P6 is a project management software used for scheduling, Float is the amount of time an activity can be delayed without delaying the project, Critical activities are tasks that must be completed on time to prevent project delays.
P6 is a software used for project scheduling and management
Float is the amount of time an activity can be delayed without affecting the project deadline
Critical activities are tasks that have z...
I applied via LinkedIn and was interviewed before Aug 2023. There were 2 interview rounds.
Managed various projects including software development, system integration, and process improvement.
Led a team in developing a new software application for streamlining customer data management
Implemented system integration solutions to improve communication between different departments
Executed process improvement initiatives to increase efficiency and reduce costs
Collaborated with cross-functional teams to ensure pr
Continuous learning, growth, challenging projects, leadership opportunities, work-life balance
Continuous learning and skill development through training and certifications
Opportunities for career growth and advancement
Challenging projects that allow for problem-solving and innovation
Leadership opportunities to mentor and guide junior team members
Maintaining a healthy work-life balance to prevent burnout
I applied via Naukri.com and was interviewed in Apr 2024. There was 1 interview round.
Minimum gap between two structures for seismic point of view is typically around 1.5 times the height of the taller structure.
Minimum gap is usually 1.5 times the height of the taller structure to reduce seismic interaction.
This gap helps prevent collision or structural damage during an earthquake.
Building codes and regulations may specify minimum gaps for seismic safety.
Example: If one building is 100 feet tall, the m...
I applied via Approached by Company and was interviewed before Mar 2022. There were 3 interview rounds.
It depends on the region, for me they conducted tool test in the 1st round.
I was interviewed in May 2023.
Bus bar schemes are different ways of connecting bus bars in power systems.
Single bus bar scheme
Double bus bar scheme
Main and transfer bus bar scheme
Ring bus bar scheme
Breaker and a half scheme
Mesh bus bar scheme
The equipment sequence for any line bay starts with the circuit breaker and ends with the transformer.
The circuit breaker is the first equipment in the sequence.
Next comes the isolator switch.
After that, the earth switch is operated.
Then the line disconnector is opened.
Finally, the transformer is disconnected from the line.
The sequence is reversed when the line bay is put back into service.
based on 4 reviews
Rating in categories
Quantity Surveyor
36
salaries
| ₹0 L/yr - ₹0 L/yr |
Manager Costing
26
salaries
| ₹0 L/yr - ₹0 L/yr |
Senior Quantity Surveyor
24
salaries
| ₹0 L/yr - ₹0 L/yr |
Civil Engineer
21
salaries
| ₹0 L/yr - ₹0 L/yr |
Assistant Costing Manager
18
salaries
| ₹0 L/yr - ₹0 L/yr |
AECOM
Jacobs Engineering Group
Bechtel
Fluor Corporation