Round 1 - Technical 

(5 Questions)

  • Q1. Why are remove the pile head.
  • Ans. 

    Pile heads are removed to allow for further construction or to ensure proper load transfer to the foundation.

    • To prepare for further construction on top of the piles

    • To ensure proper load transfer to the foundation

    • To facilitate the installation of pile caps or beams

    • To adjust the pile length if necessary

  • Answered by AI
  • Q2. How many deduction of 90 degree angle.
  • Ans. 

    There are four deductions of 90 degree angles.

    • A 90 degree angle is formed when two lines intersect at a right angle.

    • In a square, all four angles are 90 degrees.

    • In a rectangle, opposite angles are 90 degrees.

    • In a right triangle, one angle is always 90 degrees.

  • Answered by AI
  • Q3. What is static load test and dynamic load test.
  • Ans. 

    Static load test is used to measure the load capacity of a structure under a constant load, while dynamic load test is used to measure the response of a structure to varying loads.

    • Static load test involves applying a constant load to a structure and measuring its response over time.

    • Dynamic load test involves applying varying loads to a structure to simulate real-life conditions.

    • Static load test helps determine the maxi...

  • Answered by AI
  • Q4. How many tolerance of pile load test.
  • Ans. 

    The number of tolerance of pile load test depends on the specific project requirements and standards.

    • The number of tolerance of pile load test can vary based on the project specifications and standards.

    • Typically, a tolerance of +/- 5% to +/- 10% is considered acceptable for pile load tests.

    • Some projects may have more stringent tolerance requirements depending on the criticality of the structure.

    • It is important to refer...

  • Answered by AI
  • Q5. What is rang Density of bentonite and why is this use.
  • Ans. 

    Bentonite has a range density of 17-22 lb/gal and is used in civil engineering for drilling fluid, grouting, and sealing purposes.

    • Range density of bentonite is typically between 17-22 lb/gal.

    • Bentonite is used in civil engineering for various purposes such as drilling fluid, grouting, and sealing.

    • The range density of bentonite is important for determining its effectiveness in different applications.

    • Higher range density ...

  • Answered by AI

Skills evaluated in this interview

Interview experience
5
Excellent
Difficulty level
Easy
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Walk-in and was interviewed in Sep 2023. There were 3 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - HR 

(1 Question)

  • Q1. 1. Self indirection ? 2. What about the fall ceiling work ? 3. What kind of material using for waterproofing ? 4. What meaning of PPM ? 5. He was supervisor one door key is missing so what can you do ? 6. ...
  • Ans. 

    I am Loganathan Gangadharan I Finished diploma in civil engineering with 10 years experience in Construction Field. Building background to eat not come down

  • Answered Anonymously
Round 3 - Technical 

(4 Questions)

  • Q1. 1. 12 mm Steel Rod using for construction ok that lapping length how much
  • Ans. 

    The lapping length for a 12 mm steel rod used in construction is typically 60 times the diameter of the rod.

    • Lapping length is usually 60 times the diameter of the steel rod

    • For a 12 mm steel rod, the lapping length would be 12 mm x 60 = 720 mm

    • Lapping is done to ensure continuity and strength in the reinforcement

  • Answered by AI
  • Q2. What type of footting using the oman country
  • Ans. 

    In Oman, commonly used footings include spread footings, strip footings, and raft footings.

    • Spread footings are used for individual columns or walls and distribute the load over a larger area.

    • Strip footings are continuous footings that support a line of columns or walls.

    • Raft footings are used for large or irregularly shaped structures to distribute the load over a wider area.

    • In Oman, due to the sandy soil conditions, de...

  • Answered by AI
  • Q3. One concrete floor for broken so rectify the floor what kind of material using
  • Ans. 

    To rectify a broken concrete floor, materials like concrete mix, epoxy resin, or self-leveling compound can be used.

    • Use concrete mix to fill in the broken areas and level the floor.

    • Apply epoxy resin to seal cracks and strengthen the floor.

    • Consider using self-leveling compound for a smooth and even surface.

    • Ensure proper preparation and cleaning of the floor before applying any material.

    • Consult with a structural engineer

  • Answered by AI
  • Q4. Concrete setting times how many days
  • Ans. 

    Concrete setting times can vary depending on factors like temperature and mix design.

    • Concrete typically sets within 24-48 hours, but continues to harden over time.

    • Factors affecting setting time include temperature, humidity, and mix design.

    • For example, in hot weather, concrete may set faster, while in cold weather it may take longer.

    • Accelerators or retarders can be added to the mix to adjust setting times as needed.

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Only one advice strong answer

I applied via Recruitment Consulltant and was interviewed in Aug 2022. There was 1 interview round.

Round 1 - Technical 

(1 Question)

  • Q1. Bbs, shuttering, leveling, testing, quality.

Interview Preparation Tips

Interview preparation tips for other job seekers - Project monitoring, Project management, client management, project development, staff development skills

I applied via Naukri.com and was interviewed in Mar 2021. There were 3 interview rounds.

Interview Questionnaire 

1 Question

  • Q1. Quantity of excavation by 210 excavator in 10 hours
  • Ans. 

    The quantity of excavation by a 210 excavator in 10 hours depends on various factors such as soil type, operator efficiency, and machine capabilities.

    • The quantity of excavation can vary based on the type of soil. Harder soil may require more time and effort to excavate compared to softer soil.

    • The efficiency of the operator operating the excavator also plays a role. A skilled operator can complete more excavation work i...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Interview should have minimun time

I applied via Naukri.com and was interviewed before Jan 2020. There were 3 interview rounds.

Interview Questionnaire 

2 Questions

  • Q1. What is the tolerance in column checking?
  • Ans. 

    The tolerance in column checking refers to the acceptable deviation from the specified dimensions or alignment.

    • Tolerance is usually specified in the project specifications or codes.

    • It is important to ensure that the column is within the specified tolerance to ensure structural integrity.

    • Tolerance can vary depending on the type of column and its location in the structure.

    • For example, a column supporting a heavy load may...

  • Answered by AI
  • Q2. 1mm to 2mm

Interview Preparation Tips

Interview preparation tips for other job seekers - Basic practical knowledge Question of civil engineering.

I applied via Recruitment Consultant and was interviewed in May 2019. There were 5 interview rounds.

Interview Questionnaire 

2 Questions

  • Q1. Technical, that is what type of shuttering reinforcement works and time cycle of works, quantities of works you done....and last and
  • Q2. Importantly thay asked about safety (for me they asked safety measures in EXCAVATION)

Interview Preparation Tips

Interview preparation tips for other job seekers - Be knowledge what u worked i.e what details in your resume...
Awareness need in safety in every activity

I applied via Recruitment Consultant and was interviewed before Oct 2019. There was 1 interview round.

Interview Questionnaire 

2 Questions

  • Q1. Question ask about previous site experience.
  • Q2. Normal site questions bask about execution about R.C.C and steel

Interview Preparation Tips

Interview preparation tips for other job seekers - If you are aware about site work you can easily cleared interview

Tell us how to improve this page.

Interview Questions from Similar Companies

Tata Projects Interview Questions
4.3
 • 400 Interviews
GMR Group Interview Questions
4.1
 • 75 Interviews
GAMMON INDIA Interview Questions
3.9
 • 29 Interviews
View all

Tricon Infra Buildtech pvt.Ltd Senior Site Execution Engineer Reviews and Ratings

based on 1 review

5.0/5

Rating in categories

5.0

Skill development

5.0

Work-Life balance

5.0

Salary & Benefits

5.0

Job Security

5.0

Company culture

5.0

Promotions/Appraisal

5.0

Work Satisfaction

Explore 1 Review and Rating
Junior Engineer
43 salaries
unlock blur

₹2 L/yr - ₹3.6 L/yr

Senior Engineer
32 salaries
unlock blur

₹3 L/yr - ₹8.6 L/yr

Junior Engineer Civil
31 salaries
unlock blur

₹1.8 L/yr - ₹3.3 L/yr

Civil Site Engineer
28 salaries
unlock blur

₹1.1 L/yr - ₹5.4 L/yr

Planning Engineer
27 salaries
unlock blur

₹2.8 L/yr - ₹6.4 L/yr

Explore more salaries
Compare Tricon Infra Buildtech pvt.Ltd with

Larsen & Toubro Limited

4.0
Compare

Tata Projects

4.3
Compare

Shapoorji Pallonji Group

4.2
Compare

GMR Group

4.1
Compare

Calculate your in-hand salary

Confused about how your in-hand salary is calculated? Enter your annual salary (CTC) and get your in-hand salary
Did you find this page helpful?
Yes No
write
Share an Interview