Planning Manager Interview Questions & Answers

user image SWARUP SIKDER

posted on 13 Sep 2024

Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Technical 

(1 Question)

  • Q1. About experience

Interview questions from similar companies

Interview experience
2
Poor
Difficulty level
Moderate
Process Duration
More than 8 weeks
Result
Not Selected

I applied via Referral and was interviewed in Jul 2024. There was 1 interview round.

Round 1 - Technical 

(2 Questions)

  • Q1. Frequency of updating of baseline schedule
  • Ans. 

    Baseline schedules should be updated regularly to reflect changes in project scope, timeline, and resources.

    • Baseline schedules should be updated at key project milestones or when significant changes occur.

    • Regular updates ensure that the schedule remains accurate and reflects the current status of the project.

    • Updates should be communicated to all stakeholders to keep them informed of any changes.

    • Examples of changes that...

  • Answered by AI
  • Q2. What is crashing of schedule
  • Ans. 

    Crashing of schedule is a technique used in project management to shorten the project duration by adding more resources.

    • Crashing involves adding more resources to critical path activities to reduce the overall project duration.

    • It is typically used when there is a need to meet a deadline or when there are financial incentives for early completion.

    • Crashing may increase project costs due to the additional resources requir...

  • Answered by AI
Interview experience
2
Poor
Difficulty level
Moderate
Process Duration
More than 8 weeks
Result
Not Selected

I applied via Referral and was interviewed in Jul 2024. There was 1 interview round.

Round 1 - Technical 

(2 Questions)

  • Q1. Frequency of updating of baseline schedule
  • Ans. 

    Baseline schedules should be updated regularly to reflect changes in project scope, timeline, and resources.

    • Baseline schedules should be updated at key project milestones or when significant changes occur.

    • Regular updates ensure that the schedule remains accurate and reflects the current status of the project.

    • Updates should be communicated to all stakeholders to keep them informed of any changes.

    • Examples of changes that...

  • Answered by AI
  • Q2. What is crashing of schedule
  • Ans. 

    Crashing of schedule is a technique used in project management to shorten the project duration by adding more resources.

    • Crashing involves adding more resources to critical path activities to reduce the overall project duration.

    • It is typically used when there is a need to meet a deadline or when there are financial incentives for early completion.

    • Crashing may increase project costs due to the additional resources requir...

  • Answered by AI
Interview experience
5
Excellent
Difficulty level
Easy
Process Duration
2-4 weeks
Result
Selected Selected

I applied via Referral and was interviewed before Oct 2023. There were 2 interview rounds.

Round 1 - Technical 

(5 Questions)

  • Q1. Role of planning engineer
  • Ans. 

    Planning engineers are responsible for creating project schedules, monitoring progress, and ensuring timely completion.

    • Develop project schedules using software like Primavera P6

    • Monitor project progress and identify potential delays

    • Coordinate with various teams to ensure timely completion

    • Prepare reports on project status and communicate with stakeholders

    • Implement changes to the schedule as needed to keep the project on

  • Answered by AI
  • Q2. What is critical path
  • Ans. 

    Critical path is the longest sequence of tasks in a project that must be completed on time to ensure the project finishes on schedule.

    • Critical path helps in identifying the tasks that are crucial for the project timeline.

    • It determines the shortest possible duration for completing the project.

    • Any delay in tasks on the critical path will directly impact the project's overall timeline.

    • Activities on the critical path have ...

  • Answered by AI
  • Q3. Density of steel
  • Ans. 

    Density of steel is approximately 7.85 g/cm^3.

    • The density of steel is commonly expressed in grams per cubic centimeter (g/cm^3).

    • The density of steel is approximately 7.85 g/cm^3.

    • Different types of steel may have slightly different densities.

  • Answered by AI
  • Q4. How to calculate weight of steel
  • Ans. 

    Weight of steel can be calculated by multiplying the volume of steel by its density.

    • Calculate the volume of steel (length x width x height)

    • Determine the density of the specific type of steel being used

    • Multiply the volume by the density to get the weight

    • Example: Weight of a steel plate with dimensions 2m x 1m x 0.1m and density of 7850 kg/m^3 would be 2 x 1 x 0.1 x 7850 = 1570 kg

  • Answered by AI
  • Q5. How to calculate number of tiles
  • Ans. 

    Number of tiles can be calculated by determining the area to be covered and the size of each tile.

    • Calculate the total area to be covered by multiplying the length and width of the space.

    • Determine the size of each tile in square units.

    • Divide the total area by the size of each tile to get the number of tiles needed.

    • Consider adding extra tiles for cuts and wastage.

    • For example, if a room is 10 feet by 12 feet and each tile

  • Answered by AI
Round 2 - Technical 

(2 Questions)

  • Q1. About excel shortcuts
  • Q2. Drawing related questions
Interview experience
4
Good
Difficulty level
-
Process Duration
-
Result
-
Round 1 - One-on-one 

(2 Questions)

  • Q1. How to arrive the quantity
  • Ans. 

    Quantity can be arrived at by calculating the dimensions and quantities of materials needed for a project.

    • Calculate the dimensions of the project area

    • Determine the materials needed for the project

    • Estimate the quantities of materials required based on the dimensions and specifications

    • Consider factors such as wastage and additional materials for contingencies

    • Use software tools like AutoCAD or Excel for accurate calculati

  • Answered by AI
  • Q2. How to cost analysis
  • Ans. 

    Cost analysis involves evaluating the expenses associated with a project or operation to determine its financial feasibility.

    • Identify all costs associated with the project or operation, including direct and indirect costs.

    • Break down costs into categories such as labor, materials, equipment, overhead, and contingency.

    • Compare actual costs to budgeted costs to identify any variances and analyze the reasons behind them.

    • Use...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Good
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Technical 

(1 Question)

  • Q1. Is code for method of measurement
  • Ans. 

    Code for method of measurement is a standardized set of rules and guidelines used to quantify and evaluate the work done in a construction project.

    • Codes for method of measurement provide a uniform and consistent way to measure quantities in construction projects.

    • They help in accurately estimating costs, monitoring progress, and resolving disputes.

    • Examples include CESMM (Civil Engineering Standard Method of Measurement)...

  • Answered by AI

I applied via Walk-in and was interviewed in Sep 2022. There were 4 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - Aptitude Test 

Aptitude questions easy not much difficult but have to write

Round 3 - Technical 

(1 Question)

  • Q1. Basics and based on your experience they will ask
Round 4 - HR 

(1 Question)

  • Q1. Salary negotiation and commitments towards the company

Interview Preparation Tips

Interview preparation tips for other job seekers - Interview will be not much difficult as per me but a bit preperation is required for freshers

Interview Questionnaire 

1 Question

  • Q1. Job profile
  • Ans. Material planning ,quantification and project status updation
  • Answered by sunil thakur

Interview Preparation Tips

Interview preparation tips for other job seekers - labour productivity ,quantification for material planning.

I applied via LinkedIn and was interviewed in Jul 2021. There were 5 interview rounds.

Interview Questionnaire 

1 Question

  • Q1. Project Management related

Interview Preparation Tips

Interview preparation tips for other job seekers - Make sure you have strong basics

I applied via Naukri.com and was interviewed before Mar 2021. There were 3 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Don’t add your photo or details such as gender, age, and address in your resume. These details do not add any value.
View all tips
Round 2 - One-on-one 

(1 Question)

  • Q1. Good interview and experience
Round 3 - HR 

(5 Questions)

  • Q1. What are your salary expectations?
  • Q2. Share details of your previous job.
  • Q3. Why should we hire you?
  • Q4. What are your strengths and weaknesses?
  • Q5. Tell me about yourself.

Interview Preparation Tips

Interview preparation tips for other job seekers - Good experience and u can learn many things.

Kalpataru Limited Interview FAQs

How many rounds are there in Kalpataru Limited Planning Manager interview?
Kalpataru Limited interview process usually has 1 rounds. The most common rounds in the Kalpataru Limited interview process are Technical.
How to prepare for Kalpataru Limited Planning Manager interview?
Go through your CV in detail and study all the technologies mentioned in your CV. Prepare at least two technologies or languages in depth if you are appearing for a technical interview at Kalpataru Limited. The most common topics and skills that interviewers at Kalpataru Limited expect are Cost Estimation, MSP, Planning, Planning Engineering and Primavera.

Tell us how to improve this page.

Kalpataru Limited Planning Manager Interview Process

based on 1 interview

Interview experience

5
  
Excellent
View more

Interview Questions from Similar Companies

Tata Group Interview Questions
4.2
 • 358 Interviews
Adani Group Interview Questions
3.9
 • 185 Interviews
Sobha Interview Questions
3.9
 • 127 Interviews
Lodha Group Interview Questions
4.0
 • 124 Interviews
View all
Kalpataru Limited Planning Manager Salary
based on 6 salaries
₹15 L/yr - ₹24 L/yr
9% more than the average Planning Manager Salary in India
View more details
Assistant Manager
215 salaries
unlock blur

₹5.4 L/yr - ₹16 L/yr

Senior Engineer
162 salaries
unlock blur

₹3.2 L/yr - ₹12.5 L/yr

Assistant Engineer
105 salaries
unlock blur

₹3.1 L/yr - ₹8 L/yr

Senior Executive
92 salaries
unlock blur

₹5 L/yr - ₹11 L/yr

Manager
88 salaries
unlock blur

₹10 L/yr - ₹24 L/yr

Explore more salaries
Compare Kalpataru Limited with

Tata Group

4.2
Compare

Adani Group

3.9
Compare

Reliance Industries

4.0
Compare

Mahindra & Mahindra

4.1
Compare
Did you find this page helpful?
Yes No
write
Share an Interview