I was interviewed in Dec 2024.
Total Float is the amount of time an activity can be delayed without delaying the project completion date, while Free Float is the amount of time an activity can be delayed without delaying the early start of its successor activity.
Total Float is calculated by subtracting Early Start (ES) from Late Start (LS) or Early Finish (EF) from Late Finish (LF).
Free Float is calculated by subtracting Early Start (ES) of the succ...
Earned Value Analysis (EVA) is a project management technique used to measure project performance and progress by comparing planned work with actual work completed.
EVA integrates scope, schedule, and cost to provide a comprehensive view of project performance.
Key EVA metrics include Planned Value (PV), Earned Value (EV), and Actual Cost (AC).
EVA helps in forecasting project outcomes, identifying variances, and making d...
Key aspects to consider in delay analysis include identifying causes, assessing impact, analyzing critical path, and determining responsibility.
Identifying the causes of delays, such as design changes, weather conditions, or resource constraints
Assessing the impact of delays on the project timeline and budget
Analyzing the critical path to determine which activities are most critical to the project schedule
Determining r...
I would rate my proficiency in P6/MSP as an 8 out of 10.
I have extensive experience using P6/MSP in previous projects.
I have successfully created and managed complex schedules using P6/MSP.
I have received positive feedback on my proficiency in P6/MSP from colleagues and supervisors.
Different types of contracts include fixed-price, cost-reimbursable, time and materials, and unit price contracts.
Fixed-price contracts: Price is agreed upon upfront and does not change regardless of actual costs incurred.
Cost-reimbursable contracts: Contractor is reimbursed for all allowable costs incurred, plus a fee.
Time and materials contracts: Payment is based on actual hours worked and materials used, with a pre-...
I applied via Naukri.com and was interviewed in Mar 2024. There was 1 interview round.
Delay analysis methods are used to determine the causes and impacts of project delays.
There are various methods of delay analysis such as Critical Path Method (CPM), Time Impact Analysis (TIA), Impacted As-Planned, and As-Built.
Each method has its own advantages and limitations, and the choice of method depends on the specific circumstances of the project.
CPM is a commonly used method that analyzes the project schedule...
I applied via Walk-in and was interviewed before Sep 2023. There were 2 interview rounds.
Through a job posting on LinkedIn
Found job posting on LinkedIn
Researched company after seeing job posting
Connected with current employees on LinkedIn
Received referral from a friend or colleague
I have 8 years of experience working on high rise projects with contractor companies.
I have worked on multiple high rise projects ranging from 20 to 50 stories.
Managed structural design and construction of high rise buildings.
Collaborated with architects, contractors, and clients to ensure project success.
Asking about Experience like structure, finishing.
What is testing of Steel IS CODE
BILLING OF IS CODE
BBS IS CODE.
CMD IS CODE.
SAFETY HAZARD ANALYSIS.
CONSTRUCTION METHOD STATEMENT.
TYPES OF PLASTER
OUTER PLASTER THICKNESS.
INNER PLASTER THICKNESS.
Leighton Contractors interview questions for popular designations
Get interview-ready with Top Leighton Contractors Interview Questions
The procedure of laying tile and granite involves preparing the surface, applying adhesive, laying the tiles/granite, grouting, and sealing.
Prepare the surface by ensuring it is clean, level, and dry.
Apply adhesive to the surface using a trowel, ensuring even coverage.
Lay the tiles/granite starting from the center and working outwards in a pattern.
Grout the tiles/granite by filling the gaps between them with grout and ...
I was interviewed in Aug 2022.
7years as Lifting supervisor in construction
I have been working in the construction industry for 10 years.
I started as a laborer and worked my way up to a carpenter.
I have experience in both residential and commercial construction.
I have been a supervisor for the past 3 years.
I am familiar with safety regulations and have a good track record in ensuring compliance.
Yes, I have 7 years of experience as a lifting supervisor.
During my 7 years of experience, I have supervised various lifting operations including heavy machinery, construction materials, and personnel lifts.
I have ensured that all lifting operations are carried out safely and in compliance with relevant regulations and standards.
I have also trained and supervised lifting teams, conducted risk assessments, and developed...
I applied via Referral and was interviewed before May 2023. There was 1 interview round.
I applied via Referral and was interviewed before Aug 2022. There were 2 interview rounds.
I have worked with a variety of equipments including HVAC systems, fire protection systems, plumbing systems, and electrical systems.
HVAC systems
Fire protection systems
Plumbing systems
Electrical systems
I applied via Walk-in and was interviewed before Feb 2022. There were 3 interview rounds.
Top trending discussions
The duration of Leighton Contractors interview process can vary, but typically it takes about less than 2 weeks to complete.
based on 17 interviews
Interview experience
based on 393 reviews
Rating in categories
Assistant Manager
16
salaries
| ₹0 L/yr - ₹0 L/yr |
Project Engineer
16
salaries
| ₹0 L/yr - ₹0 L/yr |
Senior Civil Engineer
15
salaries
| ₹0 L/yr - ₹0 L/yr |
Senior Engineer
13
salaries
| ₹0 L/yr - ₹0 L/yr |
Senior Quantity Surveyor
11
salaries
| ₹0 L/yr - ₹0 L/yr |
Larsen & Toubro Limited
Tata Projects
Shapoorji Pallonji Group
Hindustan Construction Company