LD for column refers to Liquidated Damages for delay in completing the column construction.
LD stands for Liquidated Damages.
It is a predetermined amount of money that the contractor will pay to the client in case of delay in completing the project.
LD for column specifically refers to the amount of money that will be deducted for each day of delay in constructing the column.
The LD amount is usually mentioned in the cont...
The mix ratio of M20 grade of concrete is 1:1.5:3.
The mix ratio of M20 grade of concrete means the proportion of cement, sand, and aggregate used in the concrete mix.
For M20 grade concrete, the mix ratio is 1 part cement : 1.5 parts sand : 3 parts aggregate.
This means that for every 1 part of cement, 1.5 parts of sand, and 3 parts of aggregate are used.
For example, if you have 1 bag of cement (50 kg), you would need 1....
The unit weight of steel varies depending on its type and grade.
The unit weight of steel is typically measured in pounds per cubic foot (lb/ft³) or kilograms per cubic meter (kg/m³).
The unit weight of common structural steel ranges from 490 to 7850 pounds per cubic foot (7850 to 12600 kg/m³).
For example, the unit weight of mild steel is approximately 490 pounds per cubic foot (7850 kg/m³).
The clear cover for a beam is the distance between the outer surface of the beam and the nearest surface of the concrete cover.
Clear cover is important to protect the reinforcement from corrosion and fire.
The clear cover for beams is typically specified in construction drawings or codes.
The clear cover can vary depending on the type of beam and its exposure conditions.
For example, in a residential building, the clear c...
The height of a parapet wall varies depending on its purpose and location.
The height of a parapet wall is typically determined by building codes and regulations.
In residential buildings, parapet walls are usually around 3 feet tall to provide safety and privacy.
In commercial or industrial buildings, parapet walls can be higher to serve as a barrier against noise, wind, or to hide rooftop equipment.
Historical buildings ...
posted on 9 Oct 2021
I applied via Referral and was interviewed in Sep 2021. There were 4 interview rounds.
High rise buildings require careful planning, design, and construction techniques.
Site selection and analysis
Structural design and analysis
Foundation design and construction
Use of high-strength materials
Installation of elevators and other building systems
Safety measures for workers and occupants
Quality control and testing
Regular maintenance and inspections
I applied via Job Portal
I applied via Referral and was interviewed before Mar 2022. There was 1 interview round.
I appeared for an interview in Jun 2019.
posted on 25 Jan 2025
I appeared for an interview before Jan 2024.
I have always been fascinated by the potential for growth and investment in real estate.
Passion for real estate market trends and opportunities
Enjoy working with people and helping them find their dream homes
Excited about the potential for financial growth and success in the industry
I reside in a cozy apartment in downtown Seattle.
I live in downtown Seattle
I have a cozy apartment
My residence is in a city
I can join the department within two weeks of receiving an offer.
I can start within two weeks of receiving an offer.
My current job requires a two-week notice period.
I have some personal commitments that I need to wrap up before starting.
I applied via Referral and was interviewed before Apr 2023. There were 3 interview rounds.
Written and excel test on real estate fundamentals
based on 2 reviews
Rating in categories
Senior Design Engineer
5
salaries
| ₹5.6 L/yr - ₹8 L/yr |
Communication Officer
5
salaries
| ₹7 L/yr - ₹8 L/yr |
Design Engineer
4
salaries
| ₹4.6 L/yr - ₹8.8 L/yr |
Project Manager
4
salaries
| ₹10 L/yr - ₹15 L/yr |
Project Engineer
4
salaries
| ₹4 L/yr - ₹6 L/yr |
Sunteck Realty
Balaji Enterprises
Pittie Group
ASSA ABLOY