I applied via LinkedIn and was interviewed in Oct 2023. There was 1 interview round.
Earthquake loads are calculated using seismic design codes and formulas based on the seismic hazard of the region.
Determine the seismic hazard of the region using historical data and seismic maps
Select a seismic design code such as ASCE 7 or Eurocode 8
Calculate the seismic base shear using the formula V = CsW
Distribute the seismic base shear to the structure using the appropriate load combinations
Consider the effects o...
Top trending discussions
posted on 23 Aug 2023
I applied via Recruitment Consulltant and was interviewed before Aug 2022. There were 2 interview rounds.
Pipe rack design involves determining layout, sizing, and support requirements for pipes in an industrial facility.
Start by determining the layout of the pipe rack based on the piping system requirements and plant layout.
Calculate the pipe sizes and materials based on the flow rates, pressure, and temperature requirements.
Design the supports for the pipe rack to ensure stability and safety.
Consider factors such as seis...
posted on 27 Jan 2022
I applied via Company Website and was interviewed in Jan 2022. There was 1 interview round.
GFC drawing stands for Good for Construction drawing, which is a final set of drawings used for construction purposes.
GFC drawings are the final set of drawings used for construction purposes
They include all the necessary details and dimensions required for construction
GFC drawings are used by contractors and builders to construct the building as per the design
They are also used for obtaining necessary permits and appr...
I applied via Referral and was interviewed in Mar 2022. There were 2 interview rounds.
Design of pier involves considering various factors such as load capacity, soil conditions, water level, and environmental impact.
Determine the load capacity and type of pier required
Analyze soil conditions and water level to determine foundation type
Consider environmental impact and regulations
Design for durability and maintenance
Ensure safety measures are in place
Rigid pile caps are designed to transfer the load from the superstructure to the piles. The design should consider the pile arrangement, load distribution, and soil properties.
The pile cap should be designed to distribute the load evenly to the piles.
The pile arrangement should be considered to ensure that the pile cap is not overloaded.
The soil properties should be analyzed to determine the bearing capacity of the pil...
Prestressing losses occur during the transfer of prestress from the jacks to the concrete. These losses can be divided into two stages.
The first stage is immediate losses, which occur due to friction between the strands and the ducts, anchorage slip, and elastic shortening of the concrete.
The second stage is time-dependent losses, which occur due to creep and shrinkage of the concrete, relaxation of the steel, and temp...
Design of steel members and connections involves determining the appropriate size and shape of steel components and how they are connected.
Consider the loads and stresses that the steel members will be subjected to
Select appropriate steel sections based on their strength and stiffness
Design connections that can transfer loads between members without failure
Ensure that the design complies with relevant codes and standar...
Pre-tension is applied before concrete is poured, while post-tension is applied after concrete has hardened.
Pre-tension involves stretching steel cables or bars before pouring concrete to create tension in the concrete as it sets.
Post-tension involves inserting steel cables or bars into hardened concrete and then tensioning them to create compression in the concrete.
Pre-tension is typically used in precast concrete ele...
Analysis and design of piles involves determining the load capacity and selecting the appropriate type of pile for a given soil condition.
Pile load capacity is determined through various methods such as static load tests, dynamic load tests, and pile integrity tests.
Factors such as soil type, groundwater level, and seismic activity must be considered when selecting the type of pile.
Common types of piles include driven ...
I applied via Referral and was interviewed before Feb 2022. There were 2 interview rounds.
I applied via Company Website and was interviewed in Sep 2023. There was 1 interview round.
I was interviewed in Oct 2022.
The duration of the notice period is typically specified in the employment contract.
The notice period can vary depending on the company and the position.
It is usually between 2 weeks to 3 months.
Some companies may require a longer notice period for senior positions.
The notice period can be negotiated during the hiring process.
It is important to adhere to the notice period to maintain a good professional relationship wi
I applied via LinkedIn and was interviewed in Aug 2023. There were 3 interview rounds.
I applied via Walk-in and was interviewed in Nov 2022. There were 3 interview rounds.
I applied via Campus Placement and was interviewed in Aug 2024. There was 1 interview round.
Question where asked from trains,permutation and some grammer
based on 1 interview
Interview experience
Advanced Associate
139
salaries
| ₹0 L/yr - ₹0 L/yr |
Design Engineer
71
salaries
| ₹0 L/yr - ₹0 L/yr |
Quality Engineer
58
salaries
| ₹0 L/yr - ₹0 L/yr |
Senior Associate
54
salaries
| ₹0 L/yr - ₹0 L/yr |
Senior Engineer
50
salaries
| ₹0 L/yr - ₹0 L/yr |
AECOM
Jacobs Engineering Group
WSP
ARCADIS