  • Q1. Explanation of BBS in details
  • Ans. 

    BBS stands for Bar Bending Schedule, which is a detailed report that provides information about the reinforcement steel required for a construction project.

    • BBS is prepared by civil engineers to ensure the proper placement and quantity of reinforcement steel in a structure.

    • It includes details such as the diameter, length, and shape of each reinforcement bar.

    • BBS helps in estimating the quantity of steel required and assi...

  • Answered by AI

Interview questions from similar companies

Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I was interviewed in Dec 2024.

Round 1 - Technical 

(3 Questions)

  • Q1. What is the grade of concrete
  • Ans. 

    The grade of concrete refers to its strength and is determined by the ratio of cement to sand to aggregate.

    • The grade of concrete is typically denoted by a number followed by the letter 'M', such as M20, M30, etc.

    • The number in the grade represents the compressive strength of the concrete in megapascals (MPa) after 28 days of curing.

    • For example, M20 concrete has a compressive strength of 20 MPa, while M30 concrete has a ...

  • Answered by AI
  • Q2. What is the unit used for estimating painting work?
  • Ans. 

    The unit used for estimating painting work is square feet.

    • Square feet is commonly used to estimate the amount of paint needed for a project.

    • Other units like square meters can also be used depending on the region.

    • Calculations are based on the surface area to be painted.

  • Answered by AI
  • Q3. What you mean by RL in survey
  • Ans. 

    RL in survey stands for Reduced Level, which is the vertical distance between a point and a reference point.

    • RL is used in surveying to determine the elevation of a point relative to a known reference point.

    • It is commonly used in construction projects to ensure accurate leveling of structures and surfaces.

    • RL can be calculated using leveling instruments such as a dumpy level or a theodolite.

    • For example, if a benchmark ha...

  • Answered by AI
Round 2 - One-on-one 

(2 Questions)

  • Q1. Types of cement
  • Ans. 

    Types of cement include Portland cement, rapid-hardening cement, and sulfate-resistant cement.

    • Portland cement is the most common type and is used in general construction.

    • Rapid-hardening cement sets quickly and is often used in repair work.

    • Sulfate-resistant cement is used in areas where soil or water has high sulfate content.

  • Answered by AI
  • Q2. Size of columns
  • Ans. 

    The size of columns in civil engineering is determined based on the load they will support and the height of the structure.

    • Columns are sized based on the load they will support, with larger loads requiring larger columns.

    • The height of the structure also plays a role in determining column size, with taller structures requiring larger columns for stability.

    • Factors such as material strength, column spacing, and building c...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Prepare for the basic civil engineering concept and knowledge
Interview experience
3
Average
Difficulty level
Easy
Process Duration
Less than 2 weeks
Result
Not Selected

I applied via Naukri.com and was interviewed in Dec 2023. There was 1 interview round.

Round 1 - Technical 

(11 Questions)

  • Q1. What is the Least Count of dumpy level Staff Reading ?
  • Ans. 

    The least count of a dumpy level staff reading is typically 0.01 ft or 1 mm.

    • The least count is the smallest measurement that can be read on the scale of the dumpy level staff.

    • For most dumpy levels, the least count is 0.01 ft or 1 mm.

    • This means that the dumpy level can measure differences in elevation as small as 0.01 ft or 1 mm.

  • Answered by AI
  • Q2. Why Concrete Cover is provided for reinforcement ?
  • Ans. 

    Concrete cover is provided for reinforcement to protect it from corrosion, fire, and other environmental factors.

    • Concrete cover protects reinforcement from corrosion by preventing exposure to moisture and aggressive chemicals.

    • It provides fire resistance by acting as a barrier between the reinforcement and the fire.

    • Concrete cover helps in maintaining the bond between reinforcement and concrete, ensuring structural integ...

  • Answered by AI
  • Q3. What is tha volume of 50 kg bag of cement ?
  • Ans. 

    The volume of a 50 kg bag of cement varies depending on the density of the cement.

    • The volume of cement can be calculated using the formula: Volume = Mass / Density

    • The density of cement typically ranges from 1.1 to 1.6 g/cm^3

    • For example, if the density of the cement is 1.4 g/cm^3, the volume of a 50 kg bag would be approximately 35.71 liters

  • Answered by AI
  • Q4. What is Dessity of steel ?
  • Ans. 

    Ductility of steel refers to its ability to deform without breaking under stress.

    • Ductility is a crucial property in structural engineering as it allows steel to be shaped and formed into various structures.

    • Steel with high ductility can undergo significant deformation before failure.

    • Ductility is often measured by the percentage of elongation or reduction in area during a tensile test.

    • Examples of ductile materials includ

  • Answered by AI
  • Q5. What is tha size of concrete Cube ?
  • Ans. 

    The size of a concrete cube is typically 150mm x 150mm x 150mm.

    • Standard size of a concrete cube is 150mm x 150mm x 150mm

    • Used for testing the compressive strength of concrete

    • Other sizes like 100mm x 100mm x 100mm or 200mm x 200mm x 200mm may also be used

  • Answered by AI
  • Q6. What is tha Role of a Civil Engineer at Site ?
  • Ans. 

    Civil engineers at site are responsible for overseeing construction projects, ensuring they are completed safely, on time, and within budget.

    • Supervising construction activities to ensure compliance with design specifications and safety standards

    • Managing resources and materials efficiently to meet project deadlines

    • Collaborating with architects, contractors, and other stakeholders to resolve any issues that may arise

    • Cond...

  • Answered by AI
  • Q7. What is tha minimum concrete grade for RCC work ?
  • Ans. 

    Minimum concrete grade for RCC work is M20.

    • Minimum concrete grade for RCC work is M20 as per IS 456:2000.

    • Higher grades like M25, M30, M35, etc. can also be used depending on structural requirements.

    • Concrete grades indicate the compressive strength of concrete after 28 days of curing.

    • Higher grades are used for structures requiring higher strength like bridges, high-rise buildings, etc.

  • Answered by AI
  • Q8. What is rha dsssity of Unit wait of cement ?
  • Ans. 

    The density of unit weight of cement is typically around 1440 kg/m^3.

    • The density of unit weight of cement is commonly around 1440 kg/m^3.

    • This value can vary slightly depending on the type and brand of cement.

    • Density is a measure of mass per unit volume, in this case, kilograms per cubic meter.

  • Answered by AI
  • Q9. What is tha Grade of Cement ?
  • Ans. 

    Grade of cement refers to the strength of the cement as per the compressive strength test.

    • Grade of cement is determined by the compressive strength of cement mortar cubes at 28 days of curing.

    • Common grades of cement include 33, 43, and 53 where the number represents the compressive strength in MPa.

    • Higher grade cement is used for structures requiring higher strength like bridges and high-rise buildings.

  • Answered by AI
  • Q10. What is the Slump value of concrete for Normal RCC work
  • Ans. 

    The slump value of concrete for Normal RCC work is typically between 25-75 mm.

    • The slump value of concrete for Normal RCC work is usually around 50 mm.

    • The slump value can vary based on the specific requirements of the project and the mix design.

    • A higher slump value indicates a more workable concrete mix, while a lower slump value may be used for specialized applications.

    • It is important to test the slump value of concret...

  • Answered by AI
  • Q11. How many cube filled for 1 cubic meter concrete ?
  • Ans. 

    Generally, 7-8 bags of cement are required to fill 1 cubic meter of concrete.

    • On average, 7-8 bags of cement are needed to fill 1 cubic meter of concrete.

    • The exact number of bags may vary based on the mix design and proportions used.

    • For example, if each bag of cement is 50 kg, then 7 bags would be 350 kg and 8 bags would be 400 kg.

  • Answered by AI

Interview Preparation Tips

Topics to prepare for Rohan Builders Civil Engineer interview:
  • Building Structure
  • Building Construction
  • Site work
  • Billing
Interview preparation tips for other job seekers - This is a good company bit don't trust any one , one day this company will remove you like me
Interview experience
5
Excellent
Difficulty level
Hard
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Walk-in and was interviewed in Feb 2024. There were 3 interview rounds.

Round 1 - Aptitude Test 

Building and roads related

Round 2 - HR 

(1 Question)

  • Q1. Salary and other details
Round 3 - Technical 

(2 Questions)

  • Q1. Building and roads project related
  • Q2. Like part of building
Interview experience
4
Good
Difficulty level
Moderate
Process Duration
2-4 weeks
Result
-

I was interviewed in Jul 2023.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - Technical 

(2 Questions)

  • Q1. Steel estimation in a beam
  • Ans. 

    Steel estimation in a beam involves calculating the quantity of steel required for reinforcement.

    • Calculate the total length of steel bars required based on the dimensions of the beam and the spacing of the bars.

    • Determine the diameter of the steel bars to be used for reinforcement.

    • Consider the grade of steel and the design requirements to calculate the total weight of steel needed.

    • Account for wastage and additional rein...

  • Answered by AI
  • Q2. What was your role in the last job
Round 3 - One-on-one 

(2 Questions)

  • Q1. Tell me about yourself
  • Q2. Tell me about the projects you have been involved in.
Round 4 - HR 

(1 Question)

  • Q1. What is your expectation
Interview experience
4
Good
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Walk-in and was interviewed in Mar 2023. There were 2 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Don’t add your photo or details such as gender, age, and address in your resume. These details do not add any value.
View all tips
Round 2 - One-on-one 

(5 Questions)

  • Q1. What is most important thing in your life, is that will give you success?
  • Q2. What's your perfect field in this job?
  • Q3. How do you handle any new problems?
  • Q4. Do you have any extra qualities?
  • Q5. Why should we hire you?

Interview Preparation Tips

Topics to prepare for Aparna Constructions and Estates Civil Engineer interview:
  • Watch related YouTube content
  • Practice your knowledge
Interview preparation tips for other job seekers - 1. Don't be panic.
2. Always say anything with confidence
3. reply politely
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Not Selected

I applied via Referral and was interviewed in Dec 2023. There were 2 interview rounds.

Round 1 - Group Discussion 

Quality control and waste management

Round 2 - Aptitude Test 

Maths reasoning and core subjects

Interview Preparation Tips

Topics to prepare for Godrej Properties Civil Engineer interview:
  • RCC
Interview preparation tips for other job seekers - Many questions related to ambition box
Interview experience
4
Good
Difficulty level
Hard
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Company Website and was interviewed in Apr 2023. There were 3 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Properly align and format text in your resume. A recruiter will have to spend more time reading poorly aligned text, leading to high chances of rejection.
View all tips
Round 2 - Technical 

(3 Questions)

  • Q1. Any technical questions ask me
  • Q2. Difrance between OPC cement and PPC cement
  • Ans. 

    OPC cement is made from limestone and clay, while PPC cement is made from fly ash and clay.

    • OPC cement has higher strength and is used for construction of high-rise buildings and bridges.

    • PPC cement has better workability and is used for plastering and finishing works.

    • PPC cement is more eco-friendly as it uses industrial waste as a raw material.

    • OPC cement is costlier than PPC cement.

    • OPC cement is commonly used in areas w...

  • Answered by AI
  • Q3. What is two way slab
  • Ans. 

    A two way slab is a type of reinforced concrete slab that is supported by beams on all four sides.

    • Two way slab is used in buildings with large column spacing

    • It is designed to resist both positive and negative bending moments

    • It is commonly used in parking garages, commercial buildings, and residential buildings

    • Two way slab is more economical than one way slab for larger spans

  • Answered by AI
Round 3 - Assignment 

Dgijvcctuhgcvh hjjcc ghjj

Interview Questionnaire 

1 Question

  • Q1. Minivan related questions
Interview experience
4
Good
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I was interviewed in Dec 2024.

Round 1 - Technical 

(2 Questions)

  • Q1. What is the full form of SBC
  • Q2. Find different RLs from the given figure
Round 2 - One-on-one 

(1 Question)

  • Q1. What is the Diamter of TBM

Tell us how to improve this page.

VRAJ INFRASTRUCTURE Civil Engineer Interview Process

based on 1 interview

Interview experience

5
  
Excellent
View more
VRAJ INFRASTRUCTURE Civil Engineer Salary
based on 9 salaries
₹1.8 L/yr - ₹5.5 L/yr
11% less than the average Civil Engineer Salary in India
View more details

VRAJ INFRASTRUCTURE Civil Engineer Reviews and Ratings

based on 2 reviews

4.0/5

Rating in categories

3.2

Skill development

3.2

Work-life balance

3.4

Salary

2.4

Job security

1.7

Company culture

2.5

Promotions

3.2

Work satisfaction

Explore 2 Reviews and Ratings
Civil Site Engineer
46 salaries
unlock blur

₹1.5 L/yr - ₹4.8 L/yr

Site Engineer
25 salaries
unlock blur

₹2.2 L/yr - ₹4.8 L/yr

Civil Engineer
9 salaries
unlock blur

₹1.8 L/yr - ₹5.5 L/yr

Senior Surveyor
6 salaries
unlock blur

₹3.5 L/yr - ₹4 L/yr

Junior Engineer Civil
6 salaries
unlock blur

₹1.2 L/yr - ₹2.5 L/yr

Explore more salaries
Compare VRAJ INFRASTRUCTURE with

Larsen & Toubro Limited

4.0
Compare

Tata Projects

4.2
Compare

GMR Group

4.1
Compare

Hindustan Construction Company

4.2
Compare
Did you find this page helpful?
Yes No
write
Share an Interview