I was interviewed in Jan 2025.
Yes, 3 Phase autoreclosure can be used at 400KV line with pros and cons.
Pros: Improved system reliability, reduced outage duration, automatic fault clearing
Cons: Increased wear on equipment, potential for re-ignition of faults, coordination challenges with other protection devices
1 phase AR is not used in 132KV lines due to limitations in fault detection and protection coordination.
1 phase AR lacks fault detection capabilities for all three phases
Coordination with other protection devices becomes difficult with 1 phase AR
Risk of incorrect tripping due to lack of complete system information
Potential for increased downtime and damage to equipment in case of faults
Dead time of 1 second is commonly used in protection systems to allow for accurate fault detection and coordination.
Dead time of 1 second is a standard value used in protection systems to account for relay operation time and communication delays.
It helps prevent false tripping by allowing for transient conditions to stabilize before initiating a trip.
For example, in a distance relay setting, a dead time of 1 second ens...
Reclaim time is 25 seconds to ensure proper coordination and selectivity of protection devices.
Reclaim time is set to allow downstream protective devices to clear faults before the upstream device operates.
It helps in preventing unnecessary tripping of healthy parts of the system.
The 25-second reclaim time is a standard value used in protection coordination studies.
Adjusting the reclaim time can impact the selectivity
I applied via LinkedIn and was interviewed in Jun 2024. There were 3 interview rounds.
I am a dedicated and experienced Project Control Engineer with a strong background in managing project schedules, budgets, and resources.
Over 5 years of experience in project control and management
Proficient in using project management software such as Primavera P6 and Microsoft Project
Skilled in analyzing project data and providing accurate forecasts
Strong communication and teamwork skills, able to collaborate with cr...
Primavera is a project management software used for planning, scheduling, and controlling projects.
Primavera is commonly used in industries such as construction, engineering, and manufacturing.
It allows users to create project schedules, allocate resources, track progress, and analyze project performance.
Users can generate reports, monitor costs, and manage risks within the software.
Primavera offers features like Gantt...
Different types of relationships include familial, romantic, professional, and platonic relationships.
Familial relationships: relationships between family members such as parents, siblings, and children.
Romantic relationships: intimate relationships between partners or spouses.
Professional relationships: relationships between colleagues or business partners.
Platonic relationships: non-romantic relationships based on fr
A schedule can be created by identifying project tasks, estimating durations, sequencing tasks, assigning resources, and setting milestones.
Identify all project tasks and break them down into smaller, manageable activities.
Estimate the duration of each task based on historical data or expert judgment.
Sequence the tasks in the order they need to be completed, considering dependencies between tasks.
Assign resources to ea...
A look-ahead report is a document that outlines upcoming tasks, potential issues, and solutions for a project.
Provides a snapshot of upcoming project activities
Highlights potential roadblocks and proposed solutions
Helps project team anticipate and plan for future challenges
Usually covers a short-term period, such as the next week or month
Steps to create a look-ahead report
Identify the project milestones and deadlines
Review the project schedule and identify upcoming tasks
Analyze potential risks and delays
Update the look-ahead report with current progress and forecasted completion dates
Communicate the report to stakeholders for awareness and decision-making
The 14 points of the DCMA are guidelines for effective project management in defense contracts.
Establish clear project objectives and requirements
Develop a realistic project schedule
Assign responsibilities and authorities clearly
Ensure adequate resources are available
Maintain open communication with stakeholders
Identify and manage project risks
Monitor and control project performance
Implement corrective actions when nec...
Earned value management is a project management technique for measuring project performance and progress.
Compares actual work completed and costs incurred to planned work and costs
Helps in forecasting project outcomes based on current performance
Key metrics include Planned Value (PV), Earned Value (EV), and Actual Cost (AC)
Formula: EV = % of work completed * Total budget
Example: If a project is 50% complete and the tot...
Key performance indicators are measurable values that demonstrate how effectively a company is achieving key business objectives.
KPIs are specific, quantifiable metrics used to track progress towards organizational goals.
They help in evaluating the success of a project or business by measuring performance in key areas.
Examples of KPIs for a Project Control Engineer may include project completion time, budget variance,
Formulas used to calculate Budget at Completion (BAC) in project control engineering.
BAC = Planned Value (PV) at completion
BAC = Actual Cost (AC) + Estimate to Complete (ETC)
BAC = Budgeted Cost of Work Scheduled (BCWS) + Budgeted Cost of Work Remaining (BCWR)
In five years, I see myself as a senior project control engineer leading a team of professionals and successfully managing complex projects.
Continuing to enhance my project management skills through advanced training and certifications
Taking on more responsibilities and leadership roles within the organization
Successfully completing several high-profile projects and delivering exceptional results
Mentoring and guiding j...
My salary expectations are in line with industry standards for a Project Control Engineer with my level of experience and qualifications.
Research industry standards for Project Control Engineer salaries
Consider my level of experience and qualifications
Be prepared to negotiate based on the overall compensation package offered
I am flexible with working hours and can adapt to the needs of the project. I am willing to work overtime when necessary.
I am open to working flexible hours to accommodate project needs
I am willing to work overtime when required to meet project deadlines
I can adjust my schedule to align with team meetings or client requirements
Orifice std refers to standard orifice sizes used in engineering. Types of taps include flange taps, corner taps, and D and D/2 taps.
Orifice std refers to standard sizes of orifices used in flow measurement
Types of taps include flange taps, corner taps, and D and D/2 taps
Flange taps are used for large pipes, corner taps for small pipes, and D and D/2 taps for general applications
Pressure gauge operating range refers to the minimum and maximum pressure values that the gauge can accurately measure.
Pressure gauge operating range is typically specified by the manufacturer.
It is important to ensure that the pressure being measured falls within the gauge's operating range to ensure accurate readings.
For example, a pressure gauge with an operating range of 0-100 psi should not be used to measure pres
Straight length requirements for orifice flow element ensure accurate measurement by allowing flow to stabilize before reaching the element.
Straight length requirements typically range from 10 to 44 pipe diameters upstream and 5 to 22 pipe diameters downstream of the orifice.
These requirements help prevent flow disturbances and ensure accurate measurement of flow rate.
For example, if the pipe diameter is 4 inches, the ...
I applied via Walk-in and was interviewed in Jun 2023. There were 2 interview rounds.
Burns & McDonnell interview questions for popular designations
I applied via LinkedIn and was interviewed before Apr 2023. There were 3 interview rounds.
Contact candidate to understand reasons for rejection, provide feedback, and keep communication open for future opportunities.
Contact the candidate to understand their reasons for rejecting the offer
Provide feedback on the interview process or offer to improve future interactions
Keep communication open for potential future opportunities with the candidate
Get interview-ready with Top Burns & McDonnell Interview Questions
I applied via Approached by Company and was interviewed in Oct 2023. There was 1 interview round.
I applied via Job Portal and was interviewed before Apr 2023. There were 2 interview rounds.
I applied via Naukri.com and was interviewed in Dec 2022. There were 3 interview rounds.
I applied via Referral and was interviewed in Mar 2023. There were 4 interview rounds.
I have experience working with ETAP on various projects, including designing power systems and conducting load flow analysis.
Designed power distribution systems using ETAP software
Conducted load flow analysis to optimize system performance
Implemented protective device coordination studies to ensure system reliability
Worked on projects involving power system modeling and simulation
posted on 27 Sep 2023
Technical quesgions were asked
Some of the top questions asked at the Burns & McDonnell interview for experienced candidates -
The duration of Burns & McDonnell interview process can vary, but typically it takes about less than 2 weeks to complete.
based on 13 interviews
Interview experience
based on 303 reviews
Rating in categories
Electrical Engineer
88
salaries
| ₹0 L/yr - ₹0 L/yr |
Senior Associate Engineer
50
salaries
| ₹0 L/yr - ₹0 L/yr |
Electrical Designer
50
salaries
| ₹0 L/yr - ₹0 L/yr |
Project Control Engineer
50
salaries
| ₹0 L/yr - ₹0 L/yr |
Senior Associate Electrical Engineer
36
salaries
| ₹0 L/yr - ₹0 L/yr |
Black & Veatch
AECOM
Jacobs Engineering Group
Fluor Corporation