Upload Button Icon Add office photos
Engaged Employer

i

This company page is being actively managed by L&T Realty Team. If you also belong to the team, you can get access from here

L&T Realty Verified Tick

Compare button icon Compare button icon Compare
4.1

based on 292 Reviews

Filter interviews by

L&T Realty Assistant Manager - MEP Interview Questions, Process, and Tips

Updated 10 Nov 2022

L&T Realty Assistant Manager - MEP Interview Experiences

1 interview found

I applied via Naukri.com and was interviewed before Nov 2021. There were 3 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - One-on-one 

(7 Questions)

  • Q1. What are types of plumbing?
  • Ans. 

    There are various types of plumbing systems, including water supply, drainage, vent, and gas piping.

    • Water supply plumbing systems provide clean water to homes and buildings.

    • Drainage plumbing systems remove wastewater and sewage from homes and buildings.

    • Vent plumbing systems allow air to enter and exit the plumbing system to prevent pressure buildup.

    • Gas piping plumbing systems provide gas for heating and cooking purpose...

  • Answered by AI
  • Q2. Explain plumbing system?
  • Ans. 

    Plumbing system is a network of pipes, valves, and fixtures that carry water and waste to and from a building.

    • Plumbing systems are essential for providing clean water and removing waste from buildings.

    • They consist of pipes, valves, and fixtures such as sinks, toilets, and showers.

    • Water is supplied to the building through a main water line and distributed through smaller pipes.

    • Waste is removed through a drain system tha...

  • Answered by AI
  • Q3. Explain sequence of plumbing works in toilet?
  • Ans. 

    The sequence of plumbing works in a toilet starts with rough-in plumbing, followed by installation of drain and vent pipes, water supply lines, and finally fixtures.

    • Rough-in plumbing involves installing the drain and vent pipes in the walls and floors.

    • Next, water supply lines are installed, which connect to the main water supply and run to the toilet tank and sink.

    • Finally, fixtures such as the toilet bowl, tank, and si...

  • Answered by AI
  • Q4. What are the types of pump?
  • Ans. 

    There are various types of pumps used in MEP systems, including centrifugal, positive displacement, and axial flow pumps.

    • Centrifugal pumps are commonly used in HVAC systems and move fluid by converting rotational kinetic energy to hydrodynamic energy.

    • Positive displacement pumps move fluid by trapping a fixed amount of fluid and forcing it into the discharge pipe.

    • Axial flow pumps are used for high flow and low head appl...

  • Answered by AI
  • Q5. Explain sequence for installation of elevators?
  • Ans. 

    The sequence for installation of elevators involves several steps.

    • First, the elevator shaft is constructed.

    • Next, the elevator car and its components are installed.

    • Then, the elevator doors and hoistway doors are installed.

    • After that, the elevator control system is installed and tested.

    • Finally, the elevator is inspected and certified for use.

  • Answered by AI
  • Q6. What are the types of valves?
  • Ans. 

    Valves are devices that control the flow of fluids or gases. There are several types of valves used in various industries.

    • Gate valves

    • Globe valves

    • Ball valves

    • Butterfly valves

    • Check valves

    • Diaphragm valves

    • Needle valves

    • Pinch valves

    • Pressure relief valves

    • Safety valves

  • Answered by AI
  • Q7. What is the pressure requirement for CP?
  • Ans. 

    The pressure requirement for CP depends on the specific application and system design.

    • CP stands for cathodic protection, which is used to prevent corrosion in metal structures.

    • The pressure requirement can vary depending on factors such as the type of metal being protected, the environment, and the current density.

    • For example, a pipeline in a coastal area may require a higher pressure than a storage tank in a dry climat...

  • Answered by AI
Round 3 - HR 

(3 Questions)

  • Q1. Where do you live currently ?
  • Ans. 

    I currently live in New York City.

    • I live in the heart of Manhattan.

    • I enjoy the vibrant city life and the diverse culture.

    • Living in New York City allows me to be close to various job opportunities and networking events.

    • I appreciate the convenience of having access to a wide range of amenities and services.

  • Answered by AI
  • Q2. What is your total experiance?
  • Ans. 

    I have a total experience of 8 years in MEP management.

    • I have worked as a MEP Manager for 5 years in XYZ company.

    • Prior to that, I worked as a MEP Engineer for 3 years in ABC company.

    • During my tenure as a MEP Manager, I successfully completed several projects within the given timeline and budget.

    • I have also managed a team of 10 engineers and ensured their professional growth.

    • Overall, my experience has equipped me with t...

  • Answered by AI
  • Q3. What is reason for leaving current organisation ?
  • Ans. 

    Seeking new challenges and growth opportunities

    • Looking for a role with more responsibilities and leadership opportunities

    • Desire to work in a different industry or sector

    • Seeking a better work-life balance

    • Company restructuring or downsizing

    • Relocation to a different city or country

    • Lack of career advancement or professional development in current organization

  • Answered by AI

Interview Preparation Tips

Topics to prepare for L&T Realty Assistant Manager - MEP interview:
  • AutoCAD
  • REVIT MEP
Interview preparation tips for other job seekers - Job seeker must have the knowledge of AutoCad.
Also must have knowledge of design along with execution.

Interview questions from similar companies

Interview experience
4
Good
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Walk-in and was interviewed in Dec 2024. There was 1 interview round.

Round 1 - Technical 

(2 Questions)

  • Q1. How to calculate Pile concrete Qty?
  • Q2. What is vdf ?
Interview experience
5
Excellent
Difficulty level
Easy
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Walk-in and was interviewed in Nov 2023. There were 4 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - Technical 

(2 Questions)

  • Q1. Work experience
  • Q2. Field experience
Round 3 - Technical 

(2 Questions)

  • Q1. Work experience
  • Q2. Reinforcement checking, ply shuttering work.
Round 4 - Technical 

(2 Questions)

  • Q1. Work experience
  • Q2. Dorking experience
Interview experience
4
Good
Difficulty level
Moderate
Process Duration
2-4 weeks
Result
Selected Selected

I applied via Campus Placement and was interviewed in May 2024. There were 2 interview rounds.

Round 1 - Aptitude Test 

Construction in civil

Round 2 - HR 

(2 Questions)

  • Q1. About dra homes
  • Q2. Technical questions
Interview experience
4
Good
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Technical 

(2 Questions)

  • Q1. What is Total Float?
  • Ans. 

    Total Float is the amount of time a schedule activity can be delayed without delaying the project completion date.

    • Total Float is calculated by subtracting the Early Start date of an activity from its Late Start date.

    • It indicates the flexibility in scheduling a particular activity.

    • Activities with zero Total Float are considered critical path activities.

    • Total Float helps project managers in managing project schedules eff

  • Answered by AI
  • Q2. Rate Analysis of Shuttering?
  • Ans. 

    Rate analysis of shuttering involves calculating the cost of materials, labor, and equipment for formwork used in construction projects.

    • Rate analysis of shuttering includes determining the quantity of materials needed for formwork, such as plywood, steel props, and scaffolding.

    • Labor costs for assembling and dismantling the formwork are also considered in the rate analysis.

    • Equipment costs, such as rental of concrete mix...

  • Answered by AI
Interview experience
5
Excellent
Difficulty level
Hard
Process Duration
2-4 weeks
Result
Selected Selected

I applied via Job Portal and was interviewed before Mar 2023. There were 3 interview rounds.

Round 1 - Technical 

(1 Question)

  • Q1. Electrical, fire, plumbing, HVAC
Round 2 - One-on-one 

(2 Questions)

  • Q1. About WTP ? Total wTP SYSTEM
  • Q2. Which type of STP
  • Ans. 

    STP stands for Sewage Treatment Plant, which is used to treat wastewater before releasing it back into the environment.

    • There are different types of STPs such as activated sludge process, sequencing batch reactor, and membrane bioreactor.

    • The type of STP used depends on factors like the volume of wastewater to be treated, space availability, and treatment requirements.

    • For example, an activated sludge process is commonly ...

  • Answered by AI
Round 3 - HR 

(1 Question)

  • Q1. Salary expectation

I applied via Approached by Company and was interviewed in Nov 2021. There were 2 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Don’t add your photo or details such as gender, age, and address in your resume. These details do not add any value.
View all tips
Round 2 - One-on-one 

(1 Question)

  • Q1. What should be the minimum slope for drainage pipe
  • Ans. 

    The minimum slope for drainage pipe should be 1/4 inch per foot.

    • The slope ensures proper flow of water and prevents clogging.

    • The slope may vary depending on the type of pipe and the material used.

    • The slope should be checked during installation and adjusted if necessary.

    • A slope of 1/8 inch per foot may be acceptable for larger pipes.

    • The slope should always be towards the main drain or sewer line.

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Basics of plumbing work,pipe drop,minimum slope

I applied via Company Website and was interviewed in Jan 2022. There was 1 interview round.

Round 1 - Technical 

Interview Preparation Tips

Interview preparation tips for other job seekers - Project management planning and meterial mobilation co ordinate structural engineer, manpower

L&T Realty Interview FAQs

How many rounds are there in L&T Realty Assistant Manager - MEP interview?
L&T Realty interview process usually has 3 rounds. The most common rounds in the L&T Realty interview process are Resume Shortlist, One-on-one Round and HR.
What are the top questions asked in L&T Realty Assistant Manager - MEP interview?

Some of the top questions asked at the L&T Realty Assistant Manager - MEP interview -

  1. What is the pressure requirement for ...read more
  2. Explain sequence of plumbing works in toil...read more
  3. Explain sequence for installation of elevato...read more

Tell us how to improve this page.

People are getting interviews through

based on 1 L&T Realty interview
Job Portal
100%
Low Confidence
?
Low Confidence means the data is based on a small number of responses received from the candidates.

Interview Questions from Similar Companies

Sobha Interview Questions
3.9
 • 123 Interviews
DLF Interview Questions
4.0
 • 72 Interviews
Novel Office Interview Questions
4.0
 • 44 Interviews
Prestige Group Interview Questions
4.3
 • 35 Interviews
Omaxe Interview Questions
4.2
 • 35 Interviews
Brigade Group Interview Questions
4.2
 • 32 Interviews
DEC Infra Interview Questions
3.7
 • 22 Interviews
View all
L&T Realty Assistant Manager - MEP Salary
based on 14 salaries
₹7.6 L/yr - ₹14.4 L/yr
28% more than the average Assistant Manager - MEP Salary in India
View more details

L&T Realty Assistant Manager - MEP Reviews and Ratings

based on 1 review

5.0/5

Rating in categories

5.0

Skill development

4.0

Work-Life balance

4.0

Salary & Benefits

5.0

Job Security

4.0

Company culture

4.0

Promotions/Appraisal

4.0

Work Satisfaction

Explore 1 Review and Rating
Assistant Manager
161 salaries
unlock blur

₹5.5 L/yr - ₹19 L/yr

Senior Engineer
59 salaries
unlock blur

₹5.8 L/yr - ₹7.6 L/yr

Senior Manager
24 salaries
unlock blur

₹16.6 L/yr - ₹33 L/yr

Manager
24 salaries
unlock blur

₹11 L/yr - ₹21 L/yr

Deputy General Manager
18 salaries
unlock blur

₹24.5 L/yr - ₹35 L/yr

Explore more salaries
Compare L&T Realty with

DLF

4.0
Compare

Godrej Properties

3.7
Compare

Sobha

3.9
Compare

Prestige Group

4.3
Compare

Calculate your in-hand salary

Confused about how your in-hand salary is calculated? Enter your annual salary (CTC) and get your in-hand salary
Did you find this page helpful?
Yes No
write
Share an Interview