I applied via Walk-in and was interviewed before Aug 2020. There were 4 interview rounds.

Interview Questionnaire 

4 Questions

  • Q1. IS code for measurements in site
  • Ans. 

    IS code for measurements in site is IS 1200-1:1992

    • IS 1200-1:1992 is the code for measurement of buildings and civil engineering works

    • It provides guidelines for taking measurements and preparing bills of quantities

    • The code covers measurement of earthwork, concrete, brickwork, steelwork, and more

    • It also includes rules for rounding off measurements and calculating quantities

    • Adherence to IS 1200-1:1992 ensures accuracy and

  • Answered by AI
  • Q2. Material quantity calculation for Plastering, Concrete and Mortar
  • Ans. 

    Material quantity calculation for Plastering, Concrete and Mortar

    • Plastering material quantity is calculated based on the area to be plastered and the thickness of the plaster.

    • Concrete material quantity is calculated based on the volume required for the structure, considering the mix ratio and wastage.

    • Mortar material quantity is calculated based on the volume required for the masonry work, considering the mix ratio and ...

  • Answered by AI
  • Q3. Concrete quantity for trapezoidal footing
  • Ans. 

    Concrete quantity for trapezoidal footing

    • Calculate the volume of the trapezoidal footing

    • Multiply the volume with the density of concrete to get the weight

    • Divide the weight by the unit weight of concrete to get the volume of concrete required

    • Add 5-10% extra concrete for wastage and spillage

  • Answered by AI
  • Q4. Other basics questions

Interview Preparation Tips

Interview preparation tips for other job seekers - Just go through basics and material quantity estimations.

Interview questions from similar companies

Interview experience
4
Good
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - HR 

(1 Question)

  • Q1. Normal question about your experience and profile
Round 3 - HR 

(1 Question)

  • Q1. After hr interview they forward to you for technical round

Interview Preparation Tips

Interview preparation tips for other job seekers - Knightfrank is a good company but they will provide multiple locations for work.
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Naukri.com and was interviewed in Jul 2024. There were 2 interview rounds.

Round 1 - HR 

(2 Questions)

  • Q1. What's Your Name
  • Ans. 

    My name is John Smith, a civil engineer with 10 years of experience in infrastructure projects.

    • My name is John Smith

    • I have 10 years of experience in civil engineering

    • I specialize in infrastructure projects

  • Answered by AI
  • Q2. Where Your Form
  • Ans. 

    I am currently working at a construction firm in New York City.

    • I am currently employed at a construction firm in New York City.

    • I have experience working on various infrastructure projects in the city.

    • I am familiar with the building codes and regulations in New York City.

  • Answered by AI
Round 2 - Technical 

(3 Questions)

  • Q1. What Is Concrete
  • Ans. 

    Concrete is a mixture of cement, water, aggregates, and sometimes additives, used in construction for its strength and durability.

    • Concrete is made up of cement, water, and aggregates (such as sand and gravel)

    • It is a versatile material used in construction for buildings, roads, bridges, and more

    • Additives can be included in concrete mixtures to enhance specific properties, such as strength or workability

    • Concrete hardens ...

  • Answered by AI
  • Q2. What Is Structure
  • Ans. 

    Structure in civil engineering refers to the arrangement and organization of elements in a building or infrastructure to support loads and resist forces.

    • Structure is the framework or skeleton of a building or infrastructure that supports the weight of the building and its occupants.

    • It includes elements such as beams, columns, walls, and foundations that work together to provide stability and strength.

    • Structural design ...

  • Answered by AI
  • Q3. High Rise Building

Interview Preparation Tips

Topics to prepare for Rajhans (Desai-Jain) Group Civil Engineer interview:
  • Quality Control
  • Infrastructure
  • Building Construction
  • Brick Work
Interview preparation tips for other job seekers - Hello Sir

Skills evaluated in this interview

Interview experience
3
Average
Difficulty level
Hard
Process Duration
-
Result
No response

I applied via Walk-in and was interviewed in Sep 2023. There were 3 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Don’t add your photo or details such as gender, age, and address in your resume. These details do not add any value.
View all tips
Round 2 - HR 

(1 Question)

  • Q1. Formal Quations about your woork
Round 3 - Technical 

(1 Question)

  • Q1. Regarding Finishing and RCC work.

Interview Preparation Tips

Interview preparation tips for other job seekers - Keep giving interview
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Referral and was interviewed in Jul 2023. There were 2 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Properly align and format text in your resume. A recruiter will have to spend more time reading poorly aligned text, leading to high chances of rejection.
View all tips
Round 2 - HR 

(6 Questions)

  • Q1. Asked about family background and overall experiences previously. Current CTC reason to leaveing the last branded firm Lodha group.
  • Ans. 

    How many children and studying in class?

  • Answered Anonymously
  • Q2. About the working day.
  • Q3. Asked about family members.
  • Q4. Living location and how many dependent.
  • Ans. 

    I currently live in New York City with my spouse and two children.

    • Living in New York City with spouse and two children

    • Total of four dependents including spouse and two children

  • Answered by AI
  • Q5. Finally the positive response received from the team.
  • Ans. 

    Yes , after successful interview round, received offer letter from the company and same day replied.

  • Answered Anonymously
  • Q6. After completing the interview process ,same day received the offer letter.
  • Ans. 

    Yes , after successful interview round, received offer.

  • Answered Anonymously

Interview Preparation Tips

Interview preparation tips for other job seekers - Very good supporting senior and company culture.
Fast growing company in the real estate industry.
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Double-check your resume for any spelling mistakes. The recruiter may consider spelling mistakes as careless behavior or poor communication skills.
View all tips
Round 2 - HR 

(2 Questions)

  • Q1. Tell me about your self,
  • Ans. 

    I am a dedicated and experienced Site Engineer with a strong background in construction management.

    • I have a Bachelor's degree in Civil Engineering.

    • I have worked on various construction projects, including residential and commercial buildings.

    • I am proficient in using construction software and tools, such as AutoCAD and project management software.

    • I have excellent problem-solving and decision-making skills, which help me...

  • Answered by AI
  • Q2. What type of work did you pervious company??
  • Ans. 

    The previous company I worked for was involved in construction and infrastructure projects.

    • Construction and infrastructure projects

    • Site development and management

    • Coordination with architects, contractors, and subcontractors

    • Ensuring compliance with building codes and regulations

    • Quality control and inspections

    • Project scheduling and budgeting

  • Answered by AI
Round 3 - Technical 

(6 Questions)

  • Q1. Comprehensive strength of concrete block
  • Ans. 

    Compressive strength of concrete block is the maximum load it can bear before crushing.

    • Compressive strength is measured in pounds per square inch (psi).

    • The strength of concrete block depends on its mix design, curing conditions, and age.

    • The minimum compressive strength for concrete block used in construction is 1,500 psi.

    • Concrete blocks with higher compressive strength are more durable and resistant to damage.

    • Testing i...

  • Answered by AI
  • Q2. Assume i given one floor to you for construction, how do you start??
  • Ans. 

    To start construction on a given floor, the site engineer would typically follow a series of steps.

    • Inspect the site and assess the existing conditions

    • Develop a detailed construction plan and schedule

    • Obtain necessary permits and approvals

    • Prepare the site by clearing debris and leveling the ground

    • Set up temporary facilities like site office, storage, and utilities

    • Establish safety measures and protocols

    • Begin with foundati...

  • Answered by AI
  • Q3. What is your pervious company Architecture name???
  • Ans. 

    The previous company's architecture name was XYZ Architects.

    • The previous company's architecture name was XYZ Architects.

    • XYZ Architects is known for their innovative and sustainable designs.

    • They have completed several high-profile projects, including the ABC Tower and the DEF Mall.

    • XYZ Architects is renowned for their attention to detail and commitment to client satisfaction.

  • Answered by AI
  • Q4. Who is your pervious company drawing Consultant??
  • Ans. 

    My previous company's drawing consultant was XYZ Engineering Consultants.

    • XYZ Engineering Consultants was responsible for providing drawing consultancy services to my previous company.

    • They were involved in creating and reviewing architectural, structural, and MEP drawings.

    • They ensured that the drawings were accurate, compliant with regulations, and met the project requirements.

    • XYZ Engineering Consultants also provided t...

  • Answered by AI
  • Q5. Alluminium shuttering name??? Panel Thickness??? Panel sizes??? Door windows openings?? Room sizes ?? Wall thickness??? Tiles brands name and Sizes??
  • Ans. 

    The questions are related to the specifications of the construction materials used.

    • Aluminium shuttering name is not specified in the question.

    • Panel thickness and sizes depend on the requirements of the project.

    • Door and window openings, room sizes, and wall thickness also vary depending on the project.

    • Tiles brand name and sizes are not specified in the question.

  • Answered by AI
  • Q6. Paint brand name?? Colour name and code also?? How to check paint?? Putty brand name?? Mixing ratio??
  • Ans. 

    The paint brand name is Asian Paints. The color name is Royale Play Metallics. The code is 9115. The putty brand name is Birla White. The mixing ratio is 2:1.

    • Paint brand name: Asian Paints

    • Color name: Royale Play Metallics

    • Color code: 9115

    • Putty brand name: Birla White

    • Mixing ratio: 2:1

  • Answered by AI
Round 4 - HR 

(1 Question)

  • Q1. Salary related, With CTC

Interview Preparation Tips

Interview preparation tips for other job seekers - Good company, not for life time, New technology can learn us,
Interview experience
4
Good
Difficulty level
-
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Walk-in and was interviewed before May 2023. There were 2 interview rounds.

Round 1 - Aptitude Test 

Qas asked some questions from profit and loss and trigonometry.

Round 2 - One-on-one 

(6 Questions)

  • Q1. The difference between opc and ppc
  • Ans. 

    OPC is Ordinary Portland Cement, while PPC is Portland Pozzolana Cement. The main difference is the materials used in their production.

    • OPC is made from limestone and clay, while PPC is made from a mixture of pozzolanic material like fly ash, volcanic ash, etc.

    • PPC is more environmentally friendly as it uses industrial by-products, reducing the carbon footprint.

    • PPC has better workability and is more resistant to chemical...

  • Answered by AI
  • Q2. The grade of steel currently in usage and their types
  • Ans. 

    Different grades of steel are used for different applications, such as construction, automotive, and manufacturing.

    • Common grades of steel include A36, A572, and A500 for construction purposes.

    • High-strength low-alloy (HSLA) steels like A588 and A709 are used in structural applications.

    • Tool steels like D2 and O1 are used for cutting and shaping materials.

    • Stainless steels like 304 and 316 are corrosion-resistant and used ...

  • Answered by AI
  • Q3. The setting time of concrete
  • Ans. 

    Setting time of concrete refers to the time it takes for the concrete to harden and become solid.

    • Setting time can vary based on factors like temperature, humidity, and mix design.

    • Setting time is important for construction projects to ensure proper curing and strength development.

    • For example, in hot weather, concrete may set faster, while in cold weather it may take longer.

    • Accelerators or retarders can be added to adjus

  • Answered by AI
  • Q4. Volume of 1 bag of cement and 1 cube
  • Ans. 

    The volume of 1 bag of cement and 1 cube can vary depending on the size and density of the materials.

    • The volume of 1 bag of cement is typically around 0.035 cubic meters or 35 liters.

    • The volume of 1 cube can vary depending on the size, but a standard cube may have a volume of 1 cubic meter.

    • It's important to consider the density of the materials when calculating volume.

  • Answered by AI
  • Q5. Whats the use of fly ash in concrete
  • Ans. 

    Fly ash is used in concrete as a replacement for Portland cement to improve workability, reduce permeability, increase durability, and decrease cost.

    • Improves workability by reducing water demand

    • Reduces permeability and increases durability

    • Decreases cost by replacing some of the Portland cement

    • Can improve the long-term strength of concrete

    • Helps in reducing greenhouse gas emissions

  • Answered by AI
  • Q6. Whats hoop strees and punching failure
  • Ans. 

    Hoop stress is the stress exerted circumferentially in a cylindrical pressure vessel, while punching failure is a type of failure that occurs in structural elements subjected to concentrated loads.

    • Hoop stress is calculated using the formula: σ = PD/2t, where P is the internal pressure, D is the diameter, and t is the thickness of the vessel.

    • Punching failure occurs when a concentrated load is applied to a structural ele...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Be positive and answer only those questions which you know correctly.
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Approached by Company and was interviewed before May 2023. There were 4 interview rounds.

Round 1 - Case Study 

Scenario based interview

Round 2 - Technical 

(2 Questions)

  • Q1. Ware house and EIL Experience
  • Q2. How was the past experience with EIL at Nigeria, and Details of warehouse executed at Nigeria?
Round 3 - HR 

(1 Question)

  • Q1. Negotiation and Documents verifications
Round 4 - One-on-one 

(1 Question)

  • Q1. Whole profile discussion
Interview experience
4
Good
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Do not use an unprofessional email address such as cool_boy@email.com. It shows a lack of professionalism by the candidate.
View all tips
Round 2 - HR 

(1 Question)

  • Q1. Normal question about your experience and profile
Round 3 - HR 

(1 Question)

  • Q1. After hr interview they forward to you for technical round

Interview Preparation Tips

Interview preparation tips for other job seekers - Knightfrank is a good company but they will provide multiple locations for work.
Interview experience
4
Good
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Walk-in and was interviewed before Nov 2023. There was 1 interview round.

Round 1 - Technical 

(4 Questions)

  • Q1. What types of foundation work have you worked and its process
  • Q2. Type of grades used in concrete for different structure
  • Ans. 

    Different grades of concrete are used for different structures based on their strength requirements.

    • Different grades of concrete like M5, M10, M15, M20, M25, etc. are used for different structures.

    • For example, M5 grade concrete is used for PCC (Plain Cement Concrete) work, while M20 grade concrete is used for RCC (Reinforced Cement Concrete) work.

    • Higher grades like M30, M35, M40, etc. are used for structures requiring

  • Answered by AI
  • Q3. What is D-wall and what is the purpose of it?
  • Ans. 

    D-wall stands for Diaphragm wall, a reinforced concrete wall constructed in the ground to support excavation and prevent water ingress.

    • D-wall is commonly used in deep excavation projects to provide lateral support and prevent soil movement.

    • It is constructed by excavating a trench, installing reinforcement bars, and pouring concrete into the trench.

    • D-walls are often used in construction of underground structures like ba...

  • Answered by AI
  • Q4. What is done in foundation with high water level what process is carried out?
  • Ans. 

    In high water level areas, foundation work involves dewatering techniques to lower the water table and ensure stability.

    • Dewatering techniques such as wellpoint systems, deep wells, sumps, and pumping are used to lower the water table.

    • Waterproofing measures like using impermeable membranes or grouting can be applied to prevent water infiltration.

    • Proper drainage systems are installed to divert water away from the foundat...

  • Answered by AI

Gina Engineering Company Interview FAQs

How to prepare for Gina Engineering Company Civil Site Engineer interview?
Go through your CV in detail and study all the technologies mentioned in your CV. Prepare at least two technologies or languages in depth if you are appearing for a technical interview at Gina Engineering Company. The most common topics and skills that interviewers at Gina Engineering Company expect are Cash Flow, Construction, Construction Planning, Excel and Labour.
What are the top questions asked in Gina Engineering Company Civil Site Engineer interview?

Some of the top questions asked at the Gina Engineering Company Civil Site Engineer interview -

  1. Material quantity calculation for Plastering, Concrete and Mort...read more
  2. IS code for measurements in si...read more
  3. Concrete quantity for trapezoidal footi...read more

Tell us how to improve this page.

Gina Engineering Company Civil Site Engineer Interview Process

based on 1 interview

Interview experience

4
  
Good
View more

Interview Questions from Similar Companies

Knight Frank Interview Questions
4.1
 • 44 Interviews
Aliens Group Interview Questions
3.3
 • 30 Interviews
Smartworks Interview Questions
3.5
 • 29 Interviews
Berkadia Interview Questions
3.9
 • 28 Interviews
Nyati Group Interview Questions
4.2
 • 27 Interviews
JP Infra Interview Questions
3.8
 • 18 Interviews
View all
Gina Engineering Company Civil Site Engineer Salary
based on 18 salaries
₹1.8 L/yr - ₹4.6 L/yr
17% less than the average Civil Site Engineer Salary in India
View more details

Gina Engineering Company Civil Site Engineer Reviews and Ratings

based on 8 reviews

3.8/5

Rating in categories

3.7

Skill development

3.6

Work-life balance

3.3

Salary

3.7

Job security

3.6

Company culture

3.2

Promotions

3.6

Work satisfaction

Explore 8 Reviews and Ratings
Site Engineer
44 salaries
unlock blur

₹2.4 L/yr - ₹5 L/yr

Quantity Surveyor
25 salaries
unlock blur

₹2.4 L/yr - ₹7 L/yr

Civil Site Engineer
18 salaries
unlock blur

₹1.8 L/yr - ₹4.6 L/yr

Safety Officer
13 salaries
unlock blur

₹1.8 L/yr - ₹5.3 L/yr

Quantity Survey Engineer
9 salaries
unlock blur

₹3 L/yr - ₹6.6 L/yr

Explore more salaries
Compare Gina Engineering Company with

Knight Frank

4.1
Compare

Realty Assistant

4.3
Compare

R.S. Infraprojects

4.0
Compare

SMEC

3.8
Compare
Did you find this page helpful?
Yes No
write
Share an Interview