Free float is the amount of time a task can be delayed without delaying the project. Total float is the amount of time a task can be delayed without delaying the project's critical path. Critical path is the sequence of tasks that determines the project's duration.
Free float is the time available for a task to be delayed without affecting the project's schedule.
Total float is the time available for a task to be delayed...
Free float is the amount of time an activity can be delayed without affecting the early start of its successor activity.
Free float is calculated by subtracting the duration of an activity from the amount of time available before its successor activity must start.
Reducing free float can be achieved by shortening the duration of the activity or by overlapping activities.
Free float is important in determining the critical...
posted on 7 Aug 2023
I applied via campus placement at National Institute of Construction Management and Research, Pune and was interviewed before Aug 2022. There were 3 interview rounds.
30 mins 30 questions aptitude test
posted on 7 Aug 2023
I applied via campus placement at National Institute of Construction Management and Research, Pune and was interviewed before Aug 2022. There were 3 interview rounds.
30 mins 30 questions aptitude test
Assistant Manager
5.5k
salaries
| ₹1 L/yr - ₹10.5 L/yr |
Deputy Manager
3.5k
salaries
| ₹4.2 L/yr - ₹13.7 L/yr |
Manager
1.8k
salaries
| ₹6 L/yr - ₹25 L/yr |
Senior Manager
1.4k
salaries
| ₹10.4 L/yr - ₹32 L/yr |
Network Engineer
1.1k
salaries
| ₹1.7 L/yr - ₹9.3 L/yr |
Jio Platforms
Bharti Airtel
Vodafone Idea
Bharat Sanchar Nigam