An audit is conducted in stages from planning to completion, involving risk assessment, testing, documentation, and reporting.
1. Planning stage involves understanding the client's business, identifying risks, and developing an audit plan.
2. Risk assessment is crucial to determine the areas to focus on during the audit.
3. Testing stage includes gathering evidence, performing analytical procedures, and conducting substan...
I applied via Walk-in and was interviewed in May 2024. There was 1 interview round.
I previously worked at XYZ Company as a Quality Engineer for 3 years.
Worked at XYZ Company as a Quality Engineer
Experience of 3 years in the role
Implemented quality control processes and procedures
Collaborated with cross-functional teams to improve product quality
I was responsible for ensuring the quality of products and processes in my previous company.
Developed and implemented quality control procedures
Conducted quality audits and inspections
Collaborated with cross-functional teams to address quality issues
Provided training on quality standards and best practices
I applied via LinkedIn and was interviewed before Jun 2023. There was 1 interview round.
I audited the inventory of office supplies to ensure accuracy and proper documentation.
Conducted physical count of office supplies in storage rooms and cabinets
Checked inventory records against actual items on hand
Verified that all purchases and disposals were properly documented
Reconciled any discrepancies found during the audit
Prepared a report detailing audit findings and recommendations
I applied via Referral and was interviewed in Feb 2023. There were 3 interview rounds.
Time shifting can cause problems in quality control.
Time shifting can lead to incorrect data analysis and interpretation.
It can also cause delays in identifying and addressing quality issues.
Examples include delayed detection of defects in production processes or incorrect measurements due to time differences.
Proper time synchronization and documentation can help prevent time shifting problems.
Tube Investments of India interview questions for popular designations
I applied via Referral and was interviewed before Aug 2023. There was 1 interview round.
I applied via Walk-in and was interviewed before Nov 2021. There were 2 interview rounds.
I applied via Walk-in and was interviewed in Sep 2020. There were 3 interview rounds.
Top trending discussions
I applied via Naukri.com and was interviewed before Sep 2020. There was 1 interview round.
Hydrotest procedure is a process of testing the strength and integrity of a pressure vessel or pipeline by filling it with water and pressurizing it.
The vessel or pipeline is filled with water and pressurized to a specified level
The pressure is held for a specified amount of time to check for leaks or deformations
The test is usually performed before commissioning or after repairs
The test pressure and duration are deter...
HDD procedure refers to the process of installing and configuring a hard disk drive in a computer system.
Ensure the HDD is compatible with the computer system
Physically install the HDD in the appropriate bay
Connect the necessary cables to the HDD and motherboard
Configure the HDD in the BIOS settings
Format the HDD and install the operating system
Test the HDD for proper functionality
posted on 16 May 2023
I applied via Campus Placement
Communication Colleagues
posted on 8 Apr 2024
I applied via Approached by Company and was interviewed in Mar 2024. There were 3 interview rounds.
The duration of Tube Investments of India interview process can vary, but typically it takes about less than 2 weeks to complete.
based on 5 interviews
Interview experience
based on 885 reviews
Rating in categories
Assistant Manager
141
salaries
| ₹3.5 L/yr - ₹11.9 L/yr |
Senior Executive
127
salaries
| ₹4.3 L/yr - ₹9.5 L/yr |
Senior Engineer
81
salaries
| ₹2.5 L/yr - ₹7 L/yr |
Quality Inspector
80
salaries
| ₹1 L/yr - ₹3.5 L/yr |
Quality Engineer
74
salaries
| ₹1.4 L/yr - ₹4.9 L/yr |
L&T Construction
Simplex Infrastructures
ITD Cementation India
Ashoka Buildcon