Q1. How can u mange shuttering without removing supports under slab and pourstrip
Shuttering can be managed without removing supports under slab and pourstrip by using adjustable props and beams.
Use adjustable props to support the slab and pourstrip while removing the shuttering.
Install beams to transfer the load from the slab to the props, allowing the supports to be removed.
Ensure proper alignment and spacing of props and beams to distribute the load evenly.
Regularly check and adjust the props and beams to maintain stability during the construction proce...read more
Q2. What checks do u do while doing in concrete and how will do in column and slab junction
Checks in concrete include slump test, air content test, temperature monitoring. At column and slab junction, check for proper reinforcement placement, formwork alignment, and concrete pouring.
Perform slump test to ensure proper consistency of concrete
Check air content to ensure proper durability and workability
Monitor temperature to prevent issues like thermal cracking
At column and slab junction, check reinforcement placement for proper strength
Ensure formwork alignment to p...read more
Q3. What would happen if support removed at pourstrip
The pourstrip is a critical component for support in quality control. Its removal could lead to potential issues in product packaging and quality assurance.
Loss of structural integrity in packaging
Increased risk of contamination or tampering
Difficulty in handling and storage of products
Potential impact on product shelf life and quality
Need for alternative support measures or redesign of packaging
Q4. When will do concreate in pourstrip
Concrete should be poured in pour strips after completing a certain section of formwork to prevent cracking and ensure proper curing.
Concrete should be poured in pour strips after completing a certain section of formwork to prevent cracking.
Pour strips are typically used in large concrete pours to control the placement and curing of the concrete.
The timing of pour strips will depend on the size and complexity of the project, as well as the weather conditions.
For example, in a...read more
Q5. What is the current carrying capacity of 185sqmm al cable .
The current carrying capacity of a 185sqmm al cable depends on various factors such as the material, insulation, and installation method.
The current carrying capacity of a cable is typically determined by the manufacturer and specified in the cable's datasheet.
Factors such as the material (aluminum in this case), insulation type, ambient temperature, and installation method all affect the current carrying capacity.
For a 185sqmm aluminum cable, the current carrying capacity ca...read more
Q6. What is the Height of db location on wall.
The height of a dB location on a wall depends on the specific requirements of the project or application.
The height of a dB location on a wall is typically determined by the specific needs of the project or application.
Factors such as the type of equipment being installed, the purpose of the dB location, and the layout of the space will influence the height chosen.
For example, in a control room setting, dB locations may be placed at eye level for easy access and visibility.
In...read more
Q7. Why use the work permit system?
The work permit system is used to ensure the safety of workers by controlling hazardous work activities.
To identify and assess potential hazards before starting work
To establish control measures to mitigate risks
To communicate and coordinate work activities among different teams
To ensure compliance with safety regulations and standards
To prevent accidents, injuries, and property damage
To provide a systematic approach for managing high-risk tasks
To promote a safety culture wit...read more
Top HR Questions asked in Coforge
Interview Process at Coforge
Top Interview Questions from Similar Companies
Reviews
Interviews
Salaries
Users/Month