  • Q1. Different construction activities rates, like plinth area, individual rates for shuttering, reinforcement works, how to cost control in major items in the project etc
  • Ans. 

    Cost control in construction activities through effective management of major items

    • Develop a detailed cost estimate for the project

    • Monitor and track actual costs against the estimate

    • Identify major cost drivers and implement cost-saving measures

    • Regularly review and update the project budget

    • Ensure effective communication and collaboration between all stakeholders

    • Use technology and software to streamline cost control proc...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - He was asked in project topic related new project, previous work experience and brief description of works, previous working team strength and capabilities and how to execute a project in brief from starting to closing of project in-sequence etc.

Interview questions from similar companies

Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - Technical 

(3 Questions)

  • Q1. DDUGJY Project;- 33/11 KV New PSS ,33 KV Line ,11 KV Line and LT Line
  • Ans. Rerea of New PSS 60*40 mtr control room 1700 sqft road 60 mtr width 3.75 mtr footpath 15 mtr , fencing 40 mtr cable trench 130 mtr , 2 no 5 MVA PTR, 800Amp VCB and 800 Amp rating isolator in switch yards area. cost of civil work by sub cotractor 1.15 cr and electrical work 9.85 lac.
  • Answered Anonymously
  • Q2. RGGVY 12th Plan , HVDS Project, and Segrigation
  • Q3. ADB Project 33/11 KV New PSS R&M 33&11 KV line LT Line
Round 3 - HR 

(1 Question)

  • Q1. Final negotiation of salary

Interview Preparation Tips

Interview preparation tips for other job seekers - Please consider as per work profile in electrical feild
Round 1 - Technical 

(15 Questions)

  • Q1. Two types of pavent 1:- Flexible pavement 2:-rigid pavement Types of progect 1:- New progect 2:- Realigment of road
  • Ans. 

    Flexible pavement and rigid pavement are two types of pavements used in different types of road projects.

    • Flexible pavement is made of multiple layers of materials that can flex under traffic loads.

    • Rigid pavement is made of a single layer of concrete or asphalt that is rigid and does not flex.

    • New projects involve constructing roads from scratch, while realignment projects involve changing the alignment of existing roads...

  • Answered by AI
  • Q2. Constrution process:- surveying, enchrochment ,NGL, OGL
  • Q3. Flexibile road :- 1:- Embankment as per site now taken thickness 3M , Large size of soil particles75mm lumps& cloud , liquid index<50% , plastic limit <25% , Swelling &shrinkage <50% , effective cbr as per...
  • Q4. 3:- confinement layer or new blanket
  • Q5. 4:- WMM:- It is mixture of aggregate and binding material, aggregate size4.75mm to 20mm. Binding material used stone dust ,morum,flyash, total compacted 300mm. Two layer 150mm &150mm. It is mix in pre mix...
  • Q6. (a) Prime coat:- low viscous cut back bitumen on wmm surface area fil up pores and void. (b) Tack coat:- Light application bitumen, ashphalt,emulsion,and dilute water applied on the prim coat.
  • Ans. 

    The question describes the application of prime coat and tack coat on a WMM surface.

    • Prime coat is a low viscous cut back bitumen used to fill up pores and voids on a WMM surface.

    • Tack coat is a light application of bitumen, asphalt, emulsion, or dilute water applied on the prime coat.

    • The purpose of the prime coat is to bond the WMM surface with the subsequent layers of asphalt.

    • The tack coat helps in providing a strong b...

  • Answered by AI
  • Q7. 5 :- DBM:- It is total thickness 150mm. Compacted in two layer 100mm & 50mm Aggregate size 20mm to 28mm ,bitumen viscous grade VG30 grade bitumen mixture.
  • Q8. Tack coat :- light application bitumen ,Asphalt, emulsion,and diluted water on the surface area of DBM.
  • Q9. 6:- BC :- It is total thicness 50 mm compacted. It is mixture of aggregate size 13.1mm bitumen VG30 grade viscous.
  • Q10. 7:- Seal :- 6mm to 8mm thickness grvel or coarse sand mix with bitumen on BC course .provided camber on flexble pavement 1in 40 to 1in 40.
  • Q11. RIGID PAVEMENT :- All the process of embankment to GSB is same. DLC:- Specification 1 :- Aggregate size 26.5 mm 2:-water absorption<2% 3 :- soundness test :- Naso4 12% ...
  • Q12. DESIGIN PROCEDURE :- DLC thickness 150mm. 1:- use M15 grade concrete,max aggregate cement ratio 12:1 2:-The minimum cement content 150kg per cum. If flayash is more than >20% the mini.mum cement content. ...
  • Ans. 

    Design procedure for 150mm DLC thickness using M15 grade concrete with specific requirements for cement content, testing, mixing, transportation, compaction, and curing.

    • Use M15 grade concrete with maximum aggregate cement ratio of 12:1

    • Minimum cement content of 150kg per cum, or 120kg per cum if flyash is more than 20%

    • Perform 5 sample cube test after 7 day curing with strength of 10 MPA, and 1 sample cube test after 7 d...

  • Answered by AI
  • Q13. PQC:- TOTAL THICKNESS 300MM Aggregate size 31.5mm. All specificition is same as DLC.
  • Q14. Design procedure :- 1 :- The minimum cement content 360 kg per cum.if the fly ash is more than 20% the minimum cement content 310 kg per cum. 2 :-The flexure strength of cement concrete after 28 days cur...
  • Ans. 

    Design procedure for Senior Project Manager role including cement content, strength, joint design, and surface finishing.

    • Minimum cement content of 360 kg per cum, or 310 kg per cum if fly ash is more than 20%

    • Flexure strength of cement concrete after 28 days curing is 4.5 MPA

    • Compressive strength of cement concrete after 28 days curing is 40 MPA

    • Dowel bar provided for expansion joint vehicle load transfer between slabs

    • Tie...

  • Answered by AI
  • Q15. CBR:- Developed by calforina division state highway to classiy soil sub grade &GSB CBR=3%-25% CLAY<8% SAND 15% -35% GRAVEL>25% THICKNESS OF PAVEMENT T=( 1.75P/CBR - A/3.14)

Interview Preparation Tips

Interview preparation tips for other job seekers - Other type as per location of the site.
Type of material used in high way.
highway -2 to 4 lane
Expressway- 6 to 8 lane
VUP =5.5 M
LVUP=3.5M
CUP=3M

I applied via Naukri.com and was interviewed before Dec 2019. There was 1 interview round.

Interview Questionnaire 

2 Questions

  • Q1. You ask my site experience
  • Q2. Job responsibilities and working status

Interview Preparation Tips

Interview preparation tips for other job seekers - Firsthours
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Don’t add your photo or details such as gender, age, and address in your resume. These details do not add any value.
View all tips
Round 2 - One-on-one 

(2 Questions)

  • Q1. Introduce yourself? This This question is just make you comfortable to boost your confidence because you surely know the answer.?
  • Ans. Prepare your introduction and speak. Ensure that your speak naturally - touch upon your education, family, academic & experience. Keep some thread which will generate another related questions & if successful then gobwith flow
  • Answered Anonymously
  • Q2. Why do you want to change?
  • Ans. Multiple answers.. Stagnant, better remuneration, better position, change of location... and many.. see what suits you. Try to avoid talking against any current & previous employer
  • Answered Anonymously

Interview Preparation Tips

Interview preparation tips for other job seekers - Prepare impressive CV, you can include some graphics or pics of your work from earlier employment such as pic with team .. which indirectly explain team size you handled, site pics containing yourself.. explains your site visits. Some KOMs showing formal approach... but ensure, you do not break the confidential requirements...!
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
Selected Selected
Round 1 - Technical 

(1 Question)

  • Q1. Project Monitoring, scheduling Analyze projects, budget, cash flow, coordination with contractors, Consultant and allied services, construction, resource management, quality control and quality assurance, ...
Round 2 - Group Discussion 

Already talked to you

I applied via Naukri.com and was interviewed in Nov 2022. There was 1 interview round.

Round 1 - Technical 

(2 Questions)

  • Q1. Sewerage System - Design Standards
  • Ans. 

    Design standards for sewerage system

    • Design standards vary based on location and regulations

    • Consideration should be given to factors such as population density, topography, and soil type

    • Standards may include minimum pipe diameter, slope, and depth

    • Examples of design standards include ASCE 15 and EPA guidelines

  • Answered by AI
  • Q2. Load distribution method

Interview Preparation Tips

Interview preparation tips for other job seekers - Hydraulic Design of sewerage & drainage system.
Longitudinal section of Hydraulic line
Interview experience
4
Good
Difficulty level
Hard
Process Duration
2-4 weeks
Result
Selected Selected

I applied via Walk-in and was interviewed in May 2023. There were 3 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Properly align and format text in your resume. A recruiter will have to spend more time reading poorly aligned text, leading to high chances of rejection.
View all tips
Round 2 - Technical 

(2 Questions)

  • Q1. Self introduction and roles and responsibilities of the previous company
  • Q2. Question related to safety and quality
Round 3 - HR 

(2 Questions)

  • Q1. Salary negotiation with respect to previous salary
  • Q2. Benefits and facilities provided by the company
Round 1 - Technical 

(15 Questions)

  • Q1. Two types of pavent 1:- Flexible pavement 2:-rigid pavement Types of progect 1:- New progect 2:- Realigment of road
  • Ans. 

    Flexible pavement and rigid pavement are two types of pavements used in different types of road projects.

    • Flexible pavement is made of multiple layers of materials that can flex under traffic loads.

    • Rigid pavement is made of a single layer of concrete or asphalt that is rigid and does not flex.

    • New projects involve constructing roads from scratch, while realignment projects involve changing the alignment of existing roads...

  • Answered by AI
  • Q2. Constrution process:- surveying, enchrochment ,NGL, OGL
  • Q3. Flexibile road :- 1:- Embankment as per site now taken thickness 3M , Large size of soil particles75mm lumps& cloud , liquid index<50% , plastic limit <25% , Swelling &shrinkage <50% , effective cbr as per...
  • Q4. 3:- confinement layer or new blanket
  • Q5. 4:- WMM:- It is mixture of aggregate and binding material, aggregate size4.75mm to 20mm. Binding material used stone dust ,morum,flyash, total compacted 300mm. Two layer 150mm &150mm. It is mix in pre mix...
  • Q6. (a) Prime coat:- low viscous cut back bitumen on wmm surface area fil up pores and void. (b) Tack coat:- Light application bitumen, ashphalt,emulsion,and dilute water applied on the prim coat.
  • Ans. 

    The question describes the application of prime coat and tack coat on a WMM surface.

    • Prime coat is a low viscous cut back bitumen used to fill up pores and voids on a WMM surface.

    • Tack coat is a light application of bitumen, asphalt, emulsion, or dilute water applied on the prime coat.

    • The purpose of the prime coat is to bond the WMM surface with the subsequent layers of asphalt.

    • The tack coat helps in providing a strong b...

  • Answered by AI
  • Q7. 5 :- DBM:- It is total thickness 150mm. Compacted in two layer 100mm & 50mm Aggregate size 20mm to 28mm ,bitumen viscous grade VG30 grade bitumen mixture.
  • Q8. Tack coat :- light application bitumen ,Asphalt, emulsion,and diluted water on the surface area of DBM.
  • Q9. 6:- BC :- It is total thicness 50 mm compacted. It is mixture of aggregate size 13.1mm bitumen VG30 grade viscous.
  • Q10. 7:- Seal :- 6mm to 8mm thickness grvel or coarse sand mix with bitumen on BC course .provided camber on flexble pavement 1in 40 to 1in 40.
  • Q11. RIGID PAVEMENT :- All the process of embankment to GSB is same. DLC:- Specification 1 :- Aggregate size 26.5 mm 2:-water absorption<2% 3 :- soundness test :- Naso4 12% ...
  • Q12. DESIGIN PROCEDURE :- DLC thickness 150mm. 1:- use M15 grade concrete,max aggregate cement ratio 12:1 2:-The minimum cement content 150kg per cum. If flayash is more than >20% the mini.mum cement content. ...
  • Ans. 

    Design procedure for 150mm DLC thickness using M15 grade concrete with specific requirements for cement content, testing, mixing, transportation, compaction, and curing.

    • Use M15 grade concrete with maximum aggregate cement ratio of 12:1

    • Minimum cement content of 150kg per cum, or 120kg per cum if flyash is more than 20%

    • Perform 5 sample cube test after 7 day curing with strength of 10 MPA, and 1 sample cube test after 7 d...

  • Answered by AI
  • Q13. PQC:- TOTAL THICKNESS 300MM Aggregate size 31.5mm. All specificition is same as DLC.
  • Q14. Design procedure :- 1 :- The minimum cement content 360 kg per cum.if the fly ash is more than 20% the minimum cement content 310 kg per cum. 2 :-The flexure strength of cement concrete after 28 days cur...
  • Ans. 

    Design procedure for Senior Project Manager role including cement content, strength, joint design, and surface finishing.

    • Minimum cement content of 360 kg per cum, or 310 kg per cum if fly ash is more than 20%

    • Flexure strength of cement concrete after 28 days curing is 4.5 MPA

    • Compressive strength of cement concrete after 28 days curing is 40 MPA

    • Dowel bar provided for expansion joint vehicle load transfer between slabs

    • Tie...

  • Answered by AI
  • Q15. CBR:- Developed by calforina division state highway to classiy soil sub grade &GSB CBR=3%-25% CLAY<8% SAND 15% -35% GRAVEL>25% THICKNESS OF PAVEMENT T=( 1.75P/CBR - A/3.14)

Interview Preparation Tips

Interview preparation tips for other job seekers - Other type as per location of the site.
Type of material used in high way.
highway -2 to 4 lane
Expressway- 6 to 8 lane
VUP =5.5 M
LVUP=3.5M
CUP=3M
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Double-check your resume for any spelling mistakes. The recruiter may consider spelling mistakes as careless behavior or poor communication skills.
View all tips
Round 2 - Technical 

(4 Questions)

  • Q1. Detail process of building survey
  • Ans. 

    The process of building survey involves several steps to assess the condition and suitability of a building.

    • Determine the purpose of the survey and the scope of work

    • Conduct a visual inspection of the building's exterior and interior

    • Identify any structural issues, such as cracks or signs of deterioration

    • Assess the building's systems, including electrical, plumbing, and HVAC

    • Evaluate the building's compliance with buildin...

  • Answered by AI
  • Q2. What is development length
  • Ans. 

    Development length is the minimum length of reinforcement required to transfer the stress between the concrete and the reinforcement.

    • Development length is determined by factors such as the type of reinforcement, concrete strength, and bond strength.

    • It is necessary to ensure that the reinforcement bars are properly embedded in the concrete to provide structural integrity.

    • The development length can vary depending on the ...

  • Answered by AI
  • Q3. What about you know waterproofing of toilet area
  • Ans. 

    Waterproofing of toilet area is essential to prevent water damage and maintain hygiene.

    • Waterproofing involves applying a waterproof membrane or coating to the walls, floors, and joints of the toilet area.

    • It helps to prevent water leakage, seepage, and dampness, which can lead to structural damage and mold growth.

    • Various materials like waterproofing membranes, sealants, and grouts are used for effective waterproofing.

    • Pr...

  • Answered by AI
  • Q4. Circumstances of handing over flat to Clint
  • Ans. 

    The circumstances of handing over the flat to Clint

    • The flat was handed over to Clint after completing all necessary paperwork

    • The condition of the flat was documented before handing it over to Clint

    • Keys and access cards were provided to Clint

    • Any outstanding payments or dues were settled before the handover

  • Answered by AI
Round 3 - HR 

(4 Questions)

  • Q1. Pls give information about your profile
  • Q2. What is your strength
  • Q3. During job are you comfortable of transfer
  • Q4. Why are you leaving your current company

Interview Preparation Tips

Interview preparation tips for other job seekers - Interviewer asked deep details questions of structural, finishing & hondover of high rise building project.

Tell us how to improve this page.

People are getting interviews through

based on 1 Megha Engineering & Infrastructures interview
Referral
100%
Low Confidence
?
Low Confidence means the data is based on a small number of responses received from the candidates.

Interview Questions from Similar Companies

Tata Projects Interview Questions
4.3
 • 397 Interviews
Saint-Gobain Interview Questions
4.0
 • 169 Interviews
Dilip Buildcon Interview Questions
4.0
 • 138 Interviews
G R Infraprojects Interview Questions
4.1
 • 127 Interviews
AECOM Interview Questions
4.3
 • 109 Interviews
Worley Interview Questions
4.1
 • 105 Interviews
View all
Megha Engineering & Infrastructures Senior Project Manager Salary
based on 17 salaries
₹13 L/yr - ₹23.4 L/yr
33% less than the average Senior Project Manager Salary in India
View more details

Megha Engineering & Infrastructures Senior Project Manager Reviews and Ratings

based on 2 reviews

4.0/5

Rating in categories

3.0

Skill development

3.5

Work-Life balance

3.0

Salary & Benefits

4.0

Job Security

3.0

Company culture

2.0

Promotions/Appraisal

3.5

Work Satisfaction

Explore 2 Reviews and Ratings
Senior Engineer
880 salaries
unlock blur

₹3 L/yr - ₹11.5 L/yr

Engineer
867 salaries
unlock blur

₹2.2 L/yr - ₹6.8 L/yr

Associate Manager
490 salaries
unlock blur

₹4.8 L/yr - ₹15.5 L/yr

Mechanical Engineer
398 salaries
unlock blur

₹2 L/yr - ₹7.2 L/yr

Civil Engineer
359 salaries
unlock blur

₹2 L/yr - ₹8.2 L/yr

Explore more salaries
Compare Megha Engineering & Infrastructures with

Larsen & Toubro Limited

4.0
Compare

Tata Projects

4.3
Compare

GMR Group

4.1
Compare

Hindustan Construction Company

4.2
Compare

Calculate your in-hand salary

Confused about how your in-hand salary is calculated? Enter your annual salary (CTC) and get your in-hand salary
Did you find this page helpful?
Yes No
write
Share an Interview