Bolts are fixed by inserting them into pre-drilled holes and tightening them with a wrench.
Insert bolt into pre-drilled hole
Tighten bolt with a wrench
Ensure proper torque is applied
Use lock washers or thread-locking compound if necessary
To check column shuttering, inspect the alignment, verticality, and stability of the formwork.
Inspect the alignment of the column formwork with respect to the reference lines or grids.
Check the verticality of the formwork using a plumb bob or spirit level.
Ensure the stability of the shuttering by checking for any loose or damaged components.
Verify that the formwork is adequately braced to resist the concrete pressure.
I...
My role as a Civil Supervisor is to oversee construction projects and ensure they are completed on time, within budget, and meet quality standards.
Supervising and coordinating construction activities
Ensuring compliance with safety regulations and building codes
Managing project timelines and budgets
Communicating with contractors, engineers, and other stakeholders
Inspecting work sites and resolving any issues that arise
Top trending discussions
posted on 19 Jun 2022
I applied via Walk-in and was interviewed before Jun 2021. There were 2 interview rounds.
posted on 14 Feb 2021
PQC stands for Pavement Quality Concrete. It is a type of concrete used for road construction.
PQC is a high-quality concrete mix used for the construction of rigid pavements.
It is designed to withstand heavy traffic loads and resist wear and tear.
PQC is made with a higher cement content and a lower water-cement ratio than regular concrete.
It is also reinforced with steel bars or fibers to increase its strength and dura...
posted on 19 Feb 2021
I applied via Walk-in and was interviewed in Sep 2020. There was 1 interview round.
I applied via Company Website and was interviewed in Jun 2021. There was 1 interview round.
posted on 7 Sep 2022
I applied via Recruitment Consulltant and was interviewed before Sep 2021. There were 2 interview rounds.
I applied via Campus Placement and was interviewed before May 2021. There were 2 interview rounds.
Basic
I applied via Newspaper Ad and was interviewed before Apr 2021. There were 2 interview rounds.
What You know
What you mentioned in resume
I applied via Naukri.com and was interviewed in Jan 2021. There were 3 interview rounds.
Precommissioning tests of transformers ensure proper functioning and safety before energizing.
Visual inspection of transformer and its components
Measurement of insulation resistance
Measurement of winding resistance
Verification of transformer ratio and polarity
Verification of oil level and quality
Testing of protective devices
Verification of grounding
Functional testing of cooling system
Verification of nameplate data
11kv & 33kv overhead power line distribution
11kv and 33kv are common voltage levels for overhead power lines
Overhead power lines are used to distribute electricity from power stations to consumers
The voltage level determines the distance the power can be transmitted and the size of the conductors needed
Proper insulation and grounding is important for safety
Maintenance and inspection of the lines is necessary to ensure
based on 31 reviews
Rating in categories
Deputy Manager
616
salaries
| ₹5.4 L/yr - ₹21 L/yr |
Assistant Manager
606
salaries
| ₹3.7 L/yr - ₹14 L/yr |
Senior Engineer
509
salaries
| ₹3.4 L/yr - ₹11.2 L/yr |
Engineer
288
salaries
| ₹2.7 L/yr - ₹8.5 L/yr |
Manager
261
salaries
| ₹7.9 L/yr - ₹26 L/yr |
Larsen & Toubro Limited
L&T Construction
Tata Projects
Megha Engineering & Infrastructures