Rate analysis is the process of determining the rates of various items of work involved in a construction project.
It involves breaking down the cost of a project into individual components
It helps in estimating the total cost of a project
It helps in comparing the cost of different projects
Yes, I have done rate analysis for various construction projects
Steel reinforcement of piles is calculated based on the load capacity and design of the pile.
Determine the load capacity and design of the pile
Calculate the required cross-sectional area of steel reinforcement
Determine the spacing and diameter of the reinforcement bars
Calculate the total length of steel reinforcement required
Consider any additional factors such as corrosion protection
Ensure compliance with relevant cod
Top trending discussions
I appeared for an interview in Aug 2019.
There are various types of structures, including buildings, bridges, dams, tunnels, and towers.
Structures can be classified based on their purpose, design, and materials used.
Buildings can be further classified into residential, commercial, and industrial structures.
Bridges can be classified into beam, arch, suspension, and cable-stayed bridges.
Dams can be classified into gravity, arch, buttress, and embankment dams.
Tu...
Density is the measure of mass per unit volume of a substance.
It is a physical property of matter.
It is calculated by dividing the mass of a substance by its volume.
Units of density include kg/m³, g/cm³, and lb/ft³.
Density can be used to identify substances and determine their purity.
For example, gold has a density of 19.3 g/cm³, while aluminum has a density of 2.7 g/cm³.
There are two types of density construction: compacted and loose.
Compacted density construction involves compressing the material to increase its density, such as in road construction.
Loose density construction involves leaving the material in its natural state, such as in landscaping.
The type of density construction used depends on the intended use of the material and the desired level of compaction.
Other factors that...
Tests for construction joints include visual inspection, water tightness test, and load transfer test.
Visual inspection to check for proper joint alignment and sealant application
Water tightness test to ensure no water leakage through the joint
Load transfer test to verify the joint can handle the intended load
Other tests may include pull-out test, shear test, and compression test
Testing frequency and methods may vary d...
posted on 11 Nov 2024
I applied via Walk-in and was interviewed in May 2024. There was 1 interview round.
I previously worked at XYZ Company as a Quality Engineer for 3 years.
Worked at XYZ Company as a Quality Engineer
Experience of 3 years in the role
Implemented quality control processes and procedures
Collaborated with cross-functional teams to improve product quality
I was responsible for ensuring the quality of products and processes in my previous company.
Developed and implemented quality control procedures
Conducted quality audits and inspections
Collaborated with cross-functional teams to address quality issues
Provided training on quality standards and best practices
posted on 23 Dec 2022
I applied via Walk-in and was interviewed in Aug 2022. There were 2 interview rounds.
posted on 13 Jul 2023
posted on 26 Mar 2023
I applied via Referral and was interviewed in Feb 2023. There were 3 interview rounds.
Time shifting can cause problems in quality control.
Time shifting can lead to incorrect data analysis and interpretation.
It can also cause delays in identifying and addressing quality issues.
Examples include delayed detection of defects in production processes or incorrect measurements due to time differences.
Proper time synchronization and documentation can help prevent time shifting problems.
The size of a concrete cube is typically 150mm x 150mm x 150mm for standard testing purposes.
Standard size for concrete cube is 150mm x 150mm x 150mm
Used for testing the compressive strength of concrete
Other sizes may be used for specific projects or requirements
posted on 20 Nov 2023
I applied via Walk-in and was interviewed in Oct 2023. There were 3 interview rounds.
Qc relented matarial testing
Seive analysis of aggregate is a method used to determine the particle size distribution of aggregates.
Seive analysis involves passing a sample of aggregate through a series of sieves with progressively smaller openings.
The amount of material retained on each sieve is weighed and used to calculate the percentage of material passing through each sieve.
The results of seive analysis are used to determine the gradation of ...
posted on 24 Dec 2024
I applied via Approached by Company and was interviewed before Dec 2023. There was 1 interview round.
PQC mix design involves determining the proportions of materials like cement, aggregates, water, and admixtures for pavement quality concrete.
PQC stands for Pavement Quality Concrete
Mix design involves determining the proportions of materials like cement, aggregates, water, and admixtures
Factors such as strength requirements, durability, workability, and environmental conditions are considered in mix design
Example: A t...
I applied via Approached by Company and was interviewed before Mar 2022. There were 2 interview rounds.
Questions related to site engineering including slump test, TBM, steel weight calculation, site supervision, BBS, concrete quantity calculation, and pipeline.
Slump test measures the consistency of concrete. Procedure involves filling a slump cone with concrete and measuring the slump after removing the cone.
TBM stands for Tunnel Boring Machine, used for excavating tunnels in soil or rock.
Weight of steel can be calculat...
based on 1 interview
Interview experience
based on 4 reviews
Rating in categories
Site Engineer
208
salaries
| ₹2.7 L/yr - ₹7.2 L/yr |
Civil Site Engineer
178
salaries
| ₹2.3 L/yr - ₹8.1 L/yr |
Quantity Surveyor
54
salaries
| ₹3 L/yr - ₹7.2 L/yr |
Senior Planning Engineer
53
salaries
| ₹5 L/yr - ₹8.6 L/yr |
Mechanical Engineer
49
salaries
| ₹2 L/yr - ₹6.8 L/yr |
L&T Construction
Simplex Infrastructures
ITD Cementation India
Ashoka Buildcon