Shuttering is a temporary structure used to support concrete while it sets for foundation & slab construction.
Shuttering is also known as formwork and is typically made of wood, steel, or plastic.
It is essential for creating the desired shape and structure of the foundation and slab.
Properly installed shuttering ensures the concrete is poured and cured correctly.
Examples of shuttering materials include plywood, timber
The one day target completion refers to completing a specific task within a 24-hour period.
Set clear and achievable goals for the day
Prioritize tasks based on urgency and importance
Delegate tasks if necessary to meet the deadline
Monitor progress throughout the day and make adjustments as needed
1 hour duration, related financial crisis
System implementation process involves planning, designing, testing, and deploying new software or hardware systems.
Planning phase involves defining project scope, setting goals, and creating a timeline.
Design phase includes creating system architecture, database design, and user interface.
Testing phase involves conducting various tests to ensure system functionality and performance.
Deployment phase includes installing...
Monitoring performance involves setting clear expectations, providing feedback, tracking progress, and addressing any issues that arise.
Set clear performance expectations for team members
Provide regular feedback on performance
Track progress towards goals and objectives
Address any performance issues promptly and constructively
posted on 21 Mar 2023
I applied via Referral and was interviewed in Feb 2023. There were 2 interview rounds.
I applied via Walk-in and was interviewed before Dec 2020. There were 5 interview rounds.
The neutral axis is the line where the stress is zero in a reinforced concrete structure.
The neutral axis divides the cross-section of the structure into two parts: the compression zone and the tension zone.
The depth of the neutral axis depends on the moment of resistance of the section and the bending moment applied.
The position of the neutral axis affects the amount of reinforcement required in the tension zone.
The n...
posted on 30 Nov 2023
I was interviewed before Nov 2022.
I applied via LinkedIn and was interviewed in May 2022. There were 3 interview rounds.
based on 1 interview
Interview experience
based on 3 reviews
Rating in categories
Assistant Manager
138
salaries
| ₹0 L/yr - ₹0 L/yr |
Senior Engineer
134
salaries
| ₹0 L/yr - ₹0 L/yr |
Site Engineer
92
salaries
| ₹0 L/yr - ₹0 L/yr |
Deputy Manager
77
salaries
| ₹0 L/yr - ₹0 L/yr |
Store Officer
69
salaries
| ₹0 L/yr - ₹0 L/yr |
Larsen & Toubro Limited
GMR Group
Reliance Infrastructure
IRB Infrastructure