Interview Questionnaire 

8 Questions

  • Q1. What is WBS
  • Ans. 

    WBS stands for Work Breakdown Structure, a hierarchical decomposition of project deliverables into smaller, manageable components.

    • WBS is a tool used in project management to organize and define the scope of a project

    • It breaks down the project into smaller, more manageable components

    • Each component is then assigned a unique identifier and can be further broken down into smaller components

    • WBS helps in estimating project c...

  • Answered by AI
  • Q2. How to do Progress payment
  • Ans. 

    Progress payment is a payment made to a contractor based on the percentage of work completed.

    • Determine the percentage of work completed

    • Agree on the payment schedule with the contractor

    • Verify the work completed before making the payment

    • Ensure the payment is made on time to avoid delays

    • Keep accurate records of progress payments made

  • Answered by AI
  • Q3. How to make Contract for vendors
  • Ans. 

    A contract for vendors should clearly define the scope of work, payment terms, delivery schedule, quality standards, and dispute resolution mechanisms.

    • Define the scope of work and deliverables

    • Specify the payment terms and schedule

    • Set quality standards and acceptance criteria

    • Include provisions for warranties and guarantees

    • Outline the dispute resolution mechanisms

    • Include clauses for termination and breach of contract

    • Ensu...

  • Answered by AI
  • Q4. ERP Responsibilities
  • Q5. Vendors Quotation negotiations
  • Q6. Primavera P6 Knowledge, MS project Excel in advanve
  • Q7. Weekly reports and meeting with client
  • Q8. Meeting with vendors

Interview questions from similar companies

I applied via Company Website and was interviewed before May 2021. There was 1 interview round.

Round 1 - Technical 

(1 Question)

  • Q1. What is impidance,DGR FUNDAMENTAL AND BASICS
  • Ans. 

    Impedance is the measure of opposition to the flow of electric current in a circuit. DGR fundamental refers to the Dielectric Withstand Voltage test.

    • Impedance is measured in ohms and is the combination of resistance, capacitance, and inductance in a circuit.

    • DGR fundamental is a test to determine the maximum voltage a material can withstand without breaking down.

    • Basics of impedance include understanding the relationship...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Clear basics fundamental of electrical
Round 1 - Technical 

(1 Question)

  • Q1. Codes, materials, concrete

Interview Preparation Tips

Interview preparation tips for other job seekers - Prepare well before going for interview
Specifically technical questions
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - Aptitude Test 

Nothing much , rest is basically technical

Round 3 - Group Discussion 

We have to talk on a subject for log time thats all

Round 4 - One-on-one 

(2 Questions)

  • Q1. How to speed control on motor and generator.
  • Ans. 

    Speed control on motors and generators can be achieved through various methods.

    • For motors, speed control can be achieved by adjusting the voltage, frequency, or the number of poles.

    • For generators, speed control can be achieved by adjusting the mechanical input or the load connected to the generator.

    • In motors, variable frequency drives (VFDs) can be used to control the speed by adjusting the frequency of the power suppl...

  • Answered by AI
  • Q2. What is IDFT controller ?
  • Ans. 

    IDFT controller stands for Inverse Discrete Fourier Transform controller.

    • IDFT controller is used in signal processing to convert frequency domain signals to time domain signals.

    • It is the inverse of the Discrete Fourier Transform (DFT) controller.

    • IDFT controller is commonly used in audio and video processing applications.

    • It is also used in communication systems to convert frequency domain signals to time domain signals ...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Have a great confidence and idea . answer only those you know dont blabber

I applied via Naukri.com and was interviewed in Nov 2021. There was 1 interview round.

Round 1 - Technical 

(2 Questions)

  • Q1. What is impedance ,reacance
  • Ans. 

    Impedance is the total opposition to the flow of alternating current in a circuit, while reactance is the opposition to the flow of alternating current caused by capacitance or inductance.

    • Impedance is a combination of resistance and reactance in a circuit.

    • Reactance is the opposition to the flow of alternating current caused by capacitance or inductance.

    • Capacitive reactance is the opposition to the flow of alternating c...

  • Answered by AI
  • Q2. How calculate plant load factors
  • Ans. 

    Plant load factor is calculated by dividing the actual energy generated by the maximum possible energy that could have been generated.

    • Plant load factor = Actual energy generated / Maximum possible energy that could have been generated

    • Maximum possible energy is calculated by multiplying the rated capacity of the plant with the number of hours in a given time period

    • Plant load factor is expressed as a percentage

    • It is used...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Focus on fundamental, And answer with clear mindset
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - HR 

(1 Question)

  • Q1. Shortlisting as per the JD.
Round 3 - Technical 

(1 Question)

  • Q1. Thermodynamics & Thermal Engineering
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Group Discussion 

About power plants activities

Round 2 - HR 

(1 Question)

  • Q1. Salary discussion
Round 3 - No 

(1 Question)

  • Q1. No question asked
Interview experience
4
Good
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Naukri.com and was interviewed in Jul 2023. There were 2 interview rounds.

Round 1 - HR 

(1 Question)

  • Q1. Salary discussion & general discussion
Round 2 - Group Discussion 

Technical interview with concerned HOD

Interview experience
1
Bad
Difficulty level
Easy
Process Duration
2-4 weeks
Result
Selected Selected

I appeared for an interview before Mar 2024, where I was asked the following questions.

  • Q1. Why do you want to work here
  • Q2. What are your future plans
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Company Website and was interviewed before Jul 2022. There were 3 interview rounds.

Round 1 - Technical 

(1 Question)

  • Q1. What is the ir resistance of moyor?
  • Ans. 

    The IR resistance of a motor refers to the insulation resistance, which measures the resistance of the insulation material surrounding the motor windings.

    • IR resistance is measured in ohms and indicates the ability of the insulation to prevent current leakage.

    • A higher IR resistance value indicates better insulation quality and less risk of electrical faults.

    • Regular testing of IR resistance is important to ensure the mot...

  • Answered by AI
Round 2 - HR 

(1 Question)

  • Q1. Why you intrested doing job??
Round 3 - Other 

(1 Question)

  • Q1. How much expected salary

Doosan Power Systems Interview FAQs

How to prepare for Doosan Power Systems Planning Engineer interview?
Go through your CV in detail and study all the technologies mentioned in your CV. Prepare at least two technologies or languages in depth if you are appearing for a technical interview at Doosan Power Systems. The most common topics and skills that interviewers at Doosan Power Systems expect are Budgeting, Cash Flow, Execution, Forecasting and MS Project.
What are the top questions asked in Doosan Power Systems Planning Engineer interview?

Some of the top questions asked at the Doosan Power Systems Planning Engineer interview -

  1. how to make Contract for vend...read more
  2. how to do Progress payme...read more
  3. what is ...read more

Tell us how to improve this page.

Interview Questions from Similar Companies

Vestas Interview Questions
4.3
 • 88 Interviews
Hitachi Energy Interview Questions
4.1
 • 88 Interviews
Siemens Energy Interview Questions
4.1
 • 76 Interviews
Assystem Interview Questions
3.6
 • 46 Interviews
Enphase Energy Interview Questions
2.9
 • 43 Interviews
Inox Wind Interview Questions
3.7
 • 38 Interviews
L&T Power Interview Questions
3.9
 • 33 Interviews
View all
Doosan Power Systems Planning Engineer Salary
based on 22 salaries
₹2.8 L/yr - ₹9.9 L/yr
24% less than the average Planning Engineer Salary in India
View more details

Doosan Power Systems Planning Engineer Reviews and Ratings

based on 5 reviews

4.3/5

Rating in categories

3.4

Skill development

3.3

Work-life balance

3.2

Salary

3.2

Job security

3.5

Company culture

2.8

Promotions

3.9

Work satisfaction

Explore 5 Reviews and Ratings
Deputy Manager
222 salaries
unlock blur

₹5 L/yr - ₹17.5 L/yr

Manager
161 salaries
unlock blur

₹5.8 L/yr - ₹24.1 L/yr

Senior Engineer
159 salaries
unlock blur

₹4 L/yr - ₹12 L/yr

Engineer
87 salaries
unlock blur

₹3 L/yr - ₹8.4 L/yr

Senior Manager
63 salaries
unlock blur

₹10 L/yr - ₹32 L/yr

Explore more salaries
Compare Doosan Power Systems with

Vestas

4.3
Compare

Dhoot Transmission

3.7
Compare

Hitachi Energy

4.1
Compare

Siemens Energy

4.1
Compare
Did you find this page helpful?
Yes No
write
Share an Interview