To draw a Bending Moment diagram, one needs to determine the reactions, calculate the shear force and integrate it to get the bending moment.
Determine the reactions at the supports
Calculate the shear force at each section of the beam
Integrate the shear force to get the bending moment
Plot the bending moment diagram
Provisions checked for designing a beam/column according to IS Codes
Cross-sectional dimensions
Minimum reinforcement
Maximum spacing of bars
Clear cover to reinforcement
Grade of concrete and steel
Load-bearing capacity
Bending moment and shear force
Deflection limits
IS 456 and IS 800 are codes and provisions related to concrete and steel design respectively.
IS 456 provides guidelines for the design and construction of reinforced concrete structures.
IS 800 provides guidelines for the design and construction of steel structures.
IS 456 covers topics such as materials, loads, design of members, and detailing.
IS 800 covers topics such as material properties, loads, design of members, a...
Permissible stresses in concrete and steel as per IS codes.
Permissible stress in concrete is 0.67 times the characteristic strength of concrete.
Permissible stress in steel is 0.2 times the yield strength of steel.
For example, if the characteristic strength of concrete is 30 N/mm², then the permissible stress in concrete would be 0.67 x 30 = 20 N/mm².
Similarly, if the yield strength of steel is 415 N/mm², then the permi...
Permissible values for deflection in a structure according to IS provisions.
The maximum permissible deflection for a structure is L/180 for live load and L/325 for total load.
L is the span of the beam or slab in meters.
The deflection limit is to ensure the safety and comfort of the occupants of the structure.
The deflection limit varies for different types of structures and materials used.
For example, the deflection lim...
Planning a house involves several steps from conceptualization to construction.
Understand the client's requirements and budget
Create a design plan and get it approved by the client
Obtain necessary permits and approvals from local authorities
Prepare a detailed construction plan and schedule
Select and hire contractors and subcontractors
Supervise the construction process and ensure quality control
Ensure compliance with bu...
BTP project is a railway project aimed at improving connectivity and reducing travel time.
BTP stands for Bangalore-Mysore Infrastructure Corridor
It is a 111 km long 6-lane expressway connecting Bangalore and Mysore
The project also includes the construction of a high-speed rail link between the two cities
The main objective is to reduce travel time and improve connectivity between the two cities
The project is expected to
Channel flow is open flow with free surface while pipe flow is confined flow with closed surface.
Channel flow occurs in open channels like rivers, canals, etc. while pipe flow occurs in closed conduits like pipes, tubes, etc.
In channel flow, the fluid is exposed to the atmosphere and the surface is not fixed while in pipe flow, the fluid is confined and the surface is fixed.
Channel flow is affected by gravity and surfa...
Gutter is an example of open channel flow.
Open channel flow is a flow of fluid in a channel with a free surface.
Gutter is an open channel that carries rainwater from roofs to the ground.
Closed pipe flow is a flow of fluid in a pipe with a closed surface.
Examples of closed pipe flow include water supply pipes and sewage pipes.
A distribution system in a town can be explained through a drawing.
The distribution system starts at the water treatment plant
Water is transported through pipes to storage tanks
From storage tanks, water is distributed to homes and businesses
The distribution system also includes valves, pumps, and meters
The system may also include fire hydrants and water mains
The drawing should show the flow of water and the location of
I am a detail-oriented and motivated individual with a passion for engineering and problem-solving.
I have a degree in Mechanical Engineering from XYZ University.
I have completed internships at ABC Company and DEF Inc. where I gained experience in CAD software and project management.
I am proficient in programming languages such as Python and C++.
I enjoy working in a team and collaborating with others to find innovative
I prefer TCE over other firms because of their strong reputation and commitment to innovation.
TCE has a proven track record of delivering high-quality engineering solutions.
They prioritize innovation and are always looking for new and better ways to solve problems.
TCE values collaboration and teamwork, which creates a positive and productive work environment.
Their focus on sustainability aligns with my personal values ...
I was actively involved in the Counseling service and E-Club during my college years.
In the Counseling service, I provided emotional support and guidance to students who were struggling with personal or academic issues.
As a member of the E-Club, I organized and participated in various events related to technology and entrepreneurship.
I also helped to promote the club through social media and other channels.
Through thes...
My family background is diverse and has a mix of cultures and professions.
My father is a doctor and my mother is a teacher.
I have two siblings, one is an artist and the other is a software engineer.
We come from a multicultural background with roots in India and the United States.
My family values education and hard work.
We enjoy spending time together and exploring new places.
TCE stands for Trichloroethylene, a colorless liquid used as a solvent in various industries.
TCE is commonly used in dry cleaning, metal degreasing, and as a refrigerant.
It is a potent carcinogen and can cause serious health issues if not handled properly.
TCE exposure can lead to liver and kidney damage, respiratory issues, and neurological problems.
The EPA has set a maximum contaminant level of 5 parts per billion for...
Top trending discussions
posted on 4 Aug 2024
Road construction involves several steps including planning, designing, clearing the land, laying the foundation, paving, and adding finishing touches.
Planning: Determine the route, traffic flow, and necessary permits.
Designing: Create detailed plans including width, materials, and drainage systems.
Clearing the land: Remove trees, rocks, and other obstacles.
Laying the foundation: Level the ground, add layers of gravel ...
Sub grade to wearing course technical specifications include material type, thickness, compaction requirements, and drainage considerations.
Material type for sub grade can be natural soil, stabilized soil, or aggregate base.
Thickness of sub grade is typically specified based on soil conditions and traffic loads.
Compaction requirements ensure proper density and strength of the sub grade.
Wearing course materials can incl...
posted on 11 Jan 2024
I applied via Company Website and was interviewed in Jul 2023. There was 1 interview round.
The size of covering block is determined based on the type of structure and its requirements.
The size of covering block is usually specified in the design drawings or specifications.
It is important to consider the dimensions and spacing of reinforcement bars when determining the size of covering block.
The covering block should provide adequate protection to the reinforcement bars from fire, corrosion, and other environ...
The length of development refers to the duration it takes to complete a project or task.
The length of development can vary depending on the complexity of the project.
Factors such as team size, resources, and scope can also impact the length of development.
It is important to set realistic timelines and milestones to ensure efficient development.
For example, a simple website development project may take a few weeks, whil...
Construction materials are substances used for building and construction purposes.
Construction materials include cement, concrete, bricks, steel, wood, and glass.
Cement is a binding agent used in the production of concrete.
Concrete is a mixture of cement, sand, gravel, and water, used for construction.
Bricks are rectangular blocks made of clay or concrete, used for building walls.
Steel is a strong and durable material ...
posted on 13 Sep 2022
I applied via Walk-in and was interviewed in Mar 2022. There were 2 interview rounds.
posted on 9 Jan 2021
I applied via Walk-in and was interviewed in Dec 2020. There were 4 interview rounds.
posted on 15 Mar 2022
I applied via campus placement at JIS College of Engineering, Kolkata and was interviewed before Mar 2021. There were 2 interview rounds.
Height of instrument is the vertical distance between the instrument and a reference point on the ground.
It is used in surveying to determine the elevation of points on the ground.
It is measured using a leveling instrument such as a level or a theodolite.
The height of instrument is calculated by subtracting the height of the reference point from the height of the instrument.
It is important to maintain a consistent heig...
The size of spacer bar depends on the size of the conductor and the voltage rating of the line.
The size of the spacer bar should be such that it maintains the required distance between the conductors.
The size of the spacer bar should be selected based on the voltage rating of the line.
The size of the spacer bar should be selected based on the size of the conductor.
The size of the spacer bar should be such that it can w...
posted on 27 Sep 2023
I applied via Approached by Company and was interviewed in Aug 2023. There were 2 interview rounds.
Transmission line construction involves planning, design, material procurement, site preparation, tower erection, conductor stringing, and testing.
Planning involves route selection, environmental impact assessment, and obtaining necessary permits.
Design includes determining tower locations, conductor size, and insulator type.
Material procurement involves sourcing towers, conductors, insulators, and hardware.
Site prepar...
Some of the top questions asked at the TCE Assistant Engineer interview -
based on 4 reviews
Rating in categories
Assistant Manager
475
salaries
| ₹4.5 L/yr - ₹13 L/yr |
Manager
351
salaries
| ₹6.1 L/yr - ₹16.1 L/yr |
Senior Engineer
320
salaries
| ₹3.6 L/yr - ₹10 L/yr |
Senior Manager
291
salaries
| ₹10 L/yr - ₹22.5 L/yr |
Consultant
244
salaries
| ₹3.9 L/yr - ₹13.1 L/yr |
Infosys
Wipro
HCLTech
Tech Mahindra