Upload Button Icon Add office photos

Filter interviews by

Power Grid Corporation of India Interview Questions, Process, and Tips

Updated 4 Feb 2025

Top Power Grid Corporation of India Interview Questions and Answers

View all 42 questions

Power Grid Corporation of India Interview Experiences

Popular Designations

65 interviews found

Apprentice Interview Questions & Answers

user image Chinku Chinku

posted on 8 May 2024

Interview experience
4
Good
Difficulty level
Easy
Process Duration
2-4 weeks
Result
Selected Selected

I applied via Company Website and was interviewed before May 2023. There was 1 interview round.

Round 1 - HR 

(2 Questions)

  • Q1. Based on marks obtained in MBA
  • Q2. Shortlisted based on marks

Apprentice Interview Questions asked at other Companies

Q1. 3. What do you know about artificial intelligence and Machine learning?
View answer (2)
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I was interviewed before Feb 2024.

Round 1 - Technical 

(1 Question)

  • Q1. About electrical engineering questions related to power system and machine mostly
Round 2 - Group Discussion 

Related to a recent issue.

Interview Preparation Tips

Interview preparation tips for other job seekers - Preapare well learn Power system and machine deeply to crack interview

Electrical Engineer Interview Questions asked at other Companies

Q1. What is the difference between Switch gear & Circuit Breakers ?
View answer (11)
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - Technical 

(2 Questions)

  • Q1. About transformer protection and shut down process ....Etc
  • Q2. How Buchholz relay works?
  • Ans. 

    Buchholz relay is a protective device used in oil-filled transformers to detect and prevent faults.

    • It is installed between the transformer tank and conservator tank.

    • It detects the presence of gas or oil flow in the transformer oil.

    • It operates on the principle of gas collection and oil surge.

    • It sends an alarm signal to the control room in case of any fault.

    • It helps in preventing major faults and damage to the transforme

  • Answered by AI
Round 3 - Aptitude Test 

About relationship,Problems on age

Round 4 - Group Discussion 

GD on Line operation , Shutdown of ICT

Interview Preparation Tips

Interview preparation tips for other job seekers - Mind concentration should be sharp , Present of mind should be very sharp....before interviewer ...And don't thik what company will do for you always think what can you do for the company..

Senior Engineer- Maintenance Interview Questions asked at other Companies

Q1. (1) What do you see in maintenance (2) will you do maint. Of hight power ups (3) how to reduce n/d time of plant machines (4) can you in house repiari VFD & programing /commissioning (5) To who does your reporting (6) will calibrate the... read more
View answer (1)
Interview experience
4
Good
Difficulty level
Easy
Process Duration
More than 8 weeks
Result
Selected Selected

I was interviewed before Jan 2024.

Round 1 - One-on-one 

(2 Questions)

  • Q1. OHE related all questions
  • Q2. Design OHE

Interview Preparation Tips

Interview preparation tips for other job seekers - Don't join on voyants, join only if no any other chance, otherwise sit in home is best

Power Grid Corporation of India interview questions for popular designations

 Apprentice Trainee

 (5)

 Field Engineer

 (5)

 Engineer

 (4)

 Field Supervisor

 (3)

 Apprentice

 (2)

 Apprenticeship Trainee

 (2)

 Assistant Engineer

 (2)

 Electrical Engineer

 (2)

Interview experience
5
Excellent
Difficulty level
Hard
Process Duration
2-4 weeks
Result
Selected Selected

I was interviewed in Jul 2022.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Don’t add your photo or details such as gender, age, and address in your resume. These details do not add any value.
View all tips
Round 2 - Technical 

(2 Questions)

  • Q1. 400 kv hardware detected
  • Ans. 

    400 kv hardware detected - need more context to provide answer

    • What type of hardware is being referred to?

    • What is the context of the detection?

    • What are the potential implications of the detection?

    • What steps need to be taken next?

  • Answered by AI
  • Q2. All 400 kv 220 kv line Hardware knowledge

Interview Preparation Tips

Interview preparation tips for other job seekers - All transactions lines hardware detected a tower body ect knowledge

Electrical Engineer Interview Questions asked at other Companies

Q1. What is the difference between Switch gear & Circuit Breakers ?
View answer (11)

Get interview-ready with Top Power Grid Corporation of India Interview Questions

Student Intern Interview Questions & Answers

user image Shubham Mishra

posted on 17 Oct 2023

Interview experience
5
Excellent
Difficulty level
Easy
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Walk-in and was interviewed before Oct 2022. There were 2 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Properly align and format text in your resume. A recruiter will have to spend more time reading poorly aligned text, leading to high chances of rejection.
View all tips
Round 2 - HR 

(2 Questions)

  • Q1. Related to internship topic
  • Q2. About yourself and your current qualification

Interview Preparation Tips

Interview preparation tips for other job seekers - Be in formal and stay calm

Student Intern Interview Questions asked at other Companies

Q1. Have you finished the database and data structures courses in you study program?
View answer (1)

Field Engineer Interview Questions & Answers

user image JITU CHARAN BEHERA

posted on 31 Dec 2021

I applied via Recruitment Consultant and was interviewed in Dec 2021. There was 1 interview round.

Interview Questionnaire 

10 Questions

  • Q1. Why transformer are rated in KVA.
  • Ans. 

    Transformers are rated in KVA because it represents the apparent power they can handle.

    • KVA stands for kilovolt-ampere, which is a unit of apparent power.

    • Transformers are designed to handle a certain amount of power, and the KVA rating indicates their capacity.

    • The KVA rating takes into account both the voltage and current that the transformer can handle.

    • It helps in determining the appropriate size and capacity of the tr...

  • Answered by AI
  • Q2. What is the ground clearance of 400KV transmission line.
  • Ans. 

    The ground clearance of a 400KV transmission line varies depending on various factors.

    • The ground clearance of a transmission line is the vertical distance between the lowest point of the conductor and the ground.

    • The ground clearance is determined based on safety regulations and requirements.

    • Factors that influence the ground clearance include terrain, vegetation, and proximity to buildings or roads.

    • In hilly areas, the g...

  • Answered by AI
  • Q3. What should be the tan Delta value of electrical equipment (for example T/F).
  • Ans. 

    The tan Delta value of electrical equipment should be as low as possible.

    • Tan Delta is a measure of the dielectric losses in electrical equipment.

    • A low tan Delta value indicates that the equipment has good insulation properties.

    • The tan Delta value can be affected by factors such as temperature, moisture, and aging of the equipment.

    • For transformers, a typical tan Delta value is around 0.001 or lower.

  • Answered by AI
  • Q4. Why ACSRinvar conductor are widely used in metro principal city.
  • Ans. 

    ACSRinvar conductors are widely used in metro principal cities due to their high strength and low thermal expansion.

    • ACSRinvar conductors have a high tensile strength, making them suitable for long-distance transmission lines in metro cities.

    • They have a low coefficient of thermal expansion, which helps in reducing sagging of the conductors and maintaining power transmission efficiency.

    • The use of ACSRinvar conductors in ...

  • Answered by AI
  • Q5. The Basis setting of REF protectionfor transformer should be how much.
  • Ans. 

    The Basis setting of REF protection for a transformer should be determined based on the transformer's characteristics and the system requirements.

    • The basis setting of REF (Restricted Earth Fault) protection for a transformer is typically determined by considering the transformer's winding configuration, impedance, and the system's fault level.

    • The setting should be chosen to ensure that the protection operates reliably ...

  • Answered by AI
  • Q6. The SF6 gas used for Ckt breaker chamber should be how much bar.
  • Ans. 

    The SF6 gas used for Ckt breaker chamber should be maintained at a pressure of around 5-7 bar.

    • The SF6 gas in the circuit breaker chamber should be maintained at a specific pressure to ensure proper functioning.

    • The recommended pressure for SF6 gas in the circuit breaker chamber is typically between 5 and 7 bar.

    • Maintaining the correct pressure helps in extinguishing the arc during circuit interruption.

    • Too low or too high...

  • Answered by AI
  • Q7. Why star star zero phase shift transformer winding are used.
  • Ans. 

    Star-star zero phase shift transformer windings are used to provide a balanced three-phase output with zero phase shift between primary and secondary voltages.

    • Star-star zero phase shift transformer windings are commonly used in power distribution systems.

    • They are used to supply power to three-phase loads such as motors, generators, and transformers.

    • The windings are designed in such a way that the voltages in the primar...

  • Answered by AI
  • Q8. What are the main difference between AIS and GIS Substation.
  • Ans. 

    AIS and GIS substations differ in their construction and insulation methods.

    • AIS (Air Insulated Substation) uses air as the insulation medium, while GIS (Gas Insulated Substation) uses SF6 gas.

    • AIS substations require larger land areas compared to GIS substations.

    • GIS substations are more compact and can be installed in urban areas where space is limited.

    • AIS substations are more susceptible to environmental factors like p...

  • Answered by AI
  • Q9. Why vibration damper are used with Conductor.
  • Ans. 

    Vibration dampers are used with conductors to reduce the risk of fatigue failure and damage caused by wind-induced vibrations.

    • Vibration dampers absorb and dissipate the energy generated by wind-induced vibrations in conductors.

    • They help to reduce the risk of fatigue failure and damage to the conductor and associated hardware.

    • Vibration dampers are typically installed at regular intervals along the length of the conducto...

  • Answered by AI
  • Q10. What is main function of LA in Substion.
  • Ans. 

    The main function of LA in a substation is to protect electrical equipment from lightning strikes.

    • LA stands for Lightning Arrester.

    • It is installed in substations to divert lightning strikes away from sensitive equipment.

    • LA provides a low-impedance path for lightning current to flow to the ground.

    • It helps in preventing damage to transformers, circuit breakers, and other electrical devices.

    • LA operates by ionizing the air...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - As per my point of view the interview for Electrical Experience Engineer/Manager should be on behalf of Experience and technical topics.

Top Power Grid Corporation of India Field Engineer Interview Questions and Answers

Q1. What should be the tan Delta value of electrical equipment (for example T/F).
View answer (4)

Field Engineer Interview Questions asked at other Companies

Q1. What is insulator and conductors and semiconductors
View answer (6)

I applied via Approached by Company and was interviewed in Jan 2022. There were 2 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Double-check your resume for any spelling mistakes. The recruiter may consider spelling mistakes as careless behavior or poor communication skills.
View all tips
Round 2 - Technical 

(5 Questions)

  • Q1. Genaretion transmission distribution machine
  • Q2. Circuit basic knowledge
  • Q3. Genaretion transmission distribution
  • Q4. Sub station testing ten del crm test dcrm and timings test of circuit breaker
  • Q5. Transmission distribution

Interview Preparation Tips

Interview preparation tips for other job seekers - Good skill good team work good bihaviar

Apprentice Trainee Interview Questions asked at other Companies

Q1. # Modes of heat transfer and how do they work? #Thermodynamics #performance curve of pump #priming (pump)
View answer (3)
Interview experience
5
Excellent
Difficulty level
Easy
Process Duration
2-4 weeks
Result
Selected Selected

I applied via Naukri.com and was interviewed before Dec 2021. There were 2 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Do not use an unprofessional email address such as cool_boy@email.com. It shows a lack of professionalism by the candidate.
View all tips
Round 2 - Technical 

(3 Questions)

  • Q1. 132kv & 33kv line & substation
  • Q2. Base terminal battery company
  • Q3. Electrical in transmission & bistrubation

Interview Preparation Tips

Topics to prepare for Power Grid Corporation of India Field Supervisor interview:
  • Technical
Interview preparation tips for other job seekers - I will back,we asked our readers to tell us the best job search advice thay ever heard.Now from one job seeker to another,we have complied their answers into a collection of the best job search advice from the job seekers themselves.

Field Supervisor Interview Questions asked at other Companies

Q1. If a fan of 500watt is connected to a single phases line what ampare carent it is consumed
View answer (1)
Round 1 - Technical 

(2 Questions)

  • Q1. What's your ambition
  • Q2. What's your goals why you want to go for it

Interview Preparation Tips

Interview preparation tips for other job seekers - Not bad. Better to go for other companies where the job is secure and had good leadership.
Not good for FTE

Top Power Grid Corporation of India Field Engineer Interview Questions and Answers

Q1. What should be the tan Delta value of electrical equipment (for example T/F).
View answer (4)

Field Engineer Interview Questions asked at other Companies

Q1. What is insulator and conductors and semiconductors
View answer (6)

Power Grid Corporation of India Interview FAQs

How many rounds are there in Power Grid Corporation of India interview?
Power Grid Corporation of India interview process usually has 1-2 rounds. The most common rounds in the Power Grid Corporation of India interview process are Technical, Resume Shortlist and HR.
How to prepare for Power Grid Corporation of India interview?
Go through your CV in detail and study all the technologies mentioned in your CV. Prepare at least two technologies or languages in depth if you are appearing for a technical interview at Power Grid Corporation of India. The most common topics and skills that interviewers at Power Grid Corporation of India expect are Customer Experience and Restaurant Management.
What are the top questions asked in Power Grid Corporation of India interview?

Some of the top questions asked at the Power Grid Corporation of India interview -

  1. What should be the tan Delta value of electrical equipment (for example T/...read more
  2. What is the ground clearance of 400KV transmission li...read more
  3. Why transformer are rated in K...read more
How long is the Power Grid Corporation of India interview process?

The duration of Power Grid Corporation of India interview process can vary, but typically it takes about less than 2 weeks to complete.

Tell us how to improve this page.

Power Grid Corporation of India Interview Process

based on 52 interviews

Interview experience

4.5
  
Good
View more

Interview Questions from Similar Companies

Adani Power Interview Questions
3.9
 • 215 Interviews
Tata Power Interview Questions
3.9
 • 162 Interviews
NTPC Interview Questions
4.2
 • 159 Interviews
Suzlon Group Interview Questions
4.1
 • 128 Interviews
Torrent Power Interview Questions
3.7
 • 125 Interviews
BHEL Interview Questions
4.1
 • 109 Interviews
Reliance Power Interview Questions
4.1
 • 47 Interviews
JSW Energy Interview Questions
4.1
 • 28 Interviews
CESC Interview Questions
3.8
 • 21 Interviews
NHPC Interview Questions
4.3
 • 10 Interviews
View all

Power Grid Corporation of India Reviews and Ratings

based on 887 reviews

4.4/5

Rating in categories

4.2

Skill development

4.2

Work-life balance

4.3

Salary

3.9

Job security

4.2

Company culture

3.7

Promotions

4.1

Work satisfaction

Explore 887 Reviews and Ratings
Field Engineer
209 salaries
unlock blur

₹3.5 L/yr - ₹9 L/yr

Field Supervisor
85 salaries
unlock blur

₹4.1 L/yr - ₹6.5 L/yr

Graduate Apprentice Trainee
65 salaries
unlock blur

₹1.8 L/yr - ₹3 L/yr

Electrical Engineer
63 salaries
unlock blur

₹1.7 L/yr - ₹9.1 L/yr

Associate Engineer
59 salaries
unlock blur

₹2.4 L/yr - ₹4.6 L/yr

Explore more salaries
Compare Power Grid Corporation of India with

NTPC

4.2
Compare

BHEL

4.1
Compare

Tata Power

3.9
Compare

Adani Power

3.9
Compare
Did you find this page helpful?
Yes No
write
Share an Interview