I appeared for an interview in Mar 2025, where I was asked the following questions.
SPI (Schedule Performance Index) measures project efficiency by comparing planned progress to actual progress.
SPI = Earned Value (EV) / Planned Value (PV).
An SPI of 1 indicates the project is on schedule.
An SPI greater than 1 means the project is ahead of schedule.
An SPI less than 1 indicates the project is behind schedule.
Example: If EV is $50,000 and PV is $60,000, SPI = 50,000 / 60,000 = 0.83, indicating a delay.
Updating project progress involves tracking milestones, assessing timelines, and communicating changes effectively.
Regularly review project milestones against the schedule to identify delays.
Use project management software (e.g., MS Project, Primavera) to visualize progress.
Conduct weekly or bi-weekly status meetings with the team to gather updates.
Document any changes in scope or resources that may affect timelines.
Pr...
I applied via Referral and was interviewed in Jun 2024. There was 1 interview round.
Primavera is a project management software used for planning, scheduling, and controlling projects.
Primavera is commonly used in industries such as construction, engineering, and manufacturing.
It allows users to create project schedules, allocate resources, track progress, and analyze project performance.
Users can define activities, assign durations, set dependencies, and create critical paths.
Primavera also offers fea...
Top trending discussions
I applied via Company Website and was interviewed before Sep 2020. There was 1 interview round.
posted on 11 Apr 2021
I applied via Walk-in and was interviewed before Apr 2020. There was 1 interview round.
Manpower mobilization refers to the process of deploying and managing personnel for a specific project or task.
Identifying the required personnel for a project
Recruiting and hiring personnel
Training and orienting personnel to the project
Assigning roles and responsibilities to personnel
Managing personnel performance and productivity
Ensuring compliance with labor laws and regulations
Examples include mobilizing a construc...
Cost control in project can be achieved through effective planning, monitoring and controlling of project expenses.
Create a detailed project budget and stick to it
Track expenses regularly and adjust budget as needed
Identify and eliminate unnecessary expenses
Negotiate with vendors for better pricing
Implement cost-saving measures without compromising quality
Use project management tools to monitor expenses and progress
Reg...
Handling clients requires effective communication, understanding their needs, and providing timely solutions.
Listen actively to their concerns and requirements
Communicate clearly and professionally
Provide timely updates and solutions
Build a strong relationship based on trust and respect
Be proactive in identifying and addressing potential issues
Ensure customer satisfaction by going above and beyond expectations
Manpower mobilization flow chart involves identifying needs, planning, recruitment, training, and deployment.
Identify the need for manpower
Plan the recruitment process
Source and screen candidates
Conduct interviews and assessments
Select and hire candidates
Provide training and orientation
Deploy manpower to required locations
I applied via Job Portal and was interviewed before Dec 2021. There were 3 interview rounds.
I applied via Naukri.com and was interviewed in Aug 2023. There were 2 interview rounds.
I applied via Approached by Company and was interviewed before Nov 2022. There were 3 interview rounds.
based on 2 interviews
Interview experience
based on 2 reviews
Rating in categories
Planning Engineer
11
salaries
| ₹6.2 L/yr - ₹20.6 L/yr |
Project Engineer Mechanical
7
salaries
| ₹3.9 L/yr - ₹12.4 L/yr |
Construction Management
7
salaries
| ₹24 L/yr - ₹36.2 L/yr |
Project Engineer
6
salaries
| ₹12 L/yr - ₹12.6 L/yr |
Senior Store Keeper
6
salaries
| ₹4.1 L/yr - ₹7.5 L/yr |
AECOM
L&T Energy Hydrocarbon
Apco Infratech
Saipem