Formation width is the width of the prepared surface of the subgrade and the base course of a road or highway.
Formation width is the width of the prepared surface of the subgrade and the base course of a road or highway.
It is the width of the foundation of the road or highway.
It is important to ensure that the formation width is sufficient to support the weight of the traffic that will use the road or highway.
The forma...
Crown is the slope given to the surface of a road or highway to allow for proper drainage.
Crown is the highest point of the road surface, usually at the centerline.
It is designed to allow water to drain off the road surface and prevent pooling.
The slope of the crown depends on the road's width and the amount of rainfall in the area.
Crown is important for safety as it reduces the risk of hydroplaning and improves visibi...
PQC stands for Pavement Quality Concrete. It is a type of concrete used for road construction.
PQC is a high-quality concrete mix used for the top layer of road construction.
It is designed to provide a smooth and durable surface for vehicles to travel on.
PQC is typically used for highways, airports, and other high-traffic areas.
It is made with a higher strength and lower water-cement ratio than regular concrete.
PQC is a...
I applied via Recruitment Consultant and was interviewed before Jan 2020. There were 3 interview rounds.
Top trending discussions
posted on 17 Feb 2020
I applied via Company Website and was interviewed before Feb 2019. There were 2 interview rounds.
posted on 30 Sep 2022
I applied via Approached by Company and was interviewed in Aug 2022. There were 5 interview rounds.
The wastage percentages of construction materials vary depending on the type of material and the project requirements.
Wastage percentages can range from 2-5% for cement and steel to 10-15% for bricks and tiles.
Factors that affect wastage include the skill level of workers, the quality of materials, and the complexity of the project.
Proper planning and management can help minimize wastage and reduce project costs.
Regula...
Rolling margin of steel is the difference between the cost of producing steel and the selling price.
It is a measure of profitability for steel manufacturers.
It is calculated by subtracting the cost of production from the selling price.
A higher rolling margin indicates higher profitability.
Factors that affect rolling margin include raw material costs, energy costs, and market demand.
Worker and machinery productivity are crucial for effective planning.
Worker productivity can be measured by the amount of work completed in a given time period.
Machinery productivity can be measured by the amount of output produced by the machinery in a given time period.
Both worker and machinery productivity should be taken into account when planning to ensure efficient use of resources.
For example, if workers are mor...
Deductions in client bill include taxes, discounts, late fees, and service charges.
Taxes: Sales tax, VAT, GST, etc.
Discounts: Promotions, loyalty rewards, bulk discounts, etc.
Late fees: Charges for overdue payments.
Service charges: Fees for additional services provided.
Retention and TDS are important factors to consider in subcontractor billing.
Retention refers to the amount of money withheld by the client as a form of security against any defects or issues that may arise after the project is completed.
TDS (Tax Deducted at Source) is the tax deducted by the client from the subcontractor's payment and deposited with the government.
Both retention and TDS should be clearly mentioned in ...
posted on 10 Nov 2021
I will assess the situation and take necessary actions to minimize the impact on the project timeline.
Check with the supplier for the reason of delay and expected delivery date
Evaluate the impact on the project timeline and inform the project team
Explore alternative options such as sourcing from a different supplier or adjusting the project schedule
Communicate the revised plan to all stakeholders and ensure timely deli...
To calculate cement and sand for 1 sqm cm 1:4, use the formula: (1/5.5) * 1 = 0.18 cubic meters of cement and (4/5.5) * 1 = 0.73 cubic meters of sand.
The ratio of cement to sand is 1:4
Calculate the total volume of the mixture, which is 1 sqm cm
Divide the total volume by the sum of the ratio (1+4=5)
Multiply the quotient by the individual ratio to get the volume of cement and sand
Convert the volume to weight using the de
Price escalation refers to the increase in the price of goods or services over time.
It is a common phenomenon in the market due to inflation, changes in demand and supply, and other economic factors.
Price escalation can also occur due to changes in the cost of production, such as raw material costs, labor costs, and transportation costs.
For example, the price of gasoline may escalate due to an increase in the cost of c...
posted on 16 Aug 2021
I applied via Company Website and was interviewed in Jul 2021. There were 5 interview rounds.
The question implies that the interviewer is questioning the candidate's potential departure from the company.
The question suggests that the interviewer may have concerns about the candidate's long-term commitment.
The candidate should address the concern by explaining their career goals and commitment to the role.
Providing examples of past experiences where the candidate has demonstrated long-term commitment can help a
posted on 19 Dec 2019
I applied via Referral and was interviewed before Dec 2018. There was 1 interview round.
I applied via Approached by Company and was interviewed in Nov 2021. There were 2 interview rounds.
Yes
IRC codes and SP are commonly used in structural engineering
IRC codes refer to the Indian Road Congress codes, which provide guidelines for the design and construction of roads and bridges in India
SP refers to the Standards and Practices, which are specific codes and regulations followed in the field of structural engineering
Engineers use IRC codes and SP to ensure the safety, stability, and durability of structures
...
based on 2 interviews
Interview experience
based on 75 reviews
Rating in categories
Site Engineer
7
salaries
| ₹2.5 L/yr - ₹4 L/yr |
Civil Site Engineer
7
salaries
| ₹3.5 L/yr - ₹4 L/yr |
Assistant Manager
6
salaries
| ₹2.7 L/yr - ₹11.9 L/yr |
Civil Engineer
6
salaries
| ₹1.5 L/yr - ₹8.9 L/yr |
Senior Engineer
5
salaries
| ₹5 L/yr - ₹6.1 L/yr |
L&T Construction
Simplex Infrastructures
ITD Cementation India
Ashoka Buildcon