Initial setting time is the time taken for the cement to harden to a certain degree, while final setting time is the time taken for the cement to completely harden.
Initial setting time is typically around 30 minutes to 1 hour after adding water to the cement.
Final setting time is usually around 2 to 4 hours after adding water to the cement.
Setting time can vary based on the type of cement and environmental conditions.
S
Bleeding is the process of air escaping from fresh concrete mix and rising to the surface.
Bleeding occurs when water in the concrete mix rises to the surface due to settlement of solid particles.
It can lead to surface defects if not properly managed.
Bleeding can be reduced by using proper mix design and techniques like vibration or adding admixtures.
Excessive bleeding can weaken the surface of the concrete.
Examples: Wa...
I applied via Company Website and was interviewed before Dec 2022. There were 3 interview rounds.
Cement test, bitumen test, road density, ravite, autocad
Concrete properties grade
I applied via Walk-in and was interviewed before Apr 2021. There were 3 interview rounds.
Shapoorji Pallonji Group interview questions for designations
I applied via Job Fair and was interviewed in Oct 2024. There were 3 interview rounds.
One way slab is supported on two opposite sides, while two way slab is supported on all four sides.
One way slab is designed to carry loads predominantly in one direction.
Two way slab is designed to carry loads in both directions.
One way slab is more economical for smaller spans, while two way slab is more suitable for larger spans.
Examples: One way slab - balcony, corridor. Two way slab - office building, parking garag
I applied via Walk-in and was interviewed before May 2021. There were 2 interview rounds.
CODAL provisions for concrete refer to the guidelines and regulations set by relevant authorities, while commands of software are the specific instructions or functions within a software program.
CODAL provisions for concrete include specifications for mix design, strength requirements, and durability standards.
Commands of software for site engineers may include functions for structural analysis, quantity takeoff, and p...
I applied via Company Website and was interviewed in Feb 2024. There were 2 interview rounds.
I applied via Naukri.com and was interviewed in Jul 2023. There were 3 interview rounds.
Cement consumption of M20 concrete mix ratio is 360 kg/m3.
M20 concrete mix ratio is 1:1.5:3 (1 part cement, 1.5 parts sand, 3 parts aggregate)
Cement consumption for 1 m3 of M20 concrete is 360 kg
To calculate total cement consumption, multiply 360 kg by the volume of concrete needed
Extra items added in billing should be justified with proper documentation and approval.
Ensure that the extra item was actually used on the project
Check if the extra item was approved by the client or project manager
Document the reason for adding the extra item in the billing
Provide evidence such as photos or receipts to support the inclusion of the extra item
Rate analysis involves calculating the cost of various items in a construction project.
Rate analysis helps in determining the cost of materials, labor, and equipment for each item in a project.
It involves breaking down the total cost into components like material cost, labor cost, machinery cost, and overheads.
Rate analysis is essential for accurate budgeting and cost estimation in construction projects.
For example, in...
Interview experience
based on 76 reviews
Rating in categories
Deputy Manager
595
salaries
| ₹6 L/yr - ₹16.5 L/yr |
Senior Engineer
431
salaries
| ₹4 L/yr - ₹12.2 L/yr |
Construction Engineer
301
salaries
| ₹2.4 L/yr - ₹9 L/yr |
Civil Site Engineer
236
salaries
| ₹1.5 L/yr - ₹9.2 L/yr |
Safety Officer
231
salaries
| ₹1 L/yr - ₹8.3 L/yr |
Tata Group
Reliance Industries
Adani Group
Mahindra & Mahindra