Filter interviews by
I applied via Walk-in and was interviewed in Mar 2023. There were 2 interview rounds.
Civil construction management process involves planning, organizing, and controlling construction activities to ensure successful project completion.
Planning phase includes site investigation, feasibility study, and design development.
Organizing phase involves procurement of materials, equipment, and labor.
Controlling phase includes monitoring progress, quality control, and cost management.
Regular communication and coo...
I applied via Approached by Company and was interviewed in Aug 2023. There were 3 interview rounds.
Side planing ,and labour handling
Drowning reading ,
Group discussion ,planing work next day
And side working discussion
Top trending discussions
posted on 6 Oct 2023
I applied via Walk-in and was interviewed in Sep 2023. There were 2 interview rounds.
posted on 30 Nov 2023
I applied via Naukri.com and was interviewed in Oct 2023. There were 3 interview rounds.
Bar bending schedule , RL , BSS , HI, TBM, water rasiw, , BS
The thickness of DPC can be either 2.5cm or 1 inch.
DPC stands for Damp Proof Course, which is a layer of waterproof material used in construction to prevent moisture from rising through the walls or floors.
The thickness of DPC is typically determined based on the specific requirements of the project and local building codes.
In some regions, the thickness of DPC is specified in centimeters (e.g., 2.5cm), while in others...
The height of the window is 2.1m.
The height of the window is a fixed measurement.
It is important to consider the height of the window when designing the building.
The height of the window may vary depending on the specific requirements of the project.
The height of the building is 3.15m.
The height of the building is a crucial measurement in civil engineering.
It is important to accurately measure and document the height of a building for various purposes such as construction planning, structural analysis, and code compliance.
In this case, the height of the building is specified as 3.15m.
This measurement can be used to determine the number of floors, calculate the vol...
The lintel thickness is 15cm (inch).
The lintel thickness is the measurement of the horizontal beam that supports the load above an opening, such as a door or window.
A lintel with a thickness of 15cm (inch) is considered standard in many construction projects.
The thickness of the lintel is determined based on the span of the opening and the load it needs to support.
Lintels can be made of various materials, including con...
The weight of one bag of cement is 50 kg.
The weight of cement bags is standardized at 50 kg.
This weight is important for calculating the quantity of cement required for a project.
For example, if a project requires 100 bags of cement, the total weight would be 5000 kg.
RCC ,water ratio , bar bending schedule
The minimum thickness for a wall is typically 400 mm.
The minimum thickness of a wall is determined by structural requirements and building codes.
Thicker walls provide better structural stability and can support heavier loads.
The type of wall construction and materials used also influence the minimum thickness.
For example, a load-bearing concrete wall may require a minimum thickness of 400 mm to ensure structural integr...
posted on 28 Oct 2021
I applied via Recruitment Consultant and was interviewed in May 2021. There was 1 interview round.
Grade of concrete and reinforcement diameter are important factors in civil engineering design.
The grade of concrete determines its strength and durability.
Common grades of concrete include M20, M25, and M30.
Reinforcement diameter affects the strength and stability of the structure.
Common reinforcement diameters include 8mm, 10mm, and 12mm.
The appropriate grade of concrete and reinforcement diameter depend on the speci
I applied via Naukri.com and was interviewed in Jan 2021. There were 3 interview rounds.
Precommissioning tests of transformers ensure proper functioning and safety before energizing.
Visual inspection of transformer and its components
Measurement of insulation resistance
Measurement of winding resistance
Verification of transformer ratio and polarity
Verification of oil level and quality
Testing of protective devices
Verification of grounding
Functional testing of cooling system
Verification of nameplate data
11kv & 33kv overhead power line distribution
11kv and 33kv are common voltage levels for overhead power lines
Overhead power lines are used to distribute electricity from power stations to consumers
The voltage level determines the distance the power can be transmitted and the size of the conductors needed
Proper insulation and grounding is important for safety
Maintenance and inspection of the lines is necessary to ensure
I applied via Walk-in and was interviewed before Aug 2020. There were 5 interview rounds.
Minimum grade of concrete for construction purposes.
Minimum grade of concrete used is M10.
Higher grades of concrete are used for stronger structures.
Grade of concrete depends on the type of construction and load-bearing capacity required.
I applied via Campus Placement and was interviewed before Sep 2021. There were 2 interview rounds.
It was pretty easy,
Patterns, logical reasoning kinda stuff
I applied via Campus Placement and was interviewed before May 2020. There were 3 interview rounds.
My favourite subject is Mathematics.
I enjoy solving complex problems and equations.
I find it fascinating how mathematical concepts can be applied in various fields.
I appreciate the logical and analytical thinking required in Mathematics.
I have excelled in Mathematics throughout my academic career.
I have also participated in Mathematics Olympiads and competitions.
I appeared for an interview in Aug 2017.
based on 2 interviews
Interview experience
Civil Site Engineer
215
salaries
| ₹1.8 L/yr - ₹7.2 L/yr |
Site Engineer
209
salaries
| ₹2.7 L/yr - ₹7.2 L/yr |
Quantity Surveyor
54
salaries
| ₹3 L/yr - ₹7.2 L/yr |
Senior Planning Engineer
53
salaries
| ₹5 L/yr - ₹8.6 L/yr |
Mechanical Engineer
49
salaries
| ₹2 L/yr - ₹6.8 L/yr |
L&T Construction
Simplex Infrastructures
ITD Cementation India
Ashoka Buildcon