrastructures
Nagarjuna Construction Company