Filter interviews by
To read iso, general arrangement, and other drawings, one needs to understand the symbols, dimensions, and annotations used in the drawings.
Understand the symbols used in the drawings, such as valves, pumps, and instruments.
Pay attention to the dimensions and measurements provided in the drawings.
Read the annotations and notes carefully to understand the specifications and requirements.
Refer to the drawing legends and ...
Job execution can be sequenced by breaking it down into smaller tasks and prioritizing them based on dependencies.
Identify all the tasks required to complete the job
Determine the dependencies between tasks
Prioritize the tasks based on their dependencies
Assign resources and timelines for each task
Monitor progress and adjust timelines as necessary
Yes, I have experience in project management and team leadership.
Project management skills
Team leadership experience
Ability to manage multiple projects simultaneously
Effective communication skills
Experience in budgeting and cost control
Proficient in relevant software and tools
Experience in risk assessment and mitigation
Top trending discussions
posted on 14 Jul 2017
I appeared for an interview before Jul 2016.
posted on 23 Oct 2020
I applied via Recruitment Consultant and was interviewed in Apr 2020. There were 3 interview rounds.
I applied via Recruitment Consultant and was interviewed in Sep 2019. There were 3 interview rounds.
posted on 12 Jul 2021
I applied via Referral and was interviewed before Jul 2020. There were 4 interview rounds.
posted on 30 Dec 2020
I applied via Naukri.com and was interviewed in Feb 2021. There were 2 interview rounds.
WHAT IS NPHSA AND WHAT IS PIPING STANDARD AND WHAT IS EQUPIPMENT LAYOUT
I applied via Company Website and was interviewed in Mar 2021. There were 4 interview rounds.
The procedure for erecting a Heat Exchanger involves several steps including site preparation, foundation installation, equipment placement, piping connection, and testing.
Prepare the site by leveling the ground and ensuring adequate space for the equipment
Install the foundation to support the weight of the Heat Exchanger
Place the Heat Exchanger on the foundation and secure it in place
Connect the piping to the Heat Exc...
Precautions before starting confined space work
Identify the confined space and assess the hazards
Ensure proper ventilation and air quality testing
Use appropriate personal protective equipment
Have a rescue plan in place and train all workers involved
Obtain necessary permits and follow all safety regulations
Communicate clearly with all workers involved in the job
Alignment of a column can be checked using various methods.
Visual inspection can be done to check if the column is straight and vertical.
Laser alignment tools can be used to check the alignment of the column.
String lines can be used to check the alignment of the column.
Plumb bobs can be used to check the vertical alignment of the column.
Optical instruments like theodolites can be used to check the alignment of the colu...
Acceptance limit for column alignment is typically 1/500th of the column height.
The acceptance limit for column alignment is usually specified in the project specifications.
It is typically 1/500th of the column height.
This means that for a 20-meter column, the maximum allowable deviation from vertical is 40 mm.
Alignment is critical for the proper functioning of the column and to prevent damage to the structure.
Alignmen...
I applied via Referral and was interviewed before Jun 2023. There was 1 interview round.
I applied via Walk-in and was interviewed in Jul 2022. There were 2 interview rounds.
Pipe supports are used to hold and position pipes in various applications.
Pipe hangers: Used to suspend pipes from ceilings or walls.
Pipe clamps: Used to secure pipes to structural supports.
Pipe shoes: Used to support pipes on flat surfaces.
Spring supports: Used to absorb vibrations and provide flexibility.
Rigid supports: Used to provide fixed support to pipes.
Variable supports: Used to accommodate thermal expansion an
Piping of pump involves selecting appropriate pipe size, routing, and supporting the pipe to avoid stress and vibration.
Select pipe size based on pump flow rate and pressure requirements
Route the pipe to minimize friction loss and avoid obstacles
Support the pipe adequately to avoid stress and vibration
Use appropriate fittings and valves to connect the pump to the piping system
Consider the material of the pipe and fitti...
based on 3 reviews
Rating in categories
Site Engineer
10
salaries
| ₹2 L/yr - ₹6.3 L/yr |
Store Keeper
8
salaries
| ₹1 L/yr - ₹10.5 L/yr |
Planning Engineer
8
salaries
| ₹17.5 L/yr - ₹40 L/yr |
HSE Officer
8
salaries
| ₹10.8 L/yr - ₹16 L/yr |
Procurement Engineer
7
salaries
| ₹11 L/yr - ₹22 L/yr |
Megha Engineering & Infrastructures
Shapoorji Pallonji Group
Alstom Transportation
Tata Technologies