Layouts involve planning and designing the physical arrangement of structures, while stake out involves physically marking the positions of these structures on the ground.
Layouts refer to the process of planning and designing the physical arrangement of structures, such as buildings, roads, or utilities.
Stake out involves physically marking the positions of these structures on the ground based on the layout plans.
Layou...
Top trending discussions
I have operated various surveying instruments including total stations, GPS receivers, and levels. I am proficient in AutoCAD 2D.
Operated total stations for precise angle and distance measurements
Used GPS receivers for satellite-based positioning
Utilized levels for determining elevations
Proficient in AutoCAD 2D for drafting and design work
I applied via Walk-in and was interviewed in Aug 2020. There were 4 interview rounds.
P&p stands for Policies and Procedures.
Policies and Procedures are a set of guidelines and rules that an organization follows.
They help in maintaining consistency and standardization in the organization.
Policies and Procedures cover various aspects such as HR, finance, operations, etc.
They are designed to ensure compliance with legal and regulatory requirements.
Examples of P&p include employee code of conduct, IT secur
posted on 26 Jan 2024
I applied via Walk-in and was interviewed in Jul 2023. There was 1 interview round.
The question asks about the code for mode of measurement, types of joints in flooring, and previous projects and estimation preparation.
The code for mode of measurement refers to the standard method used to measure quantities in construction projects.
Types of joints in flooring include butt joints, tongue and groove joints, and expansion joints.
Previous projects can include residential buildings, commercial complexes, ...
I applied via Referral and was interviewed before Oct 2022. There were 3 interview rounds.
Current CTC is $60,000 and Expected CTC is $70,000.
Current CTC is the current annual salary of the candidate.
Expected CTC is the annual salary the candidate is expecting from the new job.
It is important for the employer to know the candidate's salary expectations to assess if it aligns with the budget.
For example, if the candidate's Current CTC is $50,000 and Expected CTC is $65,000, there is a $15,000 difference.
Yes, I am actively involved in preparing cost estimations for construction projects. I typically prepare detailed estimates based on quantities, labor rates, material costs, and overhead expenses.
I prepare detailed estimates based on quantities of materials and labor required for a project.
I consider factors such as material costs, labor rates, equipment costs, and overhead expenses in my estimates.
I use software tools...
Verify the bill by checking quantities, rates, unit prices, supporting documents, and site measurements.
Check quantities mentioned in the bill against the actual work done on site.
Verify rates and unit prices for each item in the bill with the contract agreement.
Ensure all supporting documents such as invoices, receipts, and delivery notes are provided.
Conduct site measurements to confirm the work completed matches the
Evidential documents required for scrutinizing the RA Bill
Contract documents
Measurement sheets
Bills of quantities
Variation orders
Payment certificates
Justification of change of scope works involves thorough analysis, cost estimation, impact assessment, and communication with stakeholders.
Conduct a detailed analysis of the proposed changes in scope, including the reasons for the change and the potential impact on the project.
Estimate the additional costs and resources required for the change of scope works, taking into account materials, labor, and any other relevant...
Basic inputs for preparing the Bill of Quantities include drawings, specifications, and site visits.
Drawings: Architectural, structural, and MEP drawings are essential for accurately quantifying materials and labor.
Specifications: Detailed project specifications outline the quality and standards required for each item in the bill.
Site visits: Surveyors need to visit the site to assess existing conditions, access, and a...
posted on 7 Dec 2021
I applied via Naukri.com and was interviewed in Nov 2021. There were 3 interview rounds.
I applied via Recruitment Consultant and was interviewed in May 2021. There were 4 interview rounds.
posted on 10 Nov 2021
I applied via Referral and was interviewed in Dec 2020. There were 4 interview rounds.
I have operated various surveying instruments including total stations, GPS receivers, and levels. I am proficient in AutoCAD 2D.
Operated total stations for precise angle and distance measurements
Used GPS receivers for satellite-based positioning
Utilized levels for determining elevations
Proficient in AutoCAD 2D for drafting and design work
I applied via Recruitment Consulltant and was interviewed in Sep 2024. There were 2 interview rounds.
based on 2 reviews
Rating in categories
Safety Officer
76
salaries
| ₹1.6 L/yr - ₹5 L/yr |
Junior Engineer
62
salaries
| ₹2 L/yr - ₹3.6 L/yr |
Senior Engineer
49
salaries
| ₹4.1 L/yr - ₹9.1 L/yr |
Junior Engineer Civil
43
salaries
| ₹2.2 L/yr - ₹4.2 L/yr |
Quantity Surveyor
37
salaries
| ₹3 L/yr - ₹8.5 L/yr |
DLF
Godrej Properties
Prestige Group
Sobha