Productivity rates for small bore pipe welding depend on various factors such as pipe diameter, welding position, and welding process.
Productivity rates can vary from 2-10 inches per hour depending on the pipe diameter.
Welding position also affects productivity rates. Overhead welding is slower than flat or horizontal welding.
Welding process used also plays a role in productivity rates. TIG welding is slower than MIG w...
I applied via Approached by Company and was interviewed in Apr 2022. There were 2 interview rounds.
Reconciling materials involves comparing actual usage with planned usage and identifying discrepancies.
Review the project plan and compare it to actual usage
Identify any discrepancies and investigate the cause
Adjust the plan as necessary to account for any changes in material usage
Communicate any changes to relevant stakeholders
Ensure that all materials are properly accounted for and documented
What people are saying about Afcons Infrastructure
I applied via Naukri.com and was interviewed in Feb 2022. There were 2 interview rounds.
Afcons Infrastructure interview questions for designations
I applied via campus placement at National Institute of Construction Management and Research, Pune and was interviewed before Nov 2021. There were 3 interview rounds.
Basic civil and planning engineering related questions.
Productivity rate for aluminium formwork depends on various factors such as the size of the project, complexity of the structure, experience of workers, and availability of equipment.
Productivity rate can range from 20 to 40 square meters per hour per worker.
Experienced workers can achieve higher productivity rates.
Availability of equipment such as cranes and hoists can also affect productivity.
The size and complexity ...
I applied via Naukri.com and was interviewed in Oct 2020. There were 3 interview rounds.
I applied via Campus Placement and was interviewed before Oct 2021. There were 3 interview rounds.
posted on 11 Aug 2024
Baselines in Primavera are snapshots of the project schedule at a specific point in time, used for comparison and tracking progress.
Baselines capture the original project plan before any changes are made.
They are used as a reference point to compare actual progress against planned progress.
Baselines help in identifying deviations from the original plan and taking corrective actions.
In Primavera, baselines can be create...
To track a project in Primavera P6 on a daily basis, use the following steps.
Update progress for each activity daily
Review critical path activities regularly
Monitor resource allocation and availability
Compare planned vs. actual progress
Generate daily reports for stakeholders
I applied via Campus Placement
The test was based on logical reasoning and verbal reasoning.
EVM stands for Earned Value Management. It is a project management technique used to measure project performance and progress.
EVM integrates scope, schedule, and cost to provide a comprehensive view of project performance.
It compares the planned value (PV), earned value (EV), and actual cost (AC) to assess project health.
PV represents the budgeted cost of the work scheduled, EV represents the budgeted cost of the work ...
2 Interview rounds
based on 41 reviews
Rating in categories
Senior Engineer
434
salaries
| ₹5.6 L/yr - ₹19 L/yr |
Planning Engineer
197
salaries
| ₹4.5 L/yr - ₹12 L/yr |
Civil Engineer
182
salaries
| ₹2 L/yr - ₹10.7 L/yr |
Executive Engineer
172
salaries
| ₹3.2 L/yr - ₹11.8 L/yr |
Engineer
163
salaries
| ₹3.5 L/yr - ₹10.1 L/yr |
Larsen & Toubro Limited
Tata Projects
Shapoorji Pallonji Group
GAMMON INDIA