The standard deduction as per IS 1200 is a fixed amount that can be deducted from the measured quantities of certain items in a construction project.
The standard deduction is typically used for items like scaffolding, formwork, and centering in construction projects.
It is a fixed percentage of the measured quantity, usually ranging from 2% to 5% depending on the item and project.
The purpose of the standard deduction is...
Material properties refer to the characteristics and behavior of materials used in construction projects.
Material properties include density, strength, durability, thermal conductivity, and elasticity.
Understanding material properties is crucial for selecting the right materials for a project.
Examples of material properties affecting construction include water absorption in concrete and thermal expansion in metals.
posted on 12 May 2024
I applied via Approached by Company
Yes, code is a mode of measurement used in quantity surveying.
Code is a standardized system of measurement used in quantity surveying to quantify and describe construction works.
It helps in accurately estimating the quantities of materials and labor required for a project.
Examples of codes used in quantity surveying include SMM7 (Standard Method of Measurement) and CESMM4 (Civil Engineering Standard Method of Measureme
posted on 8 May 2024
I applied via Newspaper Ad and was interviewed in Nov 2023. There was 1 interview round.
I applied via Walk-in and was interviewed before Oct 2021. There were 3 interview rounds.
I was interviewed in Aug 2017.
posted on 24 Sep 2022
I applied via Company Website and was interviewed before Sep 2021. There were 3 interview rounds.
Some basic questions of mathematics up to 10th class.
posted on 25 Apr 2023
I applied via Approached by Company and was interviewed before Apr 2022. There were 5 interview rounds.
It was around 5-10 minutes online test.
The percentage of wastage varies depending on the project and materials used.
The percentage of wastage can be calculated by dividing the amount of material wasted by the total amount of material used and multiplying by 100.
Factors that can contribute to wastage include poor planning, inaccurate measurements, and human error.
The percentage of wastage can be reduced through careful planning, accurate measurements, and pr...
posted on 23 Aug 2021
I applied via Naukri.com and was interviewed before Aug 2020. There were 4 interview rounds.
Mode of measurement refers to the standard method used to measure quantities in construction projects.
It is important to establish a clear mode of measurement to ensure consistency and accuracy in cost estimation.
Common modes of measurement include SMM7, CESMM, and NRM.
SMM7 (Standard Method of Measurement) is widely used in the UK for building works.
CESMM (Civil Engineering Standard Method of Measurement) is used for c...
Deduction as per IS code for Connecte, Shuttering & Plaster
As per IS code, deduction for connected items is 2.5% of the total quantity
For shuttering, deduction is 10% of the total surface area
For plaster, deduction is 20% of the total surface area
These deductions are made to account for wastage and overlapping
The consumption for mortar 1:3 and 1:6 ratio depends on the area to be covered and thickness of the layer.
The consumption of mortar is calculated in terms of volume.
For 1:3 ratio, the mix proportion is 1 part cement and 3 parts sand.
For 1:6 ratio, the mix proportion is 1 part cement and 6 parts sand.
The thickness of the layer also affects the consumption of mortar.
The area to be covered is calculated by multiplying the...
based on 4 reviews
Rating in categories
Assistant Engineer
173
salaries
| ₹2 L/yr - ₹5.4 L/yr |
Junior Engineer
109
salaries
| ₹2 L/yr - ₹4.1 L/yr |
Assistant Manager
79
salaries
| ₹4.8 L/yr - ₹11 L/yr |
Accountant
50
salaries
| ₹1.9 L/yr - ₹8.3 L/yr |
Accounts Officer
49
salaries
| ₹3.2 L/yr - ₹6.6 L/yr |
Ashoka Buildcon
IRB Infrastructure
Nagarjuna Construction Company
Simplex Infrastructures