I applied via Recruitment Consulltant and was interviewed in May 2024. There was 1 interview round.
ITP stands for Inspection and Test Plan, a document outlining the procedures and criteria for quality control in a project.
Define the scope and objectives of the project
Identify the key activities and deliverables
Specify the inspection and testing requirements
Outline the acceptance criteria
Assign responsibilities and timelines
Review and approve the ITP before implementation
Checklist can be made by identifying key tasks, setting priorities, creating categories, and including necessary details.
Identify key tasks that need to be completed
Set priorities for each task
Create categories to organize tasks
Include necessary details such as deadlines, responsible parties, and resources needed
I applied via Job Portal and was interviewed in Jan 2024. There was 1 interview round.
Different types of piles used in piling include driven piles, bored piles, and auger cast piles.
Driven piles are installed by driving them into the ground using a pile driver.
Bored piles are created by drilling a hole into the ground and then filling it with concrete.
Auger cast piles are formed by drilling a hole and then filling it with concrete while slowly withdrawing the auger.
Other types of piles include sheet pil
I applied via Approached by Company and was interviewed in Aug 2022. There was 1 interview round.
Confined space refers to an enclosed or partially enclosed area with limited access and egress, not designed for continuous occupancy.
Confined spaces have limited entry and exit points
They are not designed for continuous occupancy
They may pose risks due to restricted ventilation, hazardous substances, or physical hazards
Examples include storage tanks, sewers, tunnels, and crawl spaces
WMS stands for Warehouse Management System. It is used to efficiently manage and control warehouse operations.
WMS helps in optimizing inventory levels and reducing stockouts.
It enables accurate tracking of inventory, ensuring proper stock rotation and minimizing product expiration.
WMS improves order fulfillment by streamlining picking, packing, and shipping processes.
It provides real-time visibility into warehouse oper...
A work permit is a document that authorizes a person to perform a specific job or task in a controlled or hazardous environment.
A work permit ensures that the necessary safety precautions are taken before starting a job.
It outlines the scope of work, potential hazards, and required safety measures.
Work permits are commonly used in industries such as construction, manufacturing, and oil and gas.
Examples of work permits ...
A near-miss is an incident that could have resulted in an injury, illness, or damage, but fortunately did not.
A near-miss is a close call or a narrowly avoided accident.
It is an event that has the potential to cause harm but did not result in any injury or damage.
Near-misses are important to identify and analyze as they provide valuable insights into potential hazards and risks.
Reporting and investigating near-misses c...
The requirements of a crane lifting include proper planning, trained operators, suitable equipment, and adherence to safety regulations.
Proper planning is essential to ensure that the crane is used in a safe and efficient manner.
Trained operators should be responsible for operating the crane and should have the necessary skills and knowledge.
Suitable equipment, including the crane itself and any rigging or lifting acce...
SEPCO ELECTRIC POWER CONSTRUCTION CORPORATION interview questions for popular designations
I applied via Naukri.com and was interviewed before Oct 2020. There were 5 interview rounds.
The 87T transformer differential testing procedure is used to test the differential relay protection system of a transformer.
Disconnect the transformer from the power source
Connect the relay test set to the differential relay
Inject current into the relay and measure the response
Compare the results with the expected values
Perform a secondary injection test to verify the accuracy of the test set
Document the test results
LV circuit breaker with coupling breaker is used for protection and isolation of electrical circuits.
LV circuit breaker is a device that automatically interrupts the flow of current in an electrical circuit.
Coupling breaker is used to connect or disconnect two circuits.
LV circuit breaker with coupling breaker is used to protect and isolate electrical circuits.
It is commonly used in power distribution systems.
It helps i...
Primary injection testing is a method to verify the performance of a circuit breaker or protective relay.
Primary injection testing involves injecting a high current into the circuit to simulate a fault condition.
The current is measured and compared to the expected values to ensure the circuit breaker or relay is functioning properly.
Calculations involve determining the expected current based on the system voltage, impe...
I appeared for an interview before Apr 2020.
A work permit is a document that authorizes a person to perform a specific job. Aramco work permits are color-coded based on the type of work.
A work permit is required for any job that involves a potential hazard or risk.
Aramco work permits are color-coded based on the type of work, such as hot work, confined space entry, or electrical work.
The color of the work permit indicates the level of risk associated with the jo...
I applied via Job Portal and was interviewed before Jan 2021. There were 12 interview rounds.
I am an experienced Civil Foreman with a strong background in managing construction projects and leading teams.
Over 10 years of experience in the construction industry
Proven track record of successfully completing projects on time and within budget
Expertise in interpreting blueprints and ensuring compliance with building codes
Skilled in coordinating and supervising construction activities
Strong leadership and communica...
Top trending discussions
posted on 26 Sep 2021
I applied via Job Portal and was interviewed in Mar 2021. There were 4 interview rounds.
posted on 22 Sep 2021
I applied via Referral and was interviewed in Mar 2021. There was 1 interview round.
posted on 6 Jun 2024
I applied via Referral and was interviewed before Jun 2023. There was 1 interview round.
Target mean strength of M-35 Grade concrete is 35 MPa.
The target mean strength of M-35 Grade concrete is 35 MPa.
M-35 Grade concrete is designed for structural applications requiring high strength.
Quality control measures should be in place to ensure the concrete meets the target strength.
Soil compaction percentage in embankment typically ranges from 90% to 95% depending on the type of soil and project specifications.
Soil compaction percentage in embankment is usually between 90% to 95%
The exact percentage may vary based on the type of soil being compacted
Project specifications and requirements will dictate the specific compaction percentage to be achieved
Some of the top questions asked at the SEPCO ELECTRIC POWER CONSTRUCTION CORPORATION interview -
based on 3 interviews
Interview experience
based on 66 reviews
Rating in categories
Mechanical Engineer
6
salaries
| ₹2 L/yr - ₹11.5 L/yr |
Electrical Site Engineer
6
salaries
| ₹2.2 L/yr - ₹5 L/yr |
Electrical Engineer
5
salaries
| ₹3.3 L/yr - ₹12 L/yr |
Instrument Engineer
5
salaries
| ₹13.2 L/yr - ₹16 L/yr |
QC Piping Inspector
4
salaries
| ₹10 L/yr - ₹27.2 L/yr |
L&T Construction
Megha Engineering & Infrastructures
Shapoorji Pallonji Group
Alstom Transportation