Filter interviews by
I applied via LinkedIn and was interviewed in Aug 2023. There were 3 interview rounds.
To work in oil and gas refinery, one must have a strong understanding of piping systems, safety regulations, and industry standards.
Obtain a degree in engineering or a related field
Gain experience through internships or entry-level positions
Familiarize yourself with industry-specific software and tools
Stay updated on safety regulations and best practices
Develop strong communication and problem-solving skills
To work in oil and gas refinery erection plan, one must have knowledge of piping design, construction codes, safety regulations, and project management.
Understand piping design principles and specifications
Ensure compliance with construction codes and standards
Adhere to safety regulations and protocols
Coordinate with various teams for project management
Review and interpret engineering drawings and documents
There are two main types of cranes: mobile cranes and tower cranes.
Mobile cranes are versatile and can be easily moved from one location to another. They are commonly used for construction projects.
Tower cranes are fixed to the ground and are often used for tall buildings or structures that require heavy lifting at great heights.
I applied via Naukri.com and was interviewed before Nov 2021. There were 2 interview rounds.
Top trending discussions
I applied via Walk-in and was interviewed in Jun 2023. There were 2 interview rounds.
The process of making a minor bridge involves planning, design, construction, and inspection.
1. Planning phase involves determining the location, size, and type of bridge needed.
2. Design phase includes creating detailed drawings and calculations for the bridge structure.
3. Construction phase involves building the foundation, supports, and deck of the bridge.
4. Inspection phase ensures the bridge meets safety and quali...
Piling point can be assured by conducting thorough soil investigation, using appropriate piling equipment, and monitoring the piling process.
Conduct soil investigation to determine soil conditions and suitability for piling.
Select appropriate piling equipment based on soil conditions and project requirements.
Monitor the piling process to ensure proper installation and alignment of piles.
Perform load tests on completed
The execution of an elevated viaduct involves various tasks such as pile foundation, pier construction, post-tensioning girders, and bridge structures.
Tasks include pile foundation construction for the viaduct, pier construction for support, post-tensioning of girders for strength, and bridge structure assembly.
Activities also involve conducting load tests, NDT tests, deflection tests, and steel reconciliation for qual...
posted on 11 Oct 2021
I applied via Company Website and was interviewed in Sep 2021. There was 1 interview round.
I applied via Company Website and was interviewed before Jan 2022. There were 3 interview rounds.
based on 1 interview
Interview experience
based on 33 reviews
Rating in categories
Assistant Manager
726
salaries
| ₹4.9 L/yr - ₹19 L/yr |
Manager
328
salaries
| ₹10.2 L/yr - ₹30 L/yr |
Senior Engineer
253
salaries
| ₹4.3 L/yr - ₹12 L/yr |
Piping Engineer
138
salaries
| ₹2.5 L/yr - ₹11 L/yr |
Assistant General Manager
118
salaries
| ₹17 L/yr - ₹35 L/yr |
AECOM
Apco Infratech
Saipem
Aarvee Associates