Filter interviews by
The question is about the specifications of different layers in a flexible pavement.
The embankment layer has a thickness of 3m and is compacted at 95% with large size soil particles and effective CBR as per design.
The subgrade layer has a total thickness of 500mm and is compacted at 97% with large size soil particles and effective CBR as per design.
The GSB layer has a total thickness of 300mm and is a mixture of aggreg...
Design procedure for laying M15 grade concrete with specific requirements for cement content, compressive strength, and compaction.
Use M15 grade concrete with aggregate and cement ratio of 1:2
Minimum cement content of 150kg per cum, or 120kg per cum if flyash is more than 20%
Ensure compressive strength of 10MPA after 7 days curing, with no sample below 7.5MPA
Ensure DLC premix batching plant material is homogeneous and ...
Design procedure for PQC using M40 grade concrete
Minimum cement content of 360kg per cum
Flexural strength of 4.5MPA and compressive strength of 40MPA after 28-day curing
Dowel bars and tie bars provided for load transfer and prevention of cracking and deflection
PQC mix prepared in pre-mix batching plant and transported to site
Separation membrane and texturing and sawing operations performed for proper finishing
28-day cu...
Different types of carriage way include single lane, multilane, intermediate lane, two lane, three lane, and four lane.
Single lane has a width of 3.75m
Multilane has a width of 3.50m
Intermediate lane has a width of 5.5m
Two lane has a width of 7.5m
Three lane has a width of 10.50m
Four lane has a width of 7.5m + 7.5m
Top trending discussions
posted on 9 Feb 2025
I appeared for an interview in Aug 2024.
Rounds on technical aptitude and on process managemnet.
Case study situatiknal questions etc
I applied via Company Website and was interviewed in Mar 2021. There was 1 interview round.
posted on 13 Aug 2021
I applied via Naukri.com and was interviewed before Aug 2020. There were 4 interview rounds.
I applied via Recruitment Consultant and was interviewed in Sep 2019. There were 3 interview rounds.
I applied via Recruitment Consultant and was interviewed before Oct 2020. There was 1 interview round.
I applied via Campus Placement and was interviewed before Mar 2020. There were 4 interview rounds.
The question is unclear and lacks context.
Please provide more information about the 'update shuttering system'.
Specify the time frame for the updates.
Clarify the purpose or objective of the updates.
Provide any relevant examples or scenarios.
I want to work as an execution engineer because I enjoy the challenge of overseeing and coordinating all aspects of a project.
As an execution engineer, I would have the opportunity to work on a variety of projects and oversee all aspects of their execution.
I enjoy the challenge of coordinating different teams and ensuring that everything runs smoothly.
While working on a formwork or quality team would be valuable experi...
Concrete is the most important as it provides the strength and durability to the structure.
Concrete is the backbone of any RCC structure.
It provides the strength and durability to the structure.
Reinforcements and formwork are important too, but without concrete, they are useless.
Proper mix design and curing of concrete are crucial for the longevity of the structure.
I applied via Company Website and was interviewed before Apr 2020. There were 4 interview rounds.
Mix design of concrete and BTech project
Mix design involves determining the proportions of cement, water, aggregates, and admixtures to achieve desired properties of concrete
Factors like strength, workability, durability, and cost are considered while designing the mix
BTech project can involve studying the effect of different mix designs on properties of concrete or developing a new mix design
Examples of BTech projects...
Some of the top questions asked at the Ashoka Buildcon Senior Project Manager interview -
based on 2 reviews
Rating in categories
Engineer
198
salaries
| ₹1.8 L/yr - ₹5.5 L/yr |
Senior Engineer
147
salaries
| ₹3.5 L/yr - ₹10 L/yr |
Store Keeper
78
salaries
| ₹1.8 L/yr - ₹4.2 L/yr |
Site Engineer
76
salaries
| ₹1.8 L/yr - ₹5.5 L/yr |
Civil Engineer
72
salaries
| ₹2.1 L/yr - ₹6 L/yr |
L&T Construction
Simplex Infrastructures
ITD Cementation India
AtkinsRealis