Precommissioning tests of transformers ensure proper functioning and safety before energizing.
Visual inspection of transformer and its components
Measurement of insulation resistance
Measurement of winding resistance
Verification of transformer ratio and polarity
Verification of oil level and quality
Testing of protective devices
Verification of grounding
Functional testing of cooling system
Verification of nameplate data
11kv & 33kv overhead power line distribution
11kv and 33kv are common voltage levels for overhead power lines
Overhead power lines are used to distribute electricity from power stations to consumers
The voltage level determines the distance the power can be transmitted and the size of the conductors needed
Proper insulation and grounding is important for safety
Maintenance and inspection of the lines is necessary to ensure
posted on 20 Jul 2017
I applied via Walk-in and was interviewed before Apr 2021. There were 3 interview rounds.
I applied via Walk-in and was interviewed before May 2021. There were 2 interview rounds.
CODAL provisions for concrete refer to the guidelines and regulations set by relevant authorities, while commands of software are the specific instructions or functions within a software program.
CODAL provisions for concrete include specifications for mix design, strength requirements, and durability standards.
Commands of software for site engineers may include functions for structural analysis, quantity takeoff, and p...
I applied via Naukri.com and was interviewed before Sep 2021. There were 3 interview rounds.
posted on 6 Feb 2024
Working of power transformer
Power factor of an alternator is a measure of how effectively it converts mechanical power into electrical power.
Power factor is the cosine of the angle between the voltage and current waveforms in an AC circuit.
It indicates the phase difference between voltage and current and ranges from 0 to 1.
A power factor of 1 means the alternator is operating at maximum efficiency.
A lagging power factor (less than 1) indicates th...
I applied via LinkedIn and was interviewed before Oct 2022. There were 4 interview rounds.
based on 3 interviews
Interview experience
based on 7 reviews
Rating in categories
Field Engineer
59
salaries
| ₹2.7 L/yr - ₹5 L/yr |
Assistant Manager
53
salaries
| ₹3 L/yr - ₹9 L/yr |
Section Engineer
47
salaries
| ₹3.2 L/yr - ₹5.5 L/yr |
Resident Engineer
44
salaries
| ₹6.6 L/yr - ₹21.5 L/yr |
Site Engineer
42
salaries
| ₹2.8 L/yr - ₹7.8 L/yr |
L&T Construction
Tata Projects
Shapoorji Pallonji Group
Kalpataru Projects International