I applied via Naukri.com and was interviewed in Oct 2022. There were 3 interview rounds.
Top trending discussions
posted on 11 Aug 2024
Baselines in Primavera are snapshots of the project schedule at a specific point in time, used for comparison and tracking progress.
Baselines capture the original project plan before any changes are made.
They are used as a reference point to compare actual progress against planned progress.
Baselines help in identifying deviations from the original plan and taking corrective actions.
In Primavera, baselines can be create...
To track a project in Primavera P6 on a daily basis, use the following steps.
Update progress for each activity daily
Review critical path activities regularly
Monitor resource allocation and availability
Compare planned vs. actual progress
Generate daily reports for stakeholders
I applied via Campus Placement
The test was based on logical reasoning and verbal reasoning.
EVM stands for Earned Value Management. It is a project management technique used to measure project performance and progress.
EVM integrates scope, schedule, and cost to provide a comprehensive view of project performance.
It compares the planned value (PV), earned value (EV), and actual cost (AC) to assess project health.
PV represents the budgeted cost of the work scheduled, EV represents the budgeted cost of the work ...
posted on 30 Apr 2024
I applied via Approached by Company and was interviewed in Oct 2023. There were 3 interview rounds.
M4 in Planning refers to a milestone that marks the completion of a significant phase or deliverable in a project schedule.
M4 is typically used in project management to signify a key point in the project timeline.
It is often associated with the completion of a major task or the achievement of an important project milestone.
M4 can help track progress, identify potential delays, and ensure that the project stays on sched...
I will break down the 300 km laying project into smaller sections, assign resources, estimate durations, and create a detailed schedule.
Break down the project into manageable sections such as 10 km segments
Assign resources including equipment, manpower, and materials to each section
Estimate durations for each activity based on historical data or industry standards
Create a detailed schedule using a scheduling software l...
How will you provide schedule of WTP
posted on 13 Oct 2023
I applied via campus placement at National Institute of Technology (NIT), Jamshedpur and was interviewed in Sep 2023. There were 4 interview rounds.
The level of the exam was normal.
Quality of brick, cement, and SF & BMD diagram can be checked through visual inspection, testing, and comparison with standards.
Brick quality can be checked by inspecting for uniform size, shape, and color, and conducting water absorption test.
Cement quality can be checked by performing tests like fineness test, setting time test, and compressive strength test.
SF & BMD diagram quality can be checked by verifying accura...
posted on 30 Sep 2024
I applied via Referral and was interviewed before Sep 2023. There was 1 interview round.
Inch Dia and Inch Meter are units of measurement used in engineering for pipe sizes and lengths.
Inch Dia refers to the diameter of a pipe in inches
Inch Meter refers to the length of a pipe in meters
They are commonly used in piping and construction projects
Estimate the quantity of cement and sand needed for a boundary wall construction project.
Calculate the volume of the boundary wall in cubic meters
Determine the mix ratio of cement and sand for the project
Use the mix ratio to calculate the quantity of cement and sand needed
Consider wastage and spillage when estimating quantities
WBS stands for Work Breakdown Structure, which is a hierarchical decomposition of the total scope of work to be carried out by the project team.
WBS for a highway project would include major components like earthwork, pavement, drainage, signage, lighting, etc.
WBS for a structure project would include components like foundation, superstructure, finishes, MEP (mechanical, electrical, plumbing), etc.
Each major component i...
S-Curve in Primavera is a graphical representation of project progress over time.
S-Curve shows the planned and actual progress of a project.
It helps in visualizing the project's performance and identifying any deviations from the plan.
The curve is shaped like an 'S' due to the gradual increase in progress at the beginning and end, with a steeper slope in the middle.
The x-axis represents time, and the y-axis represents ...
I applied via Referral and was interviewed in Mar 2023. There were 4 interview rounds.
Yes, I have experience in scheduling.
I have worked on scheduling projects using software such as Primavera P6 and Microsoft Project.
I am familiar with creating and updating project schedules, resource allocation, and critical path analysis.
I have also worked on schedule risk analysis and mitigation planning.
I understand the importance of accurate scheduling in project management and strive to ensure that schedules are
Site Engineer
9
salaries
| ₹5 L/yr - ₹13 L/yr |
Planning Engineer
8
salaries
| ₹4.8 L/yr - ₹19.8 L/yr |
Project Engineer
7
salaries
| ₹4.5 L/yr - ₹10.2 L/yr |
Quantity Surveyor
7
salaries
| ₹12 L/yr - ₹19.1 L/yr |
Senior Engineer
5
salaries
| ₹4 L/yr - ₹4.1 L/yr |
DLF
Prestige Group
Godrej Properties
Brigade Group