Q1. What will you do if the site qty differ from Drawing qty

Ans.

If the site quantity differs from the drawing quantity, I will take the following steps to address the issue.

  • I will review the drawings and specifications to ensure accuracy.

  • I will communicate with the project team, including the architect and engineer, to clarify any discrepancies.

  • I will conduct a site visit to physically verify the quantities and compare them with the drawings.

  • If there are significant differences, I will document them and notify the relevant parties, such a...read more

View 7 more answers

Q2. What is margin for OH & Profits in Rate analysis

Ans.

Margin for OH & Profits in rate analysis is the additional amount added to cover overhead costs and generate profit.

  • Margin for OH & Profits is added to the direct cost of a project to cover indirect costs and generate profit.

  • It is usually expressed as a percentage of the direct cost.

  • The margin for OH & Profits varies depending on the nature of the project and market conditions.

  • For example, if the direct cost of a project is $100,000 and the margin for OH & Profits is 10%, the...read more

View 3 more answers

Q3. What is reconciliation of steel

Ans.

Reconciliation of steel involves comparing the actual quantity of steel used in a construction project with the estimated quantity.

  • Reconciliation of steel is a process used in construction projects to ensure that the actual quantity of steel used matches the estimated quantity.

  • It involves comparing the quantity of steel recorded in the project's documentation, such as drawings and specifications, with the quantity of steel actually installed on site.

  • Any discrepancies between ...read more

View 5 more answers

Q4. What is rolling margin

Ans.

Rolling margin is a financial term that refers to the difference between the revenue generated and the variable costs incurred over a specific period of time.

  • Rolling margin is used to measure the profitability of a business or project.

  • It helps in assessing the efficiency of operations and identifying areas for cost reduction.

  • The formula for calculating rolling margin is: (Revenue - Variable Costs) / Revenue * 100.

  • For example, if a company generates $100,000 in revenue and inc...read more

View 3 more answers
Discover null interview dos and don'ts from real experiences

Q5. Wastage % for Reinforcement Steel

Ans.

The wastage percentage for reinforcement steel varies depending on factors such as project complexity and workmanship.

  • Wastage percentage for reinforcement steel is typically estimated between 2-5%.

  • Factors such as project complexity, workmanship, and site conditions can affect the wastage percentage.

  • Proper planning, accurate cutting, and careful handling can help minimize wastage.

  • Examples of wastage include incorrect cutting, damage during transportation, and unused offcuts.

  • Re...read more

View 4 more answers

Q6. How you do the rate analysis

Ans.

Rate analysis is done by breaking down the cost of each item in a construction project to determine the overall cost.

  • Rate analysis involves breaking down the cost of each item in a construction project.

  • The cost of materials, labor, and equipment is analyzed to determine the overall cost.

  • Quantities of each item are measured and multiplied by their respective rates to calculate the cost.

  • Rate analysis helps in estimating the budget for a project and comparing different options.

  • F...read more

View 3 more answers

Q7. Code for Structural steel and reinforced steel

Ans.

The code for structural steel is typically governed by the American Institute of Steel Construction (AISC) while reinforced steel is governed by the American Concrete Institute (ACI).

  • Structural steel is commonly used in the construction of buildings, bridges, and other structures.

  • The AISC provides standards and guidelines for the design, fabrication, and erection of structural steel.

  • Reinforced steel, also known as rebar, is used to strengthen concrete structures.

  • The ACI provi...read more

View 1 answer

Q8. What is the procedure for BBS

Ans.

BBS stands for Bar Bending Schedule, which is a detailed list of reinforcement bars in a concrete element.

  • BBS is prepared based on the structural drawings and specifications.

  • It includes the diameter, length, shape, and number of reinforcement bars required for the element.

  • BBS helps in estimating the quantity of steel required and also ensures the correct placement of reinforcement bars.

  • It is an essential document for the construction team and is used during the fabrication, t...read more

Add your answer
Contribute & help others!
Write a review
Share interview
Contribute salary
Add office photos
Interview Tips & Stories
Ace your next interview with expert advice and inspiring stories
Share an Interview
Stay ahead in your career. Get AmbitionBox app
qr-code
Helping over 1 Crore job seekers every month in choosing their right fit company
70 Lakh+

Reviews

5 Lakh+

Interviews

4 Crore+

Salaries

1 Cr+

Users/Month

Contribute to help millions
Get AmbitionBox app

Made with ❤️ in India. Trademarks belong to their respective owners. All rights reserved © 2024 Info Edge (India) Ltd.

Follow us
  • Youtube
  • Instagram
  • LinkedIn
  • Facebook
  • Twitter