Critical path is the longest path in a project schedule, representing the shortest time in which the project can be completed.
Critical path is the sequence of tasks that determines the total duration of a project.
It is the longest path through the project network diagram, with zero float or slack.
Any delay in tasks on the critical path will directly impact the project's completion date.
Identifying the critical path hel...
I applied via Company Website and was interviewed in Oct 2022. There were 3 interview rounds.
I applied via Walk-in and was interviewed in Jul 2022. There were 4 interview rounds.
Aptitude,reasoning,general and technical questions.
Greenko Group interview questions for popular designations
I was interviewed before Jun 2023.
The username of LA is typically a combination of letters, numbers, or symbols chosen by the user for identification purposes.
Usernames are unique identifiers used for logging into accounts or accessing online platforms.
LA could stand for Los Angeles, so the username might include references to the city or abbreviations like 'LA' or 'LAX'.
It could also be a personalized username chosen by the individual, such as 'LAlove
Transformer works on the principle of electromagnetic induction to transfer electrical energy between two or more circuits.
Transformers have two coils of wire, known as primary and secondary coils, wrapped around a core made of iron or steel.
When an alternating current flows through the primary coil, it creates a changing magnetic field around the core.
This changing magnetic field induces a voltage in the secondary coi...
Get interview-ready with Top Greenko Group Interview Questions
I applied via campus placement at University of Petroleum and Energy Studies (UPES), Dehradun and was interviewed before Oct 2022. There were 4 interview rounds.
Numbers,LCM,HCF,Time speed Distance,Percentage
They randomly given any topic. Time limit is 5-10 minutes in a group of 10 members. Everyone has to speak about the topic.
Types of concrete include normal strength, high strength, and high-performance concrete, each with different mix proportions.
Normal strength concrete: typically used for general construction, with mix proportions of 1:2:4 (cement:sand:aggregate)
High strength concrete: used for structures requiring higher strength, with mix proportions of 1:1.5:3
High-performance concrete: designed for specific applications, with mix pro
Steps involved in concreting & curing include preparation of formwork, mixing of concrete, pouring, leveling, finishing, and curing.
Prepare formwork by setting up wooden or metal molds to contain the concrete.
Mix concrete ingredients such as cement, sand, aggregate, and water in the correct proportions.
Pour the concrete into the formwork, ensuring it reaches all corners and edges.
Level the concrete surface using a scre...
Retaining walls are structures designed to hold back soil and prevent erosion.
Prevent soil erosion
Support sloping terrain
Create usable space on a hillside
Enhance landscaping design
Bending moment & Shear force diagrams show the variation of internal forces along the length of a beam.
Bending moment diagram shows the variation of bending moment along the length of a beam.
Shear force diagram shows the variation of shear force along the length of a beam.
These diagrams are essential for analyzing the behavior of beams under different loading conditions.
The diagrams help in determining the maximum bend...
Quantity Surveyors manage costs and contracts for construction projects, both on-site and in the office.
Preparing cost estimates and budgets
Analyzing construction plans and specifications
Negotiating with contractors and suppliers
Managing contracts and variations
Conducting site visits and inspections
Preparing progress reports and final accounts
I applied via Referral and was interviewed before Oct 2022. There were 3 interview rounds.
I applied via Naukri.com and was interviewed before Oct 2022. There were 2 interview rounds.
Clearances in the station refer to the process of ensuring that all necessary approvals and permissions are obtained before proceeding with a task or project.
Clearances may include safety clearances, security clearances, and regulatory clearances.
Examples of clearances in a station could be obtaining permission from the fire department before conducting a fire drill, or ensuring that all employees have completed backgr...
The standard of maintaining refers to the level of quality and consistency in upkeep and repair of equipment or systems.
Regular inspections and preventative maintenance are essential
Documentation of maintenance activities should be kept
Adherence to manufacturer's guidelines and industry standards is important
Proper training and certification of maintenance personnel is necessary
The minimum requirements for employees standard vary depending on the industry and job position.
Minimum age requirement
Education and certification
Experience and skills
Physical and mental fitness
Background check and drug test
Language proficiency
Work authorization
Compliance with company policies and regulations
I applied via campus placement at National Institute of Construction Management and Research (NICMR) and was interviewed in Jan 2022. There were 2 interview rounds.
Regarding basic technical concepts on civil engineering
Top trending discussions
Some of the top questions asked at the Greenko Group interview -
based on 51 interviews
Interview experience
based on 747 reviews
Rating in categories
Assistant Manager
395
salaries
| ₹2.5 L/yr - ₹10 L/yr |
Deputy Manager
267
salaries
| ₹4.1 L/yr - ₹14.5 L/yr |
Officer
230
salaries
| ₹2 L/yr - ₹7.2 L/yr |
Manager
78
salaries
| ₹6.8 L/yr - ₹20 L/yr |
Senior Manager
70
salaries
| ₹7.8 L/yr - ₹25 L/yr |
Adani Green Energy
Tata Power Renewable Energy
ReNew
Hero Future Energies