Kalpataru Projects International Senior Planning Engineer Interview Questions and Answers

Updated 28 Sep 2021

Kalpataru Projects International Senior Planning Engineer Interview Experiences

1 interview found

Interview Questionnaire 

2 Questions

  • Q1. Management related questions, site handling related questions, Billing related questions, Sub-Contractors management related questions asked by interview panel.
  • Q2. Technical Sound Knowledge about the work, site handling situations, ROU handling, Client bill related queries, sequencing of activities etc.

Interview Preparation Tips

Interview preparation tips for other job seekers - Participant should be confident with technical sound knowledge and know about the ground reality of site work, Client dealing and better communication skill.

Interview questions from similar companies

Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via LinkedIn and was interviewed before May 2023. There were 4 interview rounds.

Round 1 - Technical 

(1 Question)

  • Q1. 1. Questions from basic productivity of manpower. 2. Questions related to preparation and detailing of master construction schedule. 3. Questions related to basic statutory norms related to operate a pro...
Round 2 - Aptitude Test 

1. Puzzle solving.
2. Psychological test.

Round 3 - One-on-one 

(1 Question)

  • Q1. Basic questions related to Planning and operations of a project.
Round 4 - HR 

(1 Question)

  • Q1. Discussion related to previous experience, educational background, expected salary etc.

Interview Preparation Tips

Interview preparation tips for other job seekers - Very well structured and systematic process of interview as well as warm and friendly too.

I applied via Naukri.com and was interviewed in Jun 2022. There were 4 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - HR 

(2 Questions)

  • Q1. How many Experience do you have in related department?
  • Ans. Said as per your Experience (with graduation it will be around 4 to 6 years of experience needed)
  • Answered Anonymously
  • Q2. When will you join in our company?
  • Ans. As per your existing company's HR Policy. (E.g. 3 Months Notice period will be there, but join as much as earlier will be an added advantage)
  • Answered Anonymously
Round 3 - Technical 

(1 Question)

  • Q1. Will check your Technical Knowledge, as per you mentioned in your resume.
  • Ans. Answer as you know boldly. Don't lie.
  • Answered Anonymously
Round 4 - HR 

(1 Question)

  • Q1. Discussion about your CTC
  • Ans. Calculate your existing CTC, ask minimum 15 to 20% hike from that.
  • Answered Anonymously

Interview Preparation Tips

Topics to prepare for KEC International Senior Planning Engineer interview:
  • Project Planning
  • Project Scheduling
  • Budgeting
  • SAP
  • Primavera
  • WBS
Interview preparation tips for other job seekers - Be Sincere, share your answers as much as you can. if any answer you don't know means don't laid there, you can say "i don't know about that"

I applied via Recruitment Consulltant and was interviewed in May 2022. There were 2 interview rounds.

Round 1 - HR 

(1 Question)

  • Q1. Currently remuneration and current assignment, ready to relocate
Round 2 - Technical 

(2 Questions)

  • Q1. Describe your self and your role in current organization
  • Q2. Scheduling principles, 10 documents of engineering along with their successors

Interview Preparation Tips

Interview preparation tips for other job seekers - Get selected but the offered salary was low than my current remuneration, plz discuss the payouts prior to interview
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Recruitment Consulltant and was interviewed in Apr 2024. There were 3 interview rounds.

Round 1 - Technical 

(1 Question)

  • Q1. Planning skills and knowledge
Round 2 - Technical 

(2 Questions)

  • Q1. Experience in scheduling software
  • Ans. 

    I have extensive experience using scheduling software to create and manage project timelines.

    • Proficient in using popular scheduling software such as Microsoft Project, Primavera P6, and Asana

    • Ability to create detailed project schedules, allocate resources, and track progress

    • Experience in setting dependencies, milestones, and critical paths to ensure project timelines are met

    • Familiarity with Gantt charts and other sched

  • Answered by AI
  • Q2. Planning knowledge and technical
Round 3 - HR 

(1 Question)

  • Q1. Salary negotiation
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
2-4 weeks
Result
Selected Selected

I applied via Approached by Company and was interviewed in Aug 2023. There were 2 interview rounds.

Round 1 - Technical 

(2 Questions)

  • Q1. What are activities in toilet area
  • Ans. 

    Activities in toilet area include personal hygiene, using the toilet, and cleaning.

    • Personal hygiene activities such as washing hands, brushing teeth, and showering

    • Using the toilet for urination and defecation

    • Cleaning activities such as wiping surfaces, changing toilet paper, and emptying trash

    • Maintenance tasks like unclogging drains or fixing leaks

  • Answered by AI
  • Q2. How will you calculate %age of completion of project
  • Ans. 

    Percentage of completion of a project can be calculated using the cost-to-cost method or milestone method.

    • Calculate %age of completion by comparing actual costs incurred to date with total estimated costs for the project.

    • Alternatively, %age of completion can be determined by tracking completion of specific project milestones.

    • Formula for cost-to-cost method: %age of completion = (Actual costs incurred / Total estimated ...

  • Answered by AI
Round 2 - Technical 

(2 Questions)

  • Q1. Plumbing work in wall and floor, wall plaster and then wall tile after that flooring
  • Ans. 

    The sequence of tasks involves plumbing work, wall plastering, wall tiling, and flooring.

    • Start by completing the plumbing work in the walls and floors

    • Next, apply wall plaster to smoothen the surface

    • Then, install wall tiles for a decorative finish

    • Finally, proceed with the flooring installation

  • Answered by AI
  • Q2. By EPC weightage %age
Interview experience
4
Good
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Referral and was interviewed in Dec 2023. There was 1 interview round.

Round 1 - One-on-one 

(1 Question)

  • Q1. Tell me detail in how you plan PQC work
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Don’t add your photo or details such as gender, age, and address in your resume. These details do not add any value.
View all tips
Round 2 - Technical 

(1 Question)

  • Q1. Primavera and job related questions
Round 3 - One-on-one 

(1 Question)

  • Q1. Job related and basic req for planning
Round 4 - HR 

(2 Questions)

  • Q1. What are your salary expectations?
  • Q2. Share details of your previous job.

Interview Preparation Tips

Interview preparation tips for other job seekers - Good company. Be clear with the contract.

I applied via Referral and was interviewed in Apr 2022. There was 1 interview round.

Round 1 - One-on-one 

(1 Question)

  • Q1. Tell me About Your Self and Past Company work processor and Details

Interview Preparation Tips

Interview preparation tips for other job seekers - Facilities and staff behaviour and company norms to good
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Properly align and format text in your resume. A recruiter will have to spend more time reading poorly aligned text, leading to high chances of rejection.
View all tips
Round 2 - Technical 

(1 Question)

  • Q1. Basic question related your previous work

Interview Preparation Tips

Interview preparation tips for other job seekers - Preparation should on as per your previous work

Kalpataru Projects International Interview FAQs

What are the top questions asked in Kalpataru Projects International Senior Planning Engineer interview?

Some of the top questions asked at the Kalpataru Projects International Senior Planning Engineer interview -

  1. Management related questions, site handling related questions, Billing related ...read more
  2. Technical Sound Knowledge about the work, site handling situations, ROU handlin...read more

Tell us how to improve this page.

Kalpataru Projects International Senior Planning Engineer Salary
based on 85 salaries
₹4 L/yr - ₹10.7 L/yr
28% less than the average Senior Planning Engineer Salary in India
View more details

Kalpataru Projects International Senior Planning Engineer Reviews and Ratings

based on 15 reviews

4.3/5

Rating in categories

4.2

Skill development

3.2

Work-life balance

3.5

Salary

4.2

Job security

3.8

Company culture

4.0

Promotions

3.5

Work satisfaction

Explore 15 Reviews and Ratings
Deputy Manager
574 salaries
unlock blur

₹5.4 L/yr - ₹18 L/yr

Senior Engineer
554 salaries
unlock blur

₹3.4 L/yr - ₹10.6 L/yr

Assistant Manager
545 salaries
unlock blur

₹3.8 L/yr - ₹16 L/yr

Manager
243 salaries
unlock blur

₹6.2 L/yr - ₹24 L/yr

Civil Engineer
241 salaries
unlock blur

₹2 L/yr - ₹7.5 L/yr

Explore more salaries
Compare Kalpataru Projects International with

Sterlite Power

4.0
Compare

Adani Transmission

3.7
Compare

Power Grid Corporation of India

4.4
Compare

Tata Power

3.9
Compare
Did you find this page helpful?
Yes No
write
Share an Interview