The pourstrip is a critical component for support in quality control. Its removal could lead to potential issues in product packaging and quality assurance.
Loss of structural integrity in packaging
Increased risk of contamination or tampering
Difficulty in handling and storage of products
Potential impact on product shelf life and quality
Need for alternative support measures or redesign of packaging
Concrete should be poured in pour strips after completing a certain section of formwork to prevent cracking and ensure proper curing.
Concrete should be poured in pour strips after completing a certain section of formwork to prevent cracking.
Pour strips are typically used in large concrete pours to control the placement and curing of the concrete.
The timing of pour strips will depend on the size and complexity of the pr...
Shuttering can be managed without removing supports under slab and pourstrip by using adjustable props and beams.
Use adjustable props to support the slab and pourstrip while removing the shuttering.
Install beams to transfer the load from the slab to the props, allowing the supports to be removed.
Ensure proper alignment and spacing of props and beams to distribute the load evenly.
Regularly check and adjust the props and...
Checks in concrete include slump test, air content test, temperature monitoring. At column and slab junction, check for proper reinforcement placement, formwork alignment, and concrete pouring.
Perform slump test to ensure proper consistency of concrete
Check air content to ensure proper durability and workability
Monitor temperature to prevent issues like thermal cracking
At column and slab junction, check reinforcement p...
I applied via Job Portal
Vensa Infrastructure interview questions for popular designations
I applied via LinkedIn and was interviewed in Nov 2023. There was 1 interview round.
I applied via Naukri.com and was interviewed in Sep 2023. There were 3 interview rounds.
I applied via Walk-in and was interviewed before Sep 2023. There was 1 interview round.
The current carrying capacity of a 185sqmm al cable depends on various factors such as the material, insulation, and installation method.
The current carrying capacity of a cable is typically determined by the manufacturer and specified in the cable's datasheet.
Factors such as the material (aluminum in this case), insulation type, ambient temperature, and installation method all affect the current carrying capacity.
For ...
The height of a dB location on a wall depends on the specific requirements of the project or application.
The height of a dB location on a wall is typically determined by the specific needs of the project or application.
Factors such as the type of equipment being installed, the purpose of the dB location, and the layout of the space will influence the height chosen.
For example, in a control room setting, dB locations ma...
I applied via Recruitment Consulltant and was interviewed in Jul 2022. There were 2 interview rounds.
I applied via Referral and was interviewed in Feb 2022. There was 1 interview round.
The work permit system is used to ensure the safety of workers by controlling hazardous work activities.
To identify and assess potential hazards before starting work
To establish control measures to mitigate risks
To communicate and coordinate work activities among different teams
To ensure compliance with safety regulations and standards
To prevent accidents, injuries, and property damage
To provide a systematic approach f...
I applied via Recruitment Consulltant and was interviewed in Feb 2022. There were 2 interview rounds.
To accomplish the task that is set out to
Top trending discussions
Interview experience
based on 144 reviews
Rating in categories
Civil Site Engineer
23
salaries
| ₹3 L/yr - ₹6 L/yr |
Senior Engineer
20
salaries
| ₹4 L/yr - ₹7.2 L/yr |
Accountant
16
salaries
| ₹2.9 L/yr - ₹5 L/yr |
Civil Engineer
15
salaries
| ₹2.5 L/yr - ₹5 L/yr |
Site Engineer
13
salaries
| ₹2 L/yr - ₹6.5 L/yr |
Larsen & Toubro Limited
Tata Projects
GMR Group
Hindustan Construction Company