The topics were of technical nature on Civil Engineering.
Yes, I have experience dealing with EPC Contracts.
Managed multiple EPC Contracts for construction projects
Negotiated terms and conditions with contractors and vendors
Ensured compliance with project specifications and timelines
Resolved disputes and issues that arose during contract execution
I applied via Approached by Company and was interviewed in Oct 2022. There were 3 interview rounds.
Technical questions about Construction engineering..
I applied via Company Website and was interviewed in Jun 2022. There were 3 interview rounds.
I applied via Referral and was interviewed in Feb 2022. There were 2 interview rounds.
The height of Piperack tier 1 depends on various factors such as the size of the pipes and the distance between them.
The height of Piperack tier 1 can range from 3 to 6 meters.
The height is determined by the size of the pipes and the distance between them.
The height also depends on the weight of the pipes and the load they can bear.
The height may vary based on the location and the purpose of the Piperack.
Consulting the...
Codes and standards are guidelines and regulations that ensure safety, quality, and consistency in various industries.
Codes and standards are developed by industry organizations, government agencies, and professional associations.
They cover a wide range of topics such as building codes, electrical codes, safety standards, and environmental regulations.
Compliance with codes and standards is often mandatory and failure t...
A pile is a long, cylindrical structure made of materials such as concrete, steel, or wood, used to support heavy loads.
Piles are commonly used in construction to support buildings, bridges, and other structures.
They are driven or drilled into the ground to provide stability and prevent settling or shifting.
Different types of piles include timber, concrete, steel, and composite piles.
Pile foundations are often used in ...
Vertical load test of pile is a test to determine the load carrying capacity of a pile.
A vertical load is applied to the pile using a hydraulic jack or a reaction frame.
The load is increased until the pile reaches its ultimate capacity or a predetermined limit.
The test helps in determining the pile's load settlement behavior and its ultimate bearing capacity.
The test is commonly used in the construction industry to ens...
Lateral load test of pile is a test to determine the lateral capacity of a pile.
It involves applying a horizontal load to the pile and measuring the deflection.
The test is conducted by using a hydraulic jack or a reaction frame.
The lateral load test helps in determining the lateral load capacity of the pile.
The test results are used to design the foundation of the structure.
The lateral load test is important for struct...
Yes
Yes, there is an IS code for vertical load test of piles.
The relevant IS code is IS 2911 (Part 4): 2013 - 'Design and construction of pile foundations - Load test on piles'.
This code provides guidelines for conducting vertical load tests on piles to determine their load-carrying capacity and performance.
The code covers various aspects such as test setup, instrumentation, loading procedures, acceptance criteria, and ...
Vertical load test of pile is done to determine the load carrying capacity of the pile.
To ensure the pile can support the intended load
To determine the settlement of the pile under load
To verify the design assumptions
To assess the quality of the pile installation
Examples: bridge piers, high-rise buildings, transmission towers
Vertical load test is a procedure to determine the load-bearing capacity of a structure.
The test involves applying a vertical load to the structure and measuring the resulting deflection.
The load is gradually increased until the structure reaches its maximum load-bearing capacity.
The test can be performed using hydraulic jacks, weights, or other equipment.
The results of the test are used to ensure the safety and stabil...
Lateral load test is a procedure to determine the strength and stability of a structure against horizontal forces.
The test involves applying a horizontal force to the structure and measuring its response.
The force is usually applied using hydraulic jacks or a reaction frame.
The test is performed on a representative section of the structure, such as a column or a wall.
The results of the test are used to verify the desig...
SPT test is a standard penetration test used to determine the soil's resistance to penetration.
SPT test involves driving a standard sampler into the soil using a hammer of standard weight and height.
The number of blows required to drive the sampler a certain distance is recorded as the SPT N-value.
SPT test is commonly used in geotechnical engineering to determine soil properties such as shear strength and bearing capac...
MPR, WPR, and DPR are acronyms used in various fields to represent different concepts.
MPR stands for Monthly Progress Report, which is a document that provides an overview of the progress made during a specific month.
WPR stands for Weekly Progress Report, which is a document that highlights the progress made on a weekly basis.
DPR stands for Daily Progress Report, which is a document that summarizes the daily progress m...
BBS calculation is a method used to determine the reinforcement required for a pile.
BBS stands for Bar Bending Schedule.
It involves calculating the length and number of steel bars required for the pile.
Factors such as load capacity, soil type, and pile diameter are taken into consideration.
The BBS is used to ensure the pile can withstand the required load and prevent failure.
The number of tests required for a pile depends on various factors such as the type of pile, soil conditions, and project requirements.
The number of tests can range from one to several depending on the project.
Common tests for piles include static load tests, dynamic load tests, and integrity tests.
Factors such as pile length, diameter, and soil type can affect the number of tests required.
The project specifications an...
The cut off level of pile depends on various factors such as soil type, load capacity, and design requirements.
The cut off level of pile is the depth at which the pile is embedded into the ground.
It is determined by the soil type and load capacity of the ground.
The design requirements of the structure being built also play a role in determining the cut off level of pile.
For example, if the structure requires a deeper f...
The minimum distance of detume bar of pile vertical load test is typically 2.5 times the diameter of the pile.
The detume bar is used to measure the settlement of the pile during the load test.
The minimum distance is important to ensure accurate measurement of the pile settlement.
The distance is typically 2.5 times the diameter of the pile, but may vary depending on the specific test requirements.
If the distance is too ...
Dynamic load test of pile is done to assess its load carrying capacity and integrity.
To ensure the pile can withstand the expected load and prevent failure
To determine the pile's ultimate bearing capacity
To assess the pile's integrity and detect any defects or damage
To verify the design assumptions and optimize the foundation design
Examples: bridge piers, tall buildings, wind turbines, etc.
Integrity test of pile is done to ensure the pile is structurally sound and can bear the required load.
To ensure the pile is not damaged during installation
To check if the pile is free from any defects or cracks
To verify if the pile can bear the required load
To ensure the safety of the structure and its occupants
Examples: Sonic Integrity Testing, Crosshole Sonic Logging, etc.
I applied via Recruitment Consulltant and was interviewed before Apr 2022. There were 2 interview rounds.
Project life cycle can be managed by following a structured approach that includes planning, execution, monitoring, and closure.
Define project scope, objectives, and deliverables
Create a project plan with timelines, milestones, and resources
Execute the plan and monitor progress regularly
Identify and manage risks, issues, and changes
Close the project by delivering the final product and conducting a post-project review
Managing client relationships involves effective communication, understanding their needs, and delivering quality service.
Establish clear communication channels and respond promptly to their queries
Understand their needs and expectations and tailor your services accordingly
Deliver quality service and exceed their expectations
Maintain transparency and honesty in all dealings
Regularly seek feedback and take corrective ac...
I was interviewed in Sep 2021.
Google Sheets is a cloud-based spreadsheet program offered by Google as part of the Google Drive office suite.
Allows users to create and edit spreadsheets online
Offers collaboration features for real-time editing and commenting
Can import and export various file formats, including Microsoft Excel
Offers add-ons and scripts for automation and customization
Accessible from any device with internet connection
MDD & OMC are important parameters for soil compaction and moisture content.
MDD stands for Maximum Dry Density, which is the maximum density that can be achieved for a given soil compaction effort.
OMC stands for Optimum Moisture Content, which is the moisture content at which the maximum dry density can be achieved.
These parameters are important for determining the appropriate moisture content and compaction effort for...
The velocity of steel varies depending on the type and conditions.
The velocity of steel can range from 5000 to 6000 meters per second
The velocity of steel can be affected by factors such as temperature and pressure
The velocity of steel is important in industries such as construction and manufacturing
The cube test result in 7 days depends on the purpose of the test and the specific cube being tested.
The cube test can refer to various tests in different fields such as construction, engineering, and materials science.
For example, in construction, the cube test is used to determine the compressive strength of concrete cubes after 7 days of curing.
The result of the cube test can vary depending on factors such as the ty...
Interview experience
based on 17 reviews
Rating in categories
Deputy Manager
1.1k
salaries
| ₹5.8 L/yr - ₹17 L/yr |
Assistant Manager
850
salaries
| ₹5 L/yr - ₹14.8 L/yr |
Manager
405
salaries
| ₹8 L/yr - ₹22.5 L/yr |
Senior Engineer
379
salaries
| ₹3.5 L/yr - ₹11.6 L/yr |
Senior Manager
359
salaries
| ₹10.4 L/yr - ₹32.5 L/yr |
Larsen & Toubro Limited
Reliance Infrastructure
GMR Group
Hindustan Construction Company